| Plan Review Notes For Permit 13010358 |
| Permit Number |
13010358 |
|
| Review Stop |
B |
| Sequence Number |
4 |
|
| Notes |
| Date |
Text |
| 2013-06-04 11:13:45 | BUILDING REVIEW APPROVED WITH PROVISO: | | | | | | 1- ENGINEER OF RECORD TO REVISE ROOF TILE FASTENING | | | INFORMATION ON PRODUCT APPROVAL TABLE ON SHEET A2.0 TO | | | MATCH PRODUCT APPROVAL SUBMITTED. THE DESIGN PRESSURES | | | AND PADDY SIZE DON'T MATCH PRODUCT APPROVAL SUBMITTED. | | | | | | 2- PROVIDE BUILDING INSPECTOR WITH COMPLETE TRUSS | | | PACKAGE WHEN REQUESTING ROOF FRAMING INSPECTION. TRUSS | | | PACKAGE TO HAVE: A)TRUSS ENGINEER'S ORIGINAL SEAL AND | | | SIGNATURE. B) ENGINEER TITLE BLOCK WITH NAME OF | | | PROJECT, NAME OF ENGINEER, ADDRESS, LICENSE NUMBER AND | | | DATE OF SIGNING AND SEALING DRAWINGS . | | | |
|