Text |
| 2014-07-07 08:47:15 | 1ST REVIEW. | | | | | | 1) THE SUBMITTAL WAS APPLIED FOR AS A REVISION BUT MUST | | | BE CHANGED TO A SEPARATE PERMIT APPLICATION. A PERMIT | | | APPLICATION BY A QUALIFIED CONTRACTOR IS REQUIRED. THE | | | APPLICATION MUST INCLUDE A VALUE FOR THE WORK IN ORDER | | | TO DETERMINE THE APPLICABLE FEES, OR AN INDICATIONTHAT | | | THE VALUE WAS PART OF THE MASTER VALUE. | | | FBC-105.3 APPLICATION FOR PERMIT. TO OBTAIN A PERMIT, | | | THE APPLICANT SHALL FIRST FILE AN APPLICATION THEREFORE | | | IN WRITING ON A FORM FURNISHED BY THE DEPARTMENT FOR | | | THAT PURPOSE. | | | | | | 2) THE ENGINEER'S SEAL UPON THE PLAN BY DONALD ARPIN | | | APPEARS TO BE A PHOTO COPY. | | | FBC-107.1 GENERAL - FAC 61G1-16.004 - | | | | | | STEVEN KENNEDY, CBO | | | CHIEF PLANS EXAMINER | | | (561) 805-6710 | | | [email protected] | | | | | | |
|