2012-02-27 17:47:56PASSED W/PROVISOS
  
 1) REPEAT COMMENT - PRIOR TO THE 1ST INSPECTION THE
 FOLLOWING SHALL BE SUBMITTED: A LANDSCAPE PERMIT FOR
 THE WORK ON TRACT C-2 AND A PARKING LOT AND DRIVEWAY
 STRIPING PERMIT FOR THE WORK ON TRACTS C-1 AND C-2 TO
 THE BUILDING DIVISION AND A PAVING PERMIT FOR TRACTS
 C-1 AND C-2 TO THE ENGINEERING SERVICES DEPARTMENT.
  
 2) ADDITIONAL SEPARATE PERMITS ARE REQUIRED FOR THE
 FENCE, SIGNAGE, DUMPSTER ENCLOSURE, AND EXTERIOR
 LIGHTING. PLEASE BE AWARE THAT THE WORK ON TRACT C-1
 REQUIRES A SEPARATE PERMIT FROM THE WORK ON C-2. PLEASE
 NOTE THAT THE ENTIRE C-2 DRIVEWAY WILL NEED TO BE SHOWN
 ON THE APPLICABLE PERMIT APPLICATION(S).
  
 3) PER RESOLUTION NO. 287-11, THE INTERNAL, TWO-WAY
 DRIVE SHALL BE CONSTRUCTED AND PASS FINAL INSPECTION
 PRIOR TO THE ISSUANCE OF THE C.O FOR THE DAY CARE
 FACILITY.
  
 4) PER RESOLUTION NO. 287-11, PRIOR TO THE ISSUANCE OF
 THE C.O. FOR THE DAY CARD FACILITY, PHASE III OF TRACT
 C OAKTON COMMONS CPD SHALL BE GRADED, TILLED AND
 PLANTED IN ACCORDANCE WITH SECTION 94-450 OF THE ZONING
 AND LAND DEVELOPMENT REGULATIONS.
  
 CONTACT ERIC SCHNEIDER @ (561) 822-1446.