| 2015-06-12 12:56:29 | MECHANICAL PROVIOS: |
| | |
| | 1) SHEET M1.02 & M4.00: REVISION REQUIRED TO PROVIDE |
| | VENTILATION CALCULATIONS FOR THE CORRIDOR AND ELEVATOR |
| | LOBBY ON THE SOUTH END OF THE BUILDING, AND SHOW A |
| | MEANS OF VENTILATION ON THE PLAN.- TABLE 403..3 FMC-10 |
| | 2) M4.01: REVISION REQUIRED TO PROVIDE A VESTIBULE FOR |
| | THE MAINTENANCE ROOM PER SECTION 305.3.2 FBC-10 FUEL |
| | GAS, OR SUBMIT SPECS FOR THE HEATER SHOWING COMPLIANCE |
| | WITH SECTION 305.3.2 (EXCEPTION) FBC-10 FUEL GAS. |
| | 3) M4.01: THE L1 INTAKE OPENING, AND THE COMBUSTION AIR |
| | INTAKE FOR THE POOL HEATER MUST BE RELOCATED A MINIMUM |
| | 10' AWAY FROM THE PARKING AREA PER SECTION 401.4.1 |
| | FMC-10 MECH. |
| | 4) M4.02: THE DUCT SMOKE DETECTORS SHALL BE CONNECTED |
| | TO THE FIRE ALARM SYSTEM- SECTIONS 606.4 AND 606.4.1 |
| | FMC-10 MECH: PLEASE PROVIDE THE CORRECT NUMBER LABELS |
| | ON THE SHAFT DETAIL FOR RTU'S 2,3, & 4. |
| | 6) AC LOAD CALCULATIONS REVISONS: A) SUBMIT CALCS FOR |
| | RTU #1-5. B) THE FITNESS CENTER IS CALCULATED AT |
| | APPROXIMATELY 3-TON COOLING, HOWEVER THE EQUIPMENT |
| | SCHEDULE IS INDICATING A 5-TON SYSTEM- SHEET M1.02. |
| | 7) ENERGY CALCULATION REVISIONSS: A) AHU-6 IS LISTED AT |
| | 34.4 BTUH IN THE CALCS AND 57.5 IN THE SCHEDULE. B) |
| | AHU-4 IS LISTED AS 57.5 IN THE CALCS AND 23.4 IN THE |
| | SCHEDULE. C) AHU-4A NOT IN THE CALCS. |
| | |
| | CHRISTOPHER COLE |
| | MECHANICAL PLANS EXAMINER |
| | 561-805-6719 |