| 2015-08-17 14:04:34 | NOTE: BUILDING REVIEW MAY BE APPROVED WITH PROVISO. |
| | COMMENTS BELOW MAY BE ADDRESSED AFTER PERMIT IS ISSUED. |
| | FEES MAY APPLY. CONTRACTOR'S RESPONSE IS REQUIRED: |
| | REQUESTING PROVISO OR RE-SUBMITTING INFORMATION BELOW. |
| | |
| | 1- SIZE OF FOOTING SPECIFIED ON PLANS AND SIZE |
| | RECOMMENDED ON THE GEOTECHNICAL REPORT DON'T MATCH. |
| | REVISE AS REQUIRED TO MATCH OR ARCHITECT TO PROVIDE |
| | LETTER ACKNOWLEDGING THAT HE READ THE GEOTHECHNICAL |
| | REPORT RECOMMENDATION AND THE FOOTING SIZE HE SPECIFIED |
| | IS ADEQUATE. SEC. 107.2.1 CITY AMENDMENTS. |
| | |
| | 2- TYPICAL WALL SECTION ON SHEET A3: COORDINATE SIZE OF |
| | FOOTING TO COMPLY WITH THE CLEARANCE FOR TERMITE |
| | INSPECTION REQUIRED BY SEC. R704 AND MINIMUM FOOTING |
| | DEPTH REQUIRED BY SEC. R403.1.4. A 16" DEEP FOOTING |
| | DOESN'T PROVIDE 6" CLEARANCE AND 12" DEPTH BELOW GRADE. |
| | REVISE TYPICAL WALL SECTION, FOUNDATION PLAN AND |
| | FOOTING SCHEDULE AS REQUIRED AND COORDINATE WITH ITEM |
| | #2 ABOVE. |
| | |
| | 3- SPECIFY THE SIZE OF THE GARAGE DOOR STRUCTURAL BUCK. |
| | SEC. R301.1. |
| | |
| | 4- REVISE THE SHUTTERS INSTALLATION SCHEDULE: SHUTTER |
| | MOUNTING CONNECTION TYPE IS INCORRECT. SUBSTRATE IS |
| | CONCRETE BLOCK NOT POURED CONCRETE. CLARIFY SHUTTER |
| | MOUNTING CONNECTION AND SPECIFIC ANCHOR TYPE. |
| | |
| | 5- NEW SHEET A4: THE LEFT HAND SIDE OF THE STRUCTURAL |
| | NOTES GOT CUT OFF. PROVIDE COMPLETE DRAWING. |
| | |
| | 6- REVISE THE ENERGY CALCULATIONS: CALCULATIONS NEED TO |
| | BE DONE ON THE ACTUAL ORIENTATION OF THE BUILDING. |
| | BUILDING IS FACING A TRUE NORTH. THERE ARE NOT NORTH |
| | EAST ORIENTATION, ETC. SEC. 103.2.1.1.2 OF 2010 |
| | FBC-ENERGY CONSERVATION. |
| | |
| | IF YOU HAVE ANY QUESTIONS, PLEASE CONTACT |
| | JULIO GOMEZ |
| | COMMERCIAL COMBINATION PLANS EXAMINER |
| | DEVELOPMENT SERVICES DEPARTMENT |
| | (561)805-6712 |
| | [email protected] |