Plan Review Notes
Plan Review Notes For Permit 13060900
Permit Number 13060900
Review Stop B
Sequence Number 1
Notes
Date Text
2013-06-27 08:39:27****CORRECTIONS****
 SAMANTHA HILL, BUILDING PLANS EXAMINER
 561-805-6724 [email protected]
 FBC FLORIDA BUILDING CODE 2010
 FBC R FLORIDA BUILDING CODE 2010 RESIDENTIAL
  
 1. FBC 1207.2, FLOOR/CEILING ASSEMBLIES SEPARATING
 DWELLING UNITS FROM EACH OTHER OR FROM PUBLIC OR
 SERVICE AREAS SHALL HAVE A SOUND TRANSMISSION CLASS
 (STC) OF NOT LESS THAN 50 (45 IF FIELD TESTED) FOR AIR
 BORNE NOISE WHEN TESTED IN ACCORDANCE WITH ASTM E 90.
  
 A TEST REPORT WAS PROVIDED WHICH TESTED WITH A
 SUSPENDED GYPSUM CEILING. PROVIDE INFORMATION REGARDING
 THE SUSPENDED GYPSUM CEILING WHICH IS REQUIRED TO BE A
 PART OF THIS ASSEMBLY (IN THE UNIT UNDERNEATH) AND
 PROVIDE INFORMATION AS TO HOW THIS CONDITION WILL NOT
 CHANGE.
  
 2. FBC 1207.3, FLOOR/CEILING ASSEMBLIES BETWEEN
 DWELLING UNITS OR BETWEEN A DWELLING UNIT AND A PUBLIC
 OR SERVICE AREA WITHIN THE STRUCTURE SHALL HAVE AN
 IMPACT INSULATION CLASS (IIC) RATING OF NOT LESS THAN
 50 (45 IF FIELD TESTED) WHEN TESTED IN ACCORDANCE WITH
 ASTM E 492.
  
 A TEST REPORT WAS PROVIDED, BUT THE PRODUCT WAS TESTED
 TO ASTM E 2179 RATHER THAN 492.
  
 SEE ALSO FBC 104.11 ALTERNATIVE MATERIALS, DESIGN AND
 METHODS OF CONSTRUCTION AND EQUIPMENT. THE PROVISIONS
 OF THIS CODE ARE NOT INTENDED TO PREVENT THE
 INSTALLATION OF ANY MATERIAL OR TO PROHIBIT ANY DESIGN
 OR METHOD OF CONSTRUCTION NOT SPECIFICALLY PRESCRIBED
 BY THIS CODE, PROVIDED THAT ANY SUCH ALTERNAT IVE HAS
 BEEN APPROVED. AN ALTERNATIVE MATERIAL, DESIGN OR
 METHOD OF CONSTRUCTION SHALL BE APPROVED WHERE THE
 BUILDING OFFICIAL FINDS THAT THE PROPOSED DESIGN IS
 SATISFACTORY AND COMPLIES WITH THE INTENT OF THE
 PROVISIONS OF THIS CODE, AND THAT THE MATERIAL, METHOD
 OR WORK OFFERED IS, FOR THE PURPOSE INTENDED, AT LEAST
 THE EQUIVALENT OF THAT PRESCRIBED IN THIS CODE IN
 QUALITY, STRENGTH, EFFECTIVENESS, FIRE RESISTANCE,
 DURABILITY AND SAFETY. WHEN ALTERNATE LIFE SAFETY
 SYSTEMS ARE DESIGNED, THE SFPE ENGINEERING GUIDE TO
 PERFORMANCE-BASED FIRE PROTECTION ANALYSIS AND DESIGN
 OF BUILDINGS, OR OTHER METHODS APPROVED BY THE BUILDING
 OFFICIAL MAY BE USED. THE BUILDING OFFICIAL SHALL
 REQUIRE THAT SUFFICIENT EVIDENCE OR PROOF BE SUBMITTED
 TO SUBSTANTIATE ANY CLAIM MADE REGARDING THE
 ALTERNATIVE.
  
 104.11.1 RESEARCH REPORTS. SUPPORTING DATA, WHERE
 NECESSARY TO ASSIST IN THE APPROVAL OF MATERIALS OR
 ASSEMBLIES NOT SPECIFICALLY PROVIDED FOR IN THIS CODE,
 SHALL CONSIST OF VALID RESEARCH REPORTS FROM APPROVED
 SOURCES.
  
 104.11.2 TESTS. WHENEVER THERE IS INSUFFICIENT EVIDENCE
 OF COMPLIANCE WITH THE PROVISIONS OF THIS CODE, OR
 EVIDENCE THAT A MATERIAL OR METHOD DOES NOT CONFORM TO
 THE REQUIREMENTS OF THIS
 CODE, OR IN ORDER TO SUBSTANTIATE CLAIMS FOR
 ALTERNATIVE MATERIALS OR METHODS, THE BUILDING OFFICIAL
 SHALL HAVE THE AUTHORITY TO REQUIRE TESTS AS EVIDENCE
 OF COMPLIANCE TO BE MADE AT NO
 EXPENSE TO THE JURISDICTION. TEST METHODS SHALL BE AS
 SPECIFIED IN THIS CODE OR BY OTHER RECOGNIZED TEST
 STANDARDS. IN THE ABSENCE OF RECOGNIZED AND ACCEPTED
 TEST METHODS, THE
 BUILDING OFFICIAL SHALL APPROVE THE TESTING PROCEDURES.
 TESTS SHALL BE PERFORMED BY AN APPROVED AGENCY. REPORTS
 OF SUCH TESTS SHALL BE RETAINED BY THE BUILDING
 OFFICIAL FOR THE PERIOD REQUIRED
 FOR RETENTION OF PUBLIC RECORDS.
  


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved