| Date |
Text |
| 2014-12-15 11:19:09 | ****CORRECTIONS**** |
| | |
| | SAMANTHA HILL |
| | BUILDING PLANS EXAMINER |
| | [email protected] |
| | 561-805-6724 |
| | |
| | 1. AS THE PROPOSED RENOVATION CONSTITUTES A SUBSTANTIAL |
| | IMPROVEMENT, PROVIDE A COPY OF THE ELEVATION |
| | CERTIFICATE FOR THIS STRUCTURE. THIS MAY BE SENT VIA |
| | EMAIL FOR PRELIMINARY REVIEW. |
| | |
| | BASED ON THE SITE PLAN, IT APPEARS THAT: |
| | |
| | THE HOUSE FINISHED FLOOR IS IN COMPLIANCE (OVER 7.5') |
| | |
| | NO INFORMATION PROVIDED REGARDING MECHANICAL EQUIPMENT |
| | (MUST BE OVER 7.5') |
| | |
| | THE GARAGE FLOOR IS AT 6.68'. THIS DOES NOT COMPLY WITH |
| | THE MINIMUM 7.5'). ARE FLOOD VENTS INSTALLED IN THE |
| | GARAGE? IS THE GARAGE TO BE RAISED? SHEET A2 SHOWS |
| | GARAGE ELEVATION AS 10'1" AND AS 7'. PROPOSED |
| | CONSTRUCTION NOT CLEAR. |
| | |
| | IS THE BREEZEWAY ENCLOSED? WILL THIS BE RAISED? |
| | |
| | THE ELEVATION CERTIFICATE SHOULD PROVIDE THE |
| | INFORMATION REQUIRED TO DETERMINE ACTIONS WHICH WILL BE |
| | REQUIRED FOR ISSUANCE. |
| | |
| | PLEASE PROVIDE A CURRENT ELEVATION CERTIFICATE WHICH |
| | SHOWS EXISTING CONDITIONS. |
| | |
| | THREE ADDITIONAL ELEVATION CERTIFICATES WILL BE |
| | REQUIRED: |
| | |
| | CONSTRUCTION DOCUMENTS (PLEASE PROVIDE AT THIS TIME, |
| | SHOWS ELEVATIONS PROPOSED) |
| | BUILDING UNDER CONSTRUCTION (WILL BE REQUIRED AT |
| | INSPECTION) |
| | FINISHED CONSTRUCTION (WILL BE REQUIRED PRIOR TO |
| | CERTIFICATE OF COMPLETION, AFTER FINISHED GRADE AND ALL |
| | MECHANICAL EQUIPMENT HAS BEEN INSTALLED) |
| | |
| | 2. DOCUMENTS PREPARED BY AN ARCHITECT AND SUBMITTED FOR |
| | PUBLIC RECORD ARE TO BE SIGNED, SEALED, DATED ORIGINALS |
| | FS 481. |
| | |
| | |
| | |