| Date |
Text |
| 2011-08-24 13:37:06 | FAILED - UPDATED ON 8/24 AFTER DISCUSSION WITH BRIAN |
| | MOREE. |
| | |
| | |
| | 1) UPDATED COMMENT - THE TREES IDENTIFIED FOR REMOVAL |
| | ARE EXOTICS AND MAY BE REMOVED AS PART OF THE PROJECT. |
| | |
| | 2) UPDATED COMMENT - THE SABAL PALM LOCATED BEHIND THE |
| | BUILDING APPEARS TO BE IMPACTED BY THE RECONSTRUCTION |
| | WORK AND IS NOT IDENTIFIED ON THE PLANS. IF THIS TREE |
| | IS IMPACTED, THEN IT SHALL BE RELOCATED TO WITHIN THE |
| | PROJECT BOUNDARIES. |
| | |
| | 3) UPDATED COMMENT - THE 36 INCH DIAMETER TREE THAT IS |
| | PROPOSED TO REMAIN APPEARS TO BE LOCATED IN AN AREA |
| | THAT WILL BE REGARDED ON THE NEW 3:1 SLOPE AND THUS THE |
| | GRADE AT THE TREE WILL LOWER APPROXIMATELY 1 FOOT. THIS |
| | GRADE CHANGE WOULD EXPOSE THE TREE ROOTS CAUSING DAMAGE |
| | TO THE TREE. WHAT IS PROPOSAL TO PROTECT THIS TREE IN |
| | PLACE? NOTE THAT THIS IS AN EXOTIC AND SHOULD BE |
| | REMOVED NOT PRESERVED IN PLACE. |
| | |
| | 4) THE REMOVAL OF ANY TREES, EXCLUDING EXOTICS, |
| | REQUIRES THE APPROVAL OF A TREE ALTERATION PERMIT BY |
| | THE PLANNING AND ZONING DEPARTMENT. NO TREE ALTERATION |
| | PERMIT HAS BEEN FILE |
| | |
| | 5) ON SHEET C2-4, THE LABEL FOR THE "TOP OF BANK TO BE |
| | RELOCATED" SOUTH OF CAROLINE STREET IS NOT DESIGNATING |
| | THE CORRECT LOCATION. |
| | |
| | CONTACT ERIC SCHNEIDER @ (561) 822-1446. |
| 2011-08-16 10:30:37 | FAILED |
| | |
| | 1) THE INFORMATION SHEETS CALL OUT THE REMOVAL OF |
| | TREES, INCLUDING A SIGNIFICANT ONE WITH A 54 INCH |
| | DIAMETER TRUNK. IF THESE ARE NOT EXOTICS, THEN THEY |
| | SHALL BE REPLACED WITHIN THE LIMITS OF WORK OR IN THE |
| | NEAR VICINITY, TO MAINTAIN THE CITY'S TREE CANOPY AND |
| | TO PROVIDE SCREENING OF THE RAILROAD AND INDUSTRIAL |
| | PROPERTIES FOR THE RESIDENTIAL DISTRICT SOUTH AND EAST |
| | OF THE SITE AND FROM PARKER AVENUE, IN ACCORDANCE WITH |
| | THE CITY'S ZONING AND LAND DEVELOPMENT REGULATIONS. |
| | |
| | 2) THE AERIAL SHOWS ADDITIONAL EXISTING TREES NOT |
| | INDICATED ON THE PLANS THAT APPEAR TO BE IMPACTED BY |
| | THE RECONSTRUCTION WORK - BEHIND THE BUILDING AND ALONG |
| | THE CAROLINE STREET CROSSING OF THE CANAL (VERIFIED BY |
| | A FIELD VISIT). |
| | |
| | 3) THE 36 INCH DIAMETER TREE THAT IS PROPOSED TO REMAIN |
| | APPEARS TO BE LOCATED IN AN AREA THAT WILL BE REGARDED |
| | ON THE NEW 3:1 SLOPE AND THUS THE GRADE AT THE TREE |
| | WILL LOWER APPROXIMATELY 1 FOOT. THIS GRADE CHANGE |
| | WOULD EXPOSE THE TREE ROOTS CAUSING DAMAGE TO THE TREE. |
| | WHAT IS PROPOSAL TO PROTECT THIS TREE IN PLACE? |
| | |
| | 4) THE REMOVAL OF ANY TREES, EXCLUDING EXOTICS, |
| | REQUIRES THE APPROVAL OF A TREE ALTERATION PERMIT BY |
| | THE PLANNING AND ZONING DEPARTMENT. NO TREE ALTERATION |
| | PERMIT HAS BEEN FILE |
| | |
| | 5) ON SHEET C2-4, THE LABEL FOR THE "TOP OF BANK TO BE |
| | RELOCATED" SOUTH OF CAROLINE STREET IS NOT DESIGNATING |
| | THE CORRECT LOCATION. |
| | |
| | CONTACT ERIC SCHNEIDER @ (561) 822-1446. |