| | A. SITE APPLICATION FOR STORMWATER RUNOFF |
| | ANY SITE DEVELOPMENT PROJECT, PROPOSED ADJACENT TO THE |
| | INTRA-COASTAL, WILL BE REQUIRED TO UTILIZE |
| | APPROVED BEST MANAGEMENT PRACTICES (BMP?S) FOR THE |
| | DETENTION AND TREATMENT OF STORMWATER RUNOFF. |
| | IN ACCORDANCE WITH STATE AND LOCAL STORMWATER |
| | MANAGEMENT POLICY, THE SITE DEVELOPER IS REQUIRED TO |
| | PREPARE TWO (2) STORMWATER RELATED PLANS. |
| | A1 THE STORMWATER POLLUTION PREVENTION PLAN IS REQUIRED |
| | TO |
| | ADDRESS STORMWATER RELATED ISSUES SUCH AS DUST CONTROL, |
| | RUNOFF, AND EROSION CONTROL DURING THE |
| | CONSTRUCTION PHASE OF THE PROJECT. |
| | A2 A STORMWATER MANAGEMENT PLAN IS PREPARED FOR THE |
| | FINAL SITE |
| | CONFIGURATION AND ADDRESSES PERMANENT SITE STORMWATER |
| | RUNOFF AND FLOOD PREVENTION. AS PART OF BOTH PLANS, |
| | PROTECTION MEASURES WILL BE EMPLOYED TO PREVENT RUNOFF |
| | TO THE INTRA-COASTAL OR THE ADJACENT PRIVATE OR CITY |
| | STORMWATER |
| | SYSTEM. |
| | SITE STORMWATER MANAGEMENT SHALL INCLUDE WATER |
| | QUALITY/QUANTITY PROVISIONS, SURFACE DRAINAGE DESIGN |
| | AND RELATED CALCULATIONS AND SHALL CONFORM TO THE SFWMD |
| | METHODOLOGY AS SHOWN ON VOLUME IV "PERMITTING |
| | INFORMATION MANUAL," MOST CURRENT EDITION. |
| | |
| | B SHOW ALL SITE DRAINAGE ELEMENTS AND IT'S |
| | CONFIGURATION. |
| | |
| | C PROVIDE CROSS ACCESS AGREEMENT TO EXISTING/PROPOSED |
| | PARKING BACKING AND ACCESSING THRU PROPERTY ON THE |
| | NORTH. |
| | |
| | MANUEL JULIAN GONZALEZ |
| | CSD ENGINEERING REVIEW |
| | 401 CLEMATIS STREET, |
| | WEST PALM BEACH, FL 33401 |
| | (MAILING ADDRESS: P.O. BOX 3366, ZIP 33402) |
| | MAIN PHONE: (561) 822-1200 |
| | DIRECT: (561) 494-1085 |
| | FAX: (561) 494-1116 |
| | MOBILE: (561) 644-7301 |
| | EMAIL: [email protected] |
| | WWW.WPB.ORG/ENGINEERING |
| | |
| | |
| | |