| Date |
Text |
| 2014-04-26 14:26:22 | ****CORRECTIONS**** |
| | ****REVISED 6/14 TO REMOVE REFERENCE TO FBC 2010 |
| | RESIDENTIAL 301.2.1.1 AND CHANGE CODE REFERENCE TO |
| | 301.1.**** |
| | |
| | SAMANTHA HILL |
| | BUILDING PLANS EXAMINER |
| | [email protected] |
| | 561-805-6724 |
| | |
| | 1. FBC 107.2.1, ALL INFORMATINO, DRAWINGS, |
| | SPECIFICATIONS AND ACCOMPANYING DATA SHALL BEAR THE |
| | NAME AND SIGNATURE OF THE PERSON RESPONSIBLE FOR THE |
| | DESIGN. |
| | |
| | 2. SHEET 2.0, PAVER WORK PROPOSED WHICH IS NOT LOCATED |
| | WITHIN THE BOUNDARIES OF THE PROPERTY FOR THIS PERMIT |
| | APPLICATION. WORK ON ANOTHER PARCEL WILL REQUIRE A |
| | SEPARATE PERMIT. |
| | |
| | 3. DRIVEWAY/PAVER WORK PROPOSED REQUIRES A SEPARATE |
| | PERMIT, FBC 107. PERMIT #14040299 FOR PAVERS WAS |
| | SUBMITTED. IT IS SUGGESTED THAT, WHEN RESUBMITTING, |
| | PLANS RELATING TO THE PAVER WORK BE RESUBMITTED |
| | SEPARATELY FROM THE PATIO/PORCH PERMIT. THIS WILL HELP |
| | TO EXPEDITE BOTH PERMITS. |
| | |
| | 4. COVER SHEET STATES THIS IS A LEVEL 2 ALTERATION; SEE |
| | FBC 2010 EXISTING BUILDING 202 AND REVISE. |
| | |
| | 5. FBC 2010 RESIDENTIAL 301.1, PLAN STATES THAT THIS |
| | DESIGN IS IN ACCORDANCE WITH ASCE7-10. IF PLANS ARE NOT |
| | PREPARED BY A DESIGN PROFESSIONAL, PROVIDE CALCULATIONS |
| | FOR STRUCTURAL ELEMENTS (CONNECTORS, FOOTING SIZES, |
| | COLUMN SIZES, SPANS, ETC). |
| | |
| | 6. ZONING HAS REDLINED SHEETS 2.0, 5.0, 9.0, AND OTHER |
| | SHEETS. PLEASE INCORPORATE THE CHANGES INTO THE PLAN, |
| | ALL SHEETS, AS THERE IS A REDUCTION IN SIZE AND AFFECTS |
| | OTHER SHEETS, FBC 107. |
| | |
| | 7. FLORIDA STATE OR LOCAL PRODUCT APPROVAL REQUIRED FOR |
| | THE SHINGLE ROOF, FBC 2010 RESIDENTIAL 301, FAC9N-3. |
| | |
| | 8. FOR THE FLAT ROOF, PROVIDE A CURRENT PRODUCT |
| | APPROVAL. THE NOA SUBMITTED HAS BEEN SUPERSEDED. THE |
| | CURRENT VERSION OF THIS APPROVAL IS AVAILABLE AT WWW.MI |
| | AMIDADE.GOV/BUILDING/LIBRARY/PRODUCTCONTROL/NOA/1207161 |
| | 8.PDF. PROVIDE TWO SETS. |
| | |
| | 9. FOR THE FLAT ROOF, INDICATE WHICH APPROVED ASSEMBLY |
| | IS PROPOSED. |
| | |
| | 10. FOR THE FLAT ROOF, PROVIDE ENGINEERING FOR THE |
| | ENHANCED FASTENING REQUIRED. |
| | |
| | |