Text |
| 2013-05-30 11:48:17 | 2010 FBC |
| | |
| | DENIED BY BUILDING |
| | |
| | 1) PROVIDE PARAPET WALL FRAMING DETAILS. SPECIFY STUD |
| | SPACING, ANCHORS AND STRAPPING NEEDED TO PROVIDE A |
| | CONTINUOUS LOAD PATH. FBC R301.1 AND R601.2 |
| | |
| | 2) SPECIFY THE ROOF AND WALL SHEATHING FASTENING |
| | REQUIREMENTS ON THE PLANS. FBC R803.2.3.1 AND R604.3 |
| | |
| | 3) SHOW COMPLIANCE WITH FBC R703.2 FOR THE REQUIRED |
| | WATER RESISTIVE BARRIER AND R703.6.3 FOR THE REQUIRED |
| | BOND BREAK BETWEEN THE WATER RESISTIVE BARRIER AND THE |
| | STUCCO. |
| | |
| | 4) SHOW COMPLIANCE WITH FBC R806.1 FOR ROOF |
| | VENTILATION. |
| | |
| | 5) THE MINIMUM ROOF SLOPE REQUIRED FOR MODIFIED BITUMEN |
| | ROOFING IS 1/4" PER FOOT PER FBC R905.11. PLEASE |
| | CORRECT PLANS. |
| | |
| | 6) THE DOWNSPOUTS FOR THE ROOF SCUPPERS ARE REQUIRED TO |
| | DISCHARGE A MINIMUM OF 1 FOOT FROM THE EXTERIOR WALLS. |
| | FBC R318.6 |
| | |
| | 7) THE ROOF PLAN ON A-01 HAS ID MARKS 'A' AND 'D' WHICH |
| | APPEAR TO BE FOR THE TRUSS ANCHORS. THE ANCHOR SCHEDULE |
| | HAS MARKS 'A' AND 'B' FOR THE TRUSS ANCHORS. PLEASE |
| | CLARIFY. THE TRUSS ANCHORS THAT ARE SPECIFIED IN THE |
| | ANCHOR SCHEDULE DO NOT APPEAR TO BE THE CORRECT ONES |
| | FOR THE APPLICATION. PLEASE REVIEW. CITY AMENDMENTS |
| | 107.2.1 |
| | |
| | 8) SUBMIT TWO COPIES OF PRODUCT APPROVALS AS REQUIRED |
| | BY DCA RULE 9N-3 FOR THE ROOF COVERING MATERIAL |
| | (INCLUDE RAS 117 CALCULATIONS FOR ENHANCED FASTENING), |
| | THE TRUSS ANCHORS AND OTHER STRAPS OR CONNECTORS. |
| | |
| | 9) THE CC-816 COLUMN IS SPECIFIED AS 16" X 16" ON A-02 |
| | AND IN THE SCHEDULE ON SHEET A-00 AN 8" X 16" COLUMN IS |
| | SHOWN FOR CC-816. PLEASE CLARIFY. CITY AMENDMENTS |
| | 107.2.1 |
| | |
| | ROBERT MCDOUGAL |
| | BLDG. PLAN REVIEW |
| | (561)805-6714 |
| | [email protected] |