| 2014-04-24 16:01:59 | MECHANICAL REVISION SECOND CHECKLIST. |
| | CODE: 2010 FBC. |
| | |
| | |
| | 1- EQUIPMENT SIZING CALCULATIONS SUBMITTED: |
| | |
| | A) CALCULATIONS CAN NOT BE DONE FOR WORST CASE |
| | SCENARIO. SEC. 403.6 OF 2010 FBC-ENERGY CONSERVATION. |
| | REVISE CALCULATIONS AS REQUIRED TO MATCH THE ACTUAL |
| | BUILDING ORIENTATION. |
| | ***NOTE: COORDINATE EQUIPMENT OF REVISED CALCULATIONS |
| | WITH EQUIPMENT SHOWN ON THE A/C PLAN. |
| | |
| | B) ADDRESS SHOWN ON THE EQUIPMENT SIZING CALCULATIONS |
| | IS INCORRECT. THE CORRECT ADDRESS IS 210 ALHAMBRA PL, |
| | NOT 201 ALHAMBRA PL. REVISE AS REQUIRED. SEC. 103.2.2 |
| | OF 2010 FBC-ENERGY CONSERVATION. |
| | |
| | C) COOLING AND HEATING INFORMATION SHOWN ON THE |
| | EQUIPMENT SIZING CALCULATIONS DON'T MATCH THE |
| | INFORMATION SHOWN ON THE ENERGY CALCULATIONS SUBMITTED. |
| | REVISE AS REQUIRED TO MATCH. SEC. 103.2.2 OF 2010 |
| | FBC-ENERGY CONSERVATION. |
| | |
| | 2- A/C CONTRACTOR RESPONSIBLE FOR THE DESIGN OF THE A/C |
| | PLAN SUBMITTED TO PROVIDE NAME AND SIGNATURE AS |
| | REQUIRED BY SEC. 107.2.1 OF CITY AMENDMENTS TO FBC. |
| | |
| | |
| | 3- ENERGY CALCULATIONS SUBMITTED: |
| | |
| | A) CORRECT ADDRESS IS 210 ALHAMBRA PL, NOT 201 |
| | ALHAMBRA. AND COMPLETE ALL THE INFORMATION ON TOP OF |
| | FORM, INCLUDING THE OWNER'S NAME, BUILDER'S NAME, |
| | PERMITTING OFFICE, ETC. REVISE AS REQUIRED. SEC. |
| | 103.2.2 OF 2010 FBC-ENERGY CONSERVATION. |
| | |
| | B) COOLING AND HEATING INFORMATION DON'T MATCH WITH THE |
| | HEATING AND COOLING INFORMATION SHOWN ON THE EQUIPMENT |
| | SIZING CALCULATIONS. REVISE AS REQUIRED TO MATCH. SEC. |
| | 103.2.2 OF 2010 FBC-ENERGY CONSERVATION. |
| | |
| | C) OWNER/AGENT TO SIGN AND DATE BOTTOM OF FORM. SEC. |
| | 103.2.3.2 OF 2010 FBC-ENERGY CONSERVATION. |
| | |
| | |
| | |