| Date |
Text |
| 2015-02-26 07:57:14 | 2/26/2015 |
| | PROJECT: BOOST MOBILE SIGN |
| | PERMIT#: 14120655 |
| | CODE: 2008 EDITION OF THE NEC, 2010 EDITION OF THE FBC |
| | ,2010 WPB AMENDMENTS TO THE FBC, CHAPTER 1, |
| | ADMINISTRATION, 2012 FBC SUPPLEMENTS. |
| | 2ND ELECTRICAL PLAN REVIEW |
| | ACTION: DENIED |
| | |
| | 1) PROVIDE ELECTRICAL PLANS AND PERMIT INDICATE |
| | COMPLIANCE WITH THE NEC ARTICLE 600 AND THE FBC CHAPTER |
| | 5 SECTION 505.2.4. SEE BELOW: |
| | |
| | 2) NEC 600.3 LISTING. |
| | ELECTRIC SIGNS, SECTION SIGNS, AND OUTLINE LIGHTING, |
| | FIXED, MOBILE, OR PORTABLE SHALL BE LISTED AND |
| | INSTALLED IN CONFORMANCE WITH THAT LISTING, UNLESS |
| | OTHERWISE APPROVED BY SPECIAL PERMISSION. |
| | |
| | 3) NEC 600.6(A)(1) |
| | EACH SIGN AND OUTLINE LIGHTING SYSTEM, OR FEEDER |
| | CIRCUIT OR BRANCH CIRCUIT SUPPLYING A SIGN OR OUT-LINE |
| | LIGHTING SYSTEM, SHALL BE CONTROLLED BY AN EXTERNALLY |
| | OPERABLE SWITCH OR CIRCUIT BREAKER THAT WILL OPEN ALL |
| | UNGROUNDED CONDUCTORS WITHIN SIGHT OF THE SIGN |
| | |
| | 4) WPB AMENDMENTS TO THE FBC 107.3.2 |
| | CONSTRUCTION DOCUMENTS SHALL BE OF SUFFICIENT CLARITY |
| | TO INDICATE THE LOCATION, NATURE AND EXTENT OF THE WORK |
| | PROPOSED AND SHOW IN DETAIL THAT IT WILL CONFORM TO THE |
| | PROVISIONS OF THIS CODE AND RELEVANT LAWS, ORDINANCES, |
| | RULES AND REGULATIONS, AS DETERMINED BY THE BUILDING |
| | OFFICIAL. PLAN SUBMITTED ARE NOT SUFFICIENT QUALITY OR |
| | SIZE TO BE LEGIBLE. |
| | |
| | 5) FBC-E 505.2.4 |
| | ALL EXTERIOR LIGHTING NOT EXEMPTED BY FBC 505.1 SHALL |
| | HAVE AUTOMATIC CONTROLS TO TURN OFF AT DAYLIGHT OR WHEN |
| | NOT REQUIRED. CONTROLS SHALL BE PHOTOSENSOR & TIME |
| | CLOCK OR ASTRONOMICAL TIME SWITCH. ALL TIME SWITCHES |
| | SHALL BE CAPABLE OF RETAINING PROGRAMING DURING A LOSS |
| | OF POWER FOR A MINIMUM OF 10 HOURS. |
| | |
| | 6) FBC WPB AMENDMENTS. SECTION 109.3 |
| | PROVIDE PROOF OF OVERALL VALUE OF THE PROJECT IS |
| | REQUIRED AND SHALL BE THE TOTAL REPLACEMENT VALUE TO |
| | INCLUDE ARCHITECTURAL DESIGN FEES, FABRICATION, |
| | STRUCTURAL, AND ELECTRICAL, PLUS OVERHEAD AND PROFIT. |
| | FINAL PERMIT VALUATION SHALL BE SET BY THE BUILDING |
| | OFFICIAL. |
| | |
| | WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE |
| | LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY |
| | RE-SUBMITTAL FORM. SEE LINK: |
| | HTTP://WPB.ORG/DEVELOPMENT/WP-CONTENT/UPLOADS/SITES/33/ |
| | 2013/09/APPLICATION_RESUBMITTAL_FORM_04132010.PDF |
| | |
| | ADDITIONALLY, IT IS REQUIRED TO INSERT THE CORRECTED |
| | PAGES INTO THE DENIED SUBMITTAL PACKAGE. VOID THE |
| | PREVIOUSLY REVIEWED SHEETS AND LEAVE FOR COMPARATIVE |
| | REVIEW. |
| | |
| | DAVID HAYES, ELECTRICAL PLANS EXAMINER, PX3421, |
| | 561-805-6717 OR [email protected] |
| | |