| Date |
Text |
| 2010-01-11 18:08:34 | REVIEW #: 1ST |
| | ACTION: DENIED |
| | |
| | FBC 2007 CODE FAMILY W/ 2009 SUPPLEMENTS |
| | FBC CH.1 AS AMENDED BY THE CITY OF WEST PALM BEACH |
| | |
| | 1. PAGE M-3 SHOWS DUCT SMOKE DETECTOR INSTALLED ON THE |
| | RETURN DUCT WHILE PACKAGE UNIT SCHEDULE CALLS FOR |
| | DETECTOR IN THE SUPPLY. SMOKE DETECTOR SHALL BE |
| | INSTALLED ON THE SUPPLY DUCT IN ACCORDANCE WITH FBC-M |
| | 606.2.1. COORDINATE FLOOR PLAN AND SCHEDULE TO SHOW THE |
| | CORRECT LOCATION (SUPPLY). |
| | |
| | 2. ENGINEERING BUSINESS LICENSE NUMBER (CERTIFICATE OF |
| | AUTHORIZATION) SHALL APPEAR IN THE TITLE BLOCK IN |
| | ACCORDANCE WITH FFAC RULE 61G15-23.002. SIMILAR |
| | REQUIREMENTS EXIST FOR THE ARCHITECTURAL BUSINESS. |
| | |
| | 3. PLAN SHOWS PACKAGE UNIT AND DUCTWORK LOCATED |
| | OUTDOORS. NO INFORMATION WAS PROVIDED REGARDING OUTDOOR |
| | INSTALLATIONS AND WIND RESISTANCE. OUTDOOR APPLIANCES |
| | AND DUCTWORK SHALL BE DEIGNED AND INSTALLED FOR WIND |
| | RESISTANCE IN ACCORDANCE WITH FBC-M 301.12. PROVIDE |
| | MANUFACTURER'S DATA FOR THE WIND RESISTANCE CABILITIES |
| | OF THE PACKAGE UNIT WITH ENGINEERED INSTALLATION |
| | DETATIL FOR THE PACKAGE UNIT AND OUTDOOR DUCTWORK. |
| | |
| | 4. PAGE M-1 MECHANICAL NOTE #7 CALLS FOR CONDENSATE TO |
| | BE DISCHARGED TO THE NEAREST DRAIN. CONDENSATE SHALL |
| | NOT DISCHARGE TO THE SANITARY SEWER SYSTEM PER CITY |
| | ORDINANCE. CONDENSATE SHALL DISCHARGE TO AN APPROVED |
| | LOCATION (SUCH AS A PERVIOUS AREA AT LEAST 12" FROM THE |
| | BUILDING) IN ACCORDANCE WITH FBC-M 307.2.1. |
| | |
| | 5. MECHANICAL NOTES AND OUTSIDE AIR SCHEDULE REFERENCE |
| | THE INTERNATIONAL CODES AND GEORGIA AMENDMENTS. PLEASE |
| | CORRECT ALL CODE REFERENCES TO THE 2007 FLORIDA |
| | BUILDING CODE WITH 2009 SUPPLEMENTS, WHICH IS THE CODE |
| | IN EFFECT IN FLORIDA AS OF MARCH 1, 2009. |
| | |
| | 6. FAN SCHEDULE NOTE #4 CALLS FOR "INLINE" EF-2 TO BE |
| | MOUNTED ON A ROOF CURB WHILE FLOOR PLAN SHOWS THE FAN |
| | INSIDE THE BUILDING. PLEASE CLARIFY. AN OUTDOOR FAN |
| | WILL BE SUBJECT TO THE WIND RESISTANCE REQUIREMENTS AS |
| | STATED IN COMMENT #3 ABOVE. |
| | |
| | 7. PACKAGE UNIT SCEDULE, VAV SCHEDULE AND FLOOR PLANS |
| | DO NOT CORRESPOND. SEE EXAMPLES. |
| | |
| | EXAMPLE: TOTAL MAX CFM FOR ALL VAV SYSTEMS IS |
| | SIGNIFICANTLY LESS THAN THE 6000 BEING PROVIDED BY THE |
| | PACKAGE SYSTEM. |
| | EXAMPLE: VAV SCHEDULE GIVES A MAX CFM OF 900 FOR VAV-1 |
| | WHILE THE FLOOR PLAN CALLS FOR 1900 CFM. |
| | |
| | THESE ARE EXAMPLES OF DISCREPANCIES AND NOT AN |
| | EXHAUSTIVE LIST. COORDINATE VOLUMES AND SIZES OF ALL |
| | EQUIPMENT AND AIR DISTRIBUTION COMPONENTS TO SHOW THE |
| | REQUIRED AIRFLOWS IN ACCORDANCE WITH FBC-M 603.1. |
| | |
| | 8. OUTSIDE AIR INTAKE ON THE PACKAGE UNIT SHALL BE |
| | EQUIPPED WITH A MOTORIZED VOLUME DAMPER WITH SHUTOFF |
| | DAMPER CONTROLS IN ACCORDANCE WITH FBC-B 13-407.AB.3.3. |
| | |
| | 9. ISOLATION ROOM 111 DOES NOT SHOW ANY MEANS FOR |
| | RETURN AIR. BALANCED RETURN AIR WITH MINIMAL PRESSURE |
| | DIFFERENTIALS IS REQUIRED. SHOW HOW BALANCED RETURN IS |
| | TO BE ACHIEVED IN THIS ROOM IN ACCORDANCE WITH FBC-M |
| | 601.4. |
| | |
| | IF YOU HAVE ANY QUESTIONS PLEASE CONTACT: |
| | RONALD J. REGUEIRO |
| | 561.805.6719 |
| | [email protected] |