| Plan Review Notes For Permit 13040311 |
| Permit Number |
13040311 |
|
| Review Stop |
B |
| Sequence Number |
1 |
|
| Notes |
| Date |
Text |
| 2013-04-11 16:34:00 | REVIEWING DEMO APPLICATION SHOWING PHASE 1 AND PHASE 2. | | | CALLED CONTRACTOR WITH QUESTIONS AND SPOKE WITH GREG | | | CELENTANO. AFTER DISCUSSING RELEASES NEEDED AND HIS | | | CHALLENGE OF KEEPING THE BUSINESS OPEN AT THE SAME TIME | | | AS DEMO WIOULD PROCEED, DECIDED THAT HE WILL TALK WITH | | | ENGINEERING FIRST. THAT AN ENGINEERING PERMIT MIGHT BE | | | MORE BENEFICIAL AT THIS TIME AND POSSIBLY HOLD OFF ON | | | THE DEMO PERMIT AND INCLUDE IT WITH THE BUILDING | | | PERMIT. | | | PUTTING THE APPLICATION IN SMALL FILE CABINET UNDER "A" | | | FOR AHRENS COMPANIES. |
|