| Plan Review Notes For Permit 12080534 |
| Permit Number |
12080534 |
|
| Review Stop |
M |
| Sequence Number |
1 |
|
| Notes |
| Date |
Text |
| 2012-08-21 09:04:22 | 2010 FBC | | | | | | DENIED BY MECHANICAL | | | | | | 1) SUBMIT TWO SETS OF ENERGY CALCULATIONS AND EQUIPMENT | | | SIZING CALCULATIONS.FBC ENERGY CONSERVATION CHAPTER 4 | | | AND FBCR M1401.3 | | | | | | 2) THE TRANSFER DUCTS FOR NEW BEDROOM #2 AND THE NEW | | | MASTER BEDROOM ARE NOT CORRECT. THE PLAN SHOWS THE | | | RETURN DUCTS TIED BETWEEN THE TWO ROOMS. IN ORDER TO BE | | | CODE COMPLIANT, THEY NEED TO TRANSFER THE AIR FROM EACH | | | ROOM TO THE COMMON HALL OR BE TIED DIRECTLY INTO THE | | | RETURN AIR AS REQUIRED BY FBCR M1602.4. | | | | | | 3) SPECIFY THE EQUIPMENT, THE SEER AND THE LOADS IN THE | | | EQUIPMENT SCHEDULE ON SHEET 5.1. FBC M1401.3 | | | | | | ROBERT MCDOUGAL | | | BLDG. PLAN REVIEW | | | (561)805-6714 | | | [email protected] |
|