2011-11-14 10:34:45MECHANICAL REVIEW APPROVED WITH PROVISO:
  
 1- REVISE EQUIPMENT SIZING CALCULATIONS:
 A) EQUIPMENT SIZING CALCULATIONS WERE DONE FOR WORST
 CASE SCENARIO. EQUIPMENT SIZING CAN'T BE DONE FOR WORST
 CASE. ACTUAL HOUSE DIRECTIONAL ORIENTATION NEED TO BE
 USED FOR THE CALCULATIONS. REVISE CALCULATIONS AND
 EQUIPMENT SIZING AS REQUIRED. SEC. N1107.AB.1.
  
 B) REVISE DOOR TYPE AND CEILING VENTILATION AND R VALUE
 TO MATCH REVISED ENERGY CALCULATIONS.
  
 C) REVISE EQUIPMENT SPECIFICATIONS ON A/C PLAN TO
 REFLECT REVISED CALCULATIONS.