| Plan Review Notes For Permit 12020426 |
| Permit Number |
12020426 |
|
| Review Stop |
B |
| Sequence Number |
2 |
|
| Notes |
| Date |
Text |
| 2012-02-23 09:48:34 | RE-ROOF SECOND REVIEW COMMENTS: | | | | | | 1- ENGINEER TO REVISE RAS 117 CALCULATIONS. NEED TO | | | REFER TO NEW MANUFACTURER'S NOA APPROVED ASSEMBLY TO BE | | | INSTALLED. INFORMATION SUBMITTED DOESN'T MATCH SELECTED | | | ASSEMBLY. REVISE SPECIFIC MATERIALS TO BE USED, REVISE | | | FASTENER SPACING AND RAS 117 CALCULATIONS AS REQUIRED. | | | ALSO, SECOND PAGE IS REFERRING TO THE GAF NOA. NOA | | | SUBMITTED IS FOR A POLYGLASS PRODUCT. REVISE AS | | | REQUIRED. | | | | | | IF YOU HAVE ANY QUESTIONS, PLEASE CALL | | | JULIO GOMEZ | | | COMMERCIAL COMBINATION PLANS EXAMINER | | | (561)805-6712 |
|