| Date |
Text |
| 2010-06-09 14:42:09 | PLUMBING REVIEW |
| | DENIED: |
| | |
| | SHEETS A-1 & A-2: |
| | WATER CLOSETS IN STALLS IN ACCESSIBLE STALLS SHALL |
| | COMPLY WITH FIGURE 30E |
| | FBC 2007 11-4.1.3(11) TOILET FACILITIES. IF TOILET |
| | ROOMS ARE PROVIDED, THEN EACH PUBLIC AND COMMON USE |
| | TOILET ROOM SHALL COMPLY WITH SECTION 11-4.22. |
| | WATER CLOSETS IN ACCESSIBLE STALLS SHALL COMPLY WITH |
| | FIGURE 30E |
| | |
| | SHEET P-1 |
| | 1. FBC 2004 WPB AMENDMENTS106.3.5.1.3 : DOMESTIC WATER |
| | RISER DIAGRAM REQUIRED. |
| | |
| | 2. A VENT IS REQUIRED BETWEEN THE 2 SHOWERS- FBC 2007 |
| | PLUMBING 901.2.1 VENTING REQUIRED. EVERY TRAP AND |
| | TRAPPED FIXTURE SHALL BE VENTED IN ACCORDANCE WITH ONE |
| | OF THE VENTING METHODS SPECIFIED IN THIS CHAPTER. |
| | |
| | 3. THE VERTICAL DRY VENT BETWEEN THE SHOWERS MAY SERVE |
| | AS THE CURCUIT VENT FOR THE 4 WATER CLOSETS ON THE |
| | SECOND FLOOR |
| | 911.2 VENT CONNECTION. THE CIRCUIT VENT CONNECTION |
| | SHALL BE LOCATED BETWEEN THE TWO MOST UPSTREAM FIXTURE |
| | DRAINS. THE VENT SHALL CONNECT TO THE HORIZONTAL BRANCH |
| | AND SHALL BE INSTALLED IN ACCORDANCE WITH SECTION 905. |
| | THE CIRCUIT VENT PIPE SHALL NOT RECEIVE THE DISCHARGE |
| | OF ANY SOIL OR WASTE. |
| | |
| | 4. A URINAL ON THE 2ND FLOOR IS LABELED AS SINK. |
| | |
| | 5. THE SOIL STACK SERVING THE 2ND FLOOR REQUIRES A |
| | CLEANOUT. |
| | |
| | 6. 911.3 THE WASTE FROM THE 2ND FLOOR IS NOT PERMITTED |
| | TO FLOW THROUGH THE 1ST FLOOR CURCUIT VENT. ATTACH THE |
| | 2ND FLOOR DOWNSTREAM OF THE 1ST WATER CLOSET ON THE 1ST |
| | FLOOR. |
| | |
| | 7. A DRY VERTICAL CURCUIT VENT IS REQUIERED BETWEEN THE |
| | TWO MOST UPSTREAM WATER CLOSETS ON THE FIRST FLOOR. |
| | |
| | 8. 20 FIXTURE UNITS ARE MAXIMUM FOR A 3" BRANCH. 4" |
| | PIPE IS REQUIRED UP TO THE BRANCHES BEFORE THE WATER |
| | CLOSETS ON THE SECOND FLOOR. |
| | |
| | REVIEW BY LARRY WAGNER |
| | CHIEF PLUMBING INSPECTOR |
| | (561) 805-6692 |
| | FAX (561) 653-2692 |
| | E-MAIL [email protected] |
| | |
| | |