| 2013-04-15 10:41:49 | THE ELECTRICAL SERVICE MAINS MUST BE GROUPED IN ONE |
| | LOCATION. THE PRINCIPAL SAFETY RULE FOR ELECTRICAL |
| | SERVICES REQUIRES A BUILDING OR STRUCTURE TO HAVE ONE |
| | POINT OF SERVICE. NEC 230.2, 230.71, 230.72 |
| | |
| | INDICATE THE FAULT CURRENT CAPACITY REQUIRED FOR THE |
| | ELECTRICAL SERVICE AND SWITCH GEAR. NEC 110.9, 110.10 |
| | |
| | PROVIDE PROPER DOWNSTREAM RATINGS OF EQUIPMENT IN |
| | ACCORDANCE WITH THE FAULT CURRENT AND/OR PROVIDE PROPER |
| | SERIES RATINGS VALUES 240.4 (B) (C) (F), 240.12 |
| | |
| | AN INTERSYSTEM BONDING STRIP IS REQUIRED AT THE MAIN |
| | SERVICE GROUND. NEC 250.94 |
| | |
| | PROVIDE A SAFETY LABELING SCHEDULE FOR FLASH PROTECTION |
| | AND FOR THE PANEL BOARDS AND MAIN DISCONNECTING MEANS. |
| | NEC 110.22, 110.16, 110.22 |
| | |
| | GROUND FAULT PROTECTION EQUIPMENT (GFPE) IS REQUIRED |
| | FOR THE NEW ELECTRIC SERVICE. NEC 230.95, 240.13 |
| | |
| | PROVIDE AND ILLUSTRATE THE SAFE WORKING CLEARANCES AND |
| | DEDICATED WORKING SPACE AT ALL ELECTRICAL PANEL BOARDS |
| | AND TRANSFORMERS. NEC 110.26, 240.24 |
| | |
| | EQUIPMENT GROUNDING CONDUCTORS IN PARALLEL TO BE FULL |
| | SIZED 250.122 (F) |
| | |
| | HOW WILL EXISTING LIGHTING, 120V AND 240V EQUIPMENT BE |
| | MAINTAINED? PLAN INDICATES THIS EQUIPMENT IS TO REFED |
| | ?IN FUTURE? AND NOT AT THIS TIME. |
| | |
| | REVIEW INCOMPLETE BASED ON MISSING INFORMATION |
| | |
| | CONTRACTOR CALLED |
| | DOUG HARVEY [email protected] 561-805-6740 |
| | |