| 2014-10-27 11:45:26 | 1) SUBMIT MANUFACTURER'S SPECIFICATIONS FOR ALL GAS |
| | EQUIPMENT / APPLIANCES. EQUIPMENT / APPLIANCES SHALL BE |
| | LISTED AND LABELED PER THE 2010 FL. GAS CODE SEC. |
| | 301.3. |
| | 2) THE GAS PIPING IS UNDERSIZED FOR THE TOTAL LOAD |
| | CONNECTED THERETO. THE MAXIMUM LOAD FOR A 1" LINE AT 50 |
| | FT. WITH 552,000 BTU LOAD IS 480,000 BTU'S. THE MINIMUM |
| | SIZE SHALL BE 1 1/4" PER TABLE 402.4 (26 ) OF THE 2010 |
| | FGC. |
| | 3) THE SEDIMENT TRAPS SHALL BE INSTALLED IN ACCORDANCE |
| | WITH THE 2010 FGC SEC.408.4.408.4 SEDIMENT TRAP. |
| | WHERE A SEDIMENT TRAP IS NOT INCORPORATED AS PART OF |
| | THE APPLIANCE , A SEDIMENT TRAP SHALL BE INSTALLED |
| | DOWNSTREAM OF THE APPLIANCE SHUTOFF VALVE AS CLOSE TO |
| | THE INLET OF THE APPLIANCE AS PRACTICAL. THE SEDIMENT |
| | TRAP SHALL BE EITHER A TEE FITTING HAVING A CAPPED |
| | NIPPLE OF ANY LENGTH INSTALLED VERTICALLY IN THE |
| | BOTTOMMOST OPENING OF THE TEE OR OTHER DEVICE APPROVED |
| | AS AN EFFECTIVE SEDIMENT TRAP. ILLUMINATING APPLIANCES, |
| | RANGES, CLOTHES DRYERS AND OUTDOOR GRILLS NEED NOT BE |
| | SO EQUIPPED. |
| | 4) SUBMIT DETAILS FOR THE ANCHORING OF THE LP TANKS. |
| | TANKS SHALL BE ANCHORED TO WITHSTAND THE WIND LOADS PER |
| | THE 2010 FBC SEC.1609. |
| | 5) THE LOCATION OF THE LP TANKS IN RELATION TO BUILDING |
| | OPENINGS LOCATED BELOW THE RELIEF VALVE OF THE TANKS |
| | AND THE DISTANCE AWAY FROM ANY SOURCE OF IGNITION SHALL |
| | COMPLY W/NFPA 58, SEC.6.3.7 (1) AND (2). SHOW THE |
| | DISTANCE OGF THE LP TANKS FROM THE DOOR AND ANY SOURCE |
| | OF IGNITION. |
| | |
| | PLUMBING PLAN REVIEW |
| | TIM LARGE |
| | CHIEF PLUMBING INSPECTOR |
| | 561-805-6692 |
| | [email protected] |
| | |
| | |
| 2014-10-15 11:39:47 | NEW SHEET P-4 SUBMITTED. JG. |