| Date |
Text |
| 2013-06-24 16:21:01 | FAILED |
| | |
| | PLEASE PROVIDE WRITTEN RESPONSES. |
| | |
| | 1) PURSUANT TO THE PALM BEACH COUNTY TRAFFIC |
| | PERFORMANCE STANDARDS REVIEW LETTER ISSUED ON SEPTEMBER |
| | 17, 2009, NO BUILDING PERMITS SHALL BE ISSUED BY THE |
| | CITY AFTER DECEMBER 31, 2012. AN EXTENSION OF THIS |
| | DEADLINE MAY BE ISSUED BY PALM BEACH COUNTY. A MINOR |
| | PLANNED DEVELOPMENT AMENDMENT IS REQUIRED TO UPDATE THE |
| | THE COUNTY BUILD OUT DATE. |
| | |
| | 2) PURSUANT TO RESOLUTION NO. 288-11, A CONSTRUCTION |
| | SITE SECURITY AND MANAGEMENT PLAN SHALL BE SUBMITTED TO |
| | THE CITY'S POLICE DEPARTMENT CRIME PREVENTION THROUGH |
| | ENVIRONMENTAL DESIGN ("CPTED") OFFICIAL AND APPROVED |
| | PRIOR TO THE ISSUANCE OF THE BUILDING PERMIT. |
| | |
| | I) THE APPLICANT, AFTER SITE CLEARING AND PLACEMENT OF |
| | CONSTRUCTION TRAILERS, SHALL INSTITUTE SECURITY |
| | MEASURES TO REDUCE OR ELIMINATE OPPORTUNITIES FOR |
| | THEFT. THE MANAGEMENT PLAN SHALL INCLUDE, BUT NOT TO BE |
| | LIMITED TO, TEMPORARY LIGHTING, SECURITY PERSONNEL, |
| | VEHICLE BARRIERS, CONSTRUCTION/VISITOR PASS, |
| | REDUCE/MINIMIZE ENTRY/EXIT POINTS, ENCOURAGE |
| | SUBCONTRACTORS TO SECURE MACHINERY AND TOOLS AT END OF |
| | WORK DAY AND/OR ANY OTHER MEASURE DEEMED APPROPRIATE TO |
| | PROVIDE A SAFE AND SECURE WORKING ENVIRONMENT. |
| | II) THE SECURITY MANAGEMENT PLAN SHALL BE MAINTAINED |
| | THROUGHOUT THE CONSTRUCTION PHASE OF THE PROJECT. |
| | NON-COMPLIANCE WITH THE APPROVED PLAN SHALL RESULT IN A |
| | STOP-WORK ORDER FOR THE ENTIRE PLANNED DEVELOPMENT. |
| | |
| | 3) SHEET A-1 DOES NOT SHOW THE FOUNDATION PLANTING |
| | AREAS AT FIVE (5) FEET WIDE UNDER THE AREAS COVERED BY |
| | THE AWNINGS. |
| | |
| | 4) IN ACCORDANCE WITH RESOLUTION NO. 288-11, ALL ROOF |
| | MOUNTED AIR CONDITIONING, MECHANICAL EQUIPMENT, |
| | SATELLITE DISHES, GENERATORS, ETC., SHALL BE SCREENED |
| | FROM VIEW ON ALL SIDES BY A VISUALLY OPAQUE BARRIER |
| | CONSISTENT WITH THE COLOR, CHARACTER AND ARCHITECTURAL |
| | STYLE OF THE STRUCTURES OR EQUIVALENT LANDSCAPE |
| | MATERIAL. THE HEIGHT OF THE OPAQUE BARRIER SHALL BE AS |
| | REQUIRED TO PROVIDE AMPLE SCREENING. PROVIDE |
| | VERIFICATION THAT THE ROOFTOP MECHANICAL EQUIPMENT WILL |
| | BE SCREENED AS REQUIRED BY THE RESOLUTION FOR THE |
| | SPECIFIC EQUIPMENT PROPOSED FOR INSTALLATION (EX. LINE |
| | OF SIGHT OR ELEVATIONS WITH THE EQUIPMENT). |
| | |
| | 5) THE APPROVED ELEVATIONS FOR BUILDING 7 HAVE CHANGED. |
| | THE BUILDING IS TALLER AND THE REQUIRED DOORS ON THE |
| | NORTH FACADE HAVE BEEN RELOCATED (2) AND REMOVED (1) |
| | AND ADDITIONAL WINDOWS WERE ADDED ON THE WESTERN |
| | FACADE. REVISED ELEVATIONS ARE REQUIRED AS PART OF A |
| | MINOR PLANNED DEVELOPMENT AMENDMENT TO SHOW THE ACTUAL |
| | CONDITIONS. THE SITE AND LANDSCAPE PLANS DO NOT MATCH |
| | THE PROPOSED DOOR MODIFICATIONS. |
| | |
| | 6) THE LANDSCAPE REQUIRES A SEPARATE PERMIT APPLICATION |
| | FOR EACH PARCEL (TRACT A & TRACT F) ON WHICH WORK IS |
| | BEING DONE. THE SAME 2 COPIES OF THE LANDSCAPE PLAN MAY |
| | BE USED FOR BOTH APPLICATIONS (SUBJECT TO CONCURRENT |
| | SUBMITTAL). A COST ESTIMATE IS REQUIRED WITH THE |
| | SUBMITTAL. |
| | |
| | 7) THE PLANS TO CONSTRUCT THE PARKING REQUIRED PRIOR TO |
| | THE C.O. OF THE LAST PHASE I BUILDING (GENERALLY ALONG |
| | THE SOUTH ACCESS DRIVE) SHALL BE INCLUDED ON A PARKING |
| | LOT STRIPING PERMIT FOR TRACT A PRIOR TO ZONING |
| | APPROVAL OF THIS PERMIT. STRIPING DETAILS FOR ALL |
| | CONDITIONS SHALL BE PROVIDED. THE PARKING SHALL BE |
| | INSTALLED PRIOR TO THE C.O. OF THIS BUILDING OR |
| | BUILDING 5/6, WHICHEVER OCCURS LAST. |
| | |
| | 8) SIGNAGE AND AWNINGS REQUIRE SEPARATE PERMITS WITH |
| | PLANS. |
| | |
| | CONTACT ERIC SCHNEIDER @ (561) 822-1446. |
| | |