| 2012-09-27 11:23:58 | RESIDENTIAL (R3) ADDITION BUILDING REVIEW COMMENTS. |
| | CODE: 2010 FBC. |
| | |
| | 1- PROVIDE ENERGY CALCULATIONS. MAKE SURE ALL THE |
| | INFORMATION IS COMPLETED AND SIGNED BY ALL PARTIES AT |
| | THE BOTTOM OF THE FORM. SEC. 103.2.1 OF 2010 FBC-ENERGY |
| | CONSERVATION. |
| | |
| | 2- BRING PLANS TO PALM BEACH COUNTY (2300 N. JOG RD.) |
| | TO VERIFY IF IMPACT FEES ARE DUE. BRING BACK STAMPED |
| | PLANS AND COPY OF PAID RECEIPT IF FEES ARE DUE. COUNTY |
| | IMPACT FEE ORDINANCE OF THE UNIFIED LAND DEVELOPMENT |
| | CODE. |
| | |
| | 3- STORM PANELS NOA 10-0222.03 SUBMITTED: PROVIDE |
| | COMPLETE INSTALLATION SCHEDULE TO VERIFY COMPLIANCE |
| | WITH THE DESIGN PRESSURES OF SEC. R301.2.1.4.3 OF 2010 |
| | FBC-RESIDENTIAL. CLEARLY IDENTIFY SPECIFIC SHUTTERS |
| | MOUNTING CONDITION AND ANCHOR TYPE AND SPACING TO BE |
| | USED. SEC. 107.2.1 CITY AMENDMENTS TO FBC. |
| | ***NOTE: CLARIFY WHY SUBMITTING STORM SHUTTERS PRODUCT |
| | APPROVAL. ARE ALL THE WINDOWS AND DOORS IMPACT |
| | RESISTANT? |
| | |
| | 4- FLAT ROOF NOA 12-0227.18 SUBMITTED. A) SELECTED |
| | ASSEMBLY ON PAGE 6 OF 7 IS FOR AN INSULATED ASSEMBLY. |
| | ARCHITECTURAL PLANS DON'T SPECIFY INSULATED ASSEMBLY. |
| | COORDINATE WITH ARCHITECT AND REVISE AS REQUIRED. |
| | |
| | B) PROVIDE RAS 117 CALCULATIONS AS REQUIRED BY GENERAL |
| | LIMITATION #7 ON LAST PAGE OF NOA SUBMITTED. |
| | |
| | 5- PROVIDE PRODUCT APPROVAL (2 COPIES) AS REQUIRED BY |
| | DCA RULE 9N-3 FOR FRENCH DOORS AS SHOWN ON PLANS. |
| | INCLUDING FRENCH DOORS WITH SIDELITES AS SHOWN ON |
| | PLANS. |
| | |
| | 6- DESIGNER OF RECORD TO REVIEW AND APPROVE IN WRITING |
| | (NOT SIGNING AND SEALING) ALL PRODUCT APPROVALS AS |
| | REQUIRED BY SEC. 107.3.4.1 OF CITY AMENDMENTS. |
| | |
| | 7- SHEET A3: PROPOSED 2ND FLOOR PLAN SHOWS NEW ATTIC |
| | ACCESS. IT LOOKS LIKE IT'S NOT READILY ACCESSIBLE AS |
| | REQUIRED BY SEC. R807. REVISE AS REQUIRED AND PROVIDE |
| | DIMENSIONS. |
| | ***NOTE: THERE IS A NOTE THAT THE AHU IS LOCATED HERE. |
| | VERIFY THAT AIR HANDLER UNIT WILL BE OK IN THIS |
| | LOCATION. CHECK ACCESS AND REQUIRED CLEARANCES TO |
| | SERVICE THE EQUIPMENT. |
| | |
| | 8- PROVIDE SOIL TEST REPORT AS REQUIRED BY SEC. R401.4. |
| | |
| | 9- PROVIDE COMPLETE SPECIFICATIONS FOR THE ICYNENE |
| | INSULATION SPECIFIED ON PLANS. SEC. 107.2.1 CITY |
| | AMENDMENTS. |
| | |
| | 10- A) ENGINEER TO REVISE ALL THE ROOF SHEATHING |
| | DETAILS AND SPECIFICATIONS. NEED TO SPECIFY MIN. 8D |
| | RING SHANK NAILS (NOT 10D) AS REQUIRED BY SEC. |
| | R803.2.3.1 AND ALSO NEED TO SPECIFY NAILS AT 4"O.C. IN |
| | ROOF ZONE #3. |
| | |
| | B) ARCHITECT TO REVISE ROOF SHEATHING NAILING |
| | SPECIFICATIONS SHOWN ON ALL THE WALL SECTIONS AND |
| | DETAILS TO MATCH REVISED ENGINEER SPECIFICATIONS. |
| | COORDINATE WITH ITEM 10(A) ABOVE. SEC. 107.2.1 CITY |
| | AMENDMENTS. |
| | |
| | IF YOU HAVE ANY QUESTIONS, PLEASE CALL |
| | JULIO GOMEZ |
| | COMMERCIAL COMBINATION PLANS EXAMINER |
| | (561)805-6712 |