| Date |
Text |
| 2015-06-10 08:46:11 | 3RD REVIEW: FBC 2010 MECHANICAL |
| | |
| | 1) SHEET M1.02 & M4.00: PROVIDE VENTILATION |
| | CALCULATIONS FOR THE CORRIDOR AND ELEVATOR LOBBY ON THE |
| | SOUTH END OF THE BUILDING, AND SHOW A MEANS ON THE |
| | PLAN.- TABLE 403..3 FMC-10 |
| | 2) M4.01: PROVIDE A VESTIBULE FOR THE MAINTENANCE ROOM |
| | PER SECTION 305.3.2 FBC-10 FUEL GAS, OR SUBMIT SPECS |
| | FOR THE HEATER SHOWING COMPLIANCE WITH SECTION 305.3.2 |
| | (EXCEPTION) FBC-10 FUEL GAS. |
| | 3) M4.01: THE L1 INTAKE OPENING, AND THE COMBUSTION AIR |
| | INTAKE FOR THE POOL HEATER MUST BE RELOCATED A MINIMUM |
| | 10' AWAY FROM THE PARKING AREA PER SECTION 401.4.1 |
| | FMC-10 MECH. |
| | 4) M4.02: INDICATE CONTROLS OPERATION AND SUPERVISION |
| | FOR THE RTU DUCT SMOKE DETECTORS- SECTIONS 606.4 AND |
| | 606.4.1 FMC-10 MECH: NOTE THEY ARE NOT SHOWN IN THE FA |
| | SYSTEM RISER- SEE SHEET E-5.03. PLEASE PROVIDE THE |
| | CORRECT NUMBER LABELS ON THE SHAFT DETAIL FOR RTU'S |
| | 2,3, & 4. |
| | 5) M4.04 & M4.05: THE LOCATION OF THE ROOF HATCH IS NOT |
| | SHOWN. PLEASE SUBMIT A FL. PRODUCT APPROVAL OR |
| | MIAMI-DADE NOA FOR THE UNIT, AND PROVIDE DETAILS FOR |
| | THE ROOF LADDER SHOWN ON SHEET A5.00. |
| | 6) AC LOAD CALCULATIONS: A) CALCULATIONS FOR RTU'S 1-5 |
| | NOT SUBMITTED. B) THE FITNESS CENTER IS CALCULATED AT |
| | APPROXIMATELY 3-TON COOLING, HOWEVER THE EQUIPMENT |
| | SCHEDULE IS INDICATING A 5-TON SYSTEM- SHEET M1.02. |
| | 7) ENERGY CALCULATIONS: A) AHU-6 IS LISTED AT 34.4 BTUH |
| | IN THE CALCS AND 57.5 IN THE SCHEDULE. B) AHU-4 IS |
| | LISTED AS 57.5 IN THE CALCS AND 23.4 IN THE SCHEDULE. |
| | C) AHU-4A NOT IN THE CALCS. |
| | 8) PLEASE PROVIDE AN EQUIPMENT SCHEDULE FOR THE FIRE |
| | DAMPERS AND FIRE/SMOKE DAMPERS: INCLUDE MAKES AND |
| | MODELS, FIRE-RESISTANCE RATINGS. SUBMIT SPECS AND |
| | PROVIDE TYPICAL INSTALLATION DETAILS ON THE PLAN. |
| | |
| | CHRISTOPHER COLE |
| | MECHANICAL PLANS EXAMINER |
| | 561-805-6719 |