| 2014-08-02 08:54:25 | 2010 FBC |
| | |
| | DENIED BY BUILDING |
| | |
| | 1) AN ELEVATION CERTIFICATE WILL BE REQUIRED PRIOR TO |
| | FINAL INSPECTION SHOWING THAT THE NEW CONSTRUCTION AND |
| | EQUIPMENT IS IN COMPLIANCE WITH THE REQUIRED BASE FLOOD |
| | ELEVATION INCLUDING THE 6 IN FREE-BOARD. CITY |
| | AMENDMENTS 107.2.1 |
| | |
| | 2) SUBMIT TWO SETS OF AN ACCURATELY COMPLETED |
| | RESIDENTIAL BUILDING FORM 402 OR 405 SHOWING THAT THE |
| | RENOVATION AND ADDITION COMPLY WITH THE 2010 FBC ENERGY |
| | CONSERVATION. |
| | |
| | 3) THE PRODUCT APPROVALS ARE REQUIRED TO BE APPROVED IN |
| | WRITING BY THE DESIGNER OF RECORD. CITY AMENDMENTS |
| | 107.3.4.1 |
| | |
| | 4) SPECIFY WHICH ONE OF THE APPROVED ASSEMBLIES LISTED |
| | IN THE CERTAINTEED BUR PRODUCT APPROVAL (NOA NO |
| | 13-0204.14) WILL BE INSTALLED. SUBMIT TWO SETS OF |
| | SIGNED AND SEALED RAS 117 CALCULATIONS FOR ENHANCED |
| | FASTENING THAT IS REQUIRED FOR THE INCREASED PRESSURES |
| | OF THE PERIMETER AND CORNER AREAS FOR A 170 MPH WIND |
| | SPEED AND EXPOSURE 'D'. FBCR 301.1 |
| | |
| | 5) SHOP DRAWINGS FOR THE SPIRAL STAIRS THAT HAVE BEEN |
| | REVIEWED AND ACCEPTED BY THE DESIGNER OF RECORD ARE |
| | REQUIRED TO BE SUBMITTED FOR REVIEW PRIOR TO |
| | INSTALLATION. FBCR 301.1 & CITY AMENDMENTS 107.2.1 |
| | |
| | 6) THE VALUE FOR THE SCOPE OF WORK APPEARS TO BE LOW. |
| | PLEASE PROVIDE A COST BREAKDOWN OR A COPY OF A SIGNED |
| | CONTRACT. CITY AMENDMENTS 109.3 |
| | |
| | 7) IN ORDER TO SPEED THE PLAN REVIEW TIMES, PLEASE |
| | SUBMIT A RESPONSE LETTER THAT INDICATES HOW EACH OF THE |
| | REVIEW COMMENTS HAS BEEN ADDRESSED. |
| | |
| | ROBERT MCDOUGAL |
| | BLDG. PLAN REVIEW |
| | (561)805-6714 |
| | [email protected] |
| | |
| | |