| 2012-07-23 09:31:25 | ****CORRECTIONS**** |
| | SAMANTHA HILL, BUILDING PLANS EXAMINER |
| | 561-805-6724 [email protected] |
| | FBC FLORIDA BUILDING CODE 2010 |
| | FBC R FLORIDA BUILDING CODE 2010 RESIDENTIAL |
| | |
| | 1. IN ORDER TO FACILITATE INSPECTIONS AND PLAN REVIEW, |
| | PLEASE COMPLETE THE INSTALLATION SCHEDULE. ANCHOR |
| | SPACING, DESIGN PRESSURE COLUMNS WERE LEFT BLANK. |
| | ANOTHER SHEET STATES THAT THIS PROJECT IS DESIGNED TO |
| | -66PSF, BUT ANCHOR SPACING PROPOSED DOES NOT COMPLY |
| | (SEE OTHER COMMENTS). THERE ARE TOO MANY OPENINGS TO |
| | PROVIDE A GENERIC STATEMENT REGARDING SPACING; |
| | INSTALLATION PROPOSED IS TO BE REVIEWED FOR COMPLIANCE |
| | WITH FBC RESIDENTIAL 301.1, RESISTANCE TO WIND LOADS. |
| | |
| | 2. MANY ITEMS WERE HIGHLIGHTED ON THE PRODUCT APPROVAL; |
| | MULTIPLE FASTENERS, FASTENING METHODS, DESIGN |
| | PRESSURES, EDGE DISTANCE, SUBSTRATE. PLEASE ONLY NOTE |
| | ITEMS APPLICABLE TO THIS PROJECT IF YOU WISH TO USE |
| | HIGHLIGHTING OR CIRCLING AS A METHOD TO ASSIST WITH |
| | PLAN REVIEW AND INSPECTIONS. |
| | |
| | 3. HORIZONTAL INSTALLATIONS TYPICALLY SHOULD USE THE |
| | HOLLOW BLOCK CHART (SEE SHEET 4) AS THEY ARE FILLED |
| | CELLS RATHER THAN FORMED AND POURED CONCRETE. EITHER |
| | PROVIDE EVIDENCE THAT THE SUBSTRATE IS FORMED AND |
| | POURED AT SIDES OF EACH OPENING, OR USE THE ANCHOR |
| | SPACING FOR HOLLOW BLOCK, FBC 301.1. |
| | |