| Date |
Text |
| 2012-06-22 15:48:29 | RESIDENTIAL (R3) ADDITION SECOND BUILDING REVIEW |
| | CHECKLIST. |
| | 2010 FBC. |
| | |
| | 1- WALL SECTION: |
| | A) REVISE R-VALUE INSULATION SHOWN ON THE WALL SECTION |
| | TO MATCH INFORMATION GIVEN ON THE ENERGY CALCULATIONS. |
| | REQUIRED BY TABLE 402.1.1 OF 2010 FBC-ENERGY |
| | CONSERVATION. |
| | |
| | B) R-30 BATT INSULATION DOESN'T FIT ON 2X8 ROOF |
| | RAFTERS. REVISE AS REQUIRED. NEED R-30 PER TABLE |
| | 402.1.1. |
| | |
| | C) FOOTING SHALL BE 12" MIN. BELOW GRADE AS REQUIRED BY |
| | SEC. R403.1.4. REPEAT COMMENT. NOT ADDRESSED. REVISE AS |
| | REQUIRED. |
| | |
| | D) COORDINATE TYPE OF ROOFING SYSTEM TO BE INSTALLED |
| | WITH PRODUCT APPROVAL SUBMITTED. SEE APPROVED FLAT ROOF |
| | SYSTEM SELECTED ON NOA SUBMITTED AND REVISE AS |
| | REQUIRED. |
| | |
| | |
| | 2- PROVIDE PRODUCT APPROVAL (2 COPIES) AS REQUIRED BY |
| | DCA RULE 9N-3 FOR: |
| | A) FLAT ROOF ASSEMBLY. NOA 08-0226.06 SUBMITTED WAS |
| | SUPERSEDED BY MIAMI-DADE. VISIT THE MIAMI-DADE WEBSITE |
| | AND DOWNLOAD CURRENT NOA. |
| | |
| | ***NOTE: PROVIDE SIGNED AND SEALED RAS 117 CALCULATIONS |
| | AS REQUIRED BY GENERAL LIMITATION # 7 ON LAST PAGE OF |
| | NOA SUBMITTED. ENGINEER TO COORDINATE RAS 117 |
| | CALCULATIONS WITH REVISED NOA. |
| | |
| | 3- ENGINEER OF RECORD TO REVIEW AND APPROVE IN WRITING |
| | (NOT SIGNING AND SEALING) NEW PRODUCT APPROVAL AS |
| | REQUIRED BY SEC. 107.3.4.1 CITY AMENDMENTS TO FBC. |
| | |
| | 4- NEED SEPARATE PERMITS FOR ELECTRICAL, MECHANICAL, |
| | PLUMBING, ROOFING. OWNER BUILDER CAN SIGN ON THE PERMIT |
| | APPLICATION FOR THESE SUBPERMITS OR CONTRACTORS MAY |
| | APPLY FOR THEIR OWN SUBPERMITS. INDICATE WHICH OPTION |
| | IS GOING TO BE. |
| | |
| | IF YOU HAVE ANY QUESTIONS, PLEASE CALL |
| | JULIO GOMEZ |
| | COMMERCIAL COMBINATION PLANS EXAMINER |
| | (561)805-6712 |