| Date |
Text |
| 2009-12-30 10:18:55 | FORMAL SUBMITTAL ACCEPTED AND PASSED |
| | |
| | PLEASE PROVIDE THE FOLLOWING INFORMATION REQUIRED FOR |
| | SITE DEVELOPMENT APPROVAL PRIOR TO COMMENCEMENT OF SITE |
| | WORK: |
| | |
| | 1. A COPY OF PERMIT ISSUED BY SOUTH FLORIDA WATER |
| | MANAGEMENT DISTRICT (SFWMD) AND |
| | |
| | 2. COPY OF GEOTECHNICAL REPORT INCLUDING STORM WATER |
| | QUALITY CALCULATIONS AND |
| | |
| | 3. FDEP NOTICE OF INTENT (NOI) FORM 62-621.300(4)(B) |
| | AND |
| | |
| | 4. APPROVED MATERIALS LIST (AML) PER CWPB ENGINEERING |
| | SERVICES AND SHOP DRAWINGS |
| | |
| | 5. EROSION CONTROL AND LAND STABILIZATION BOND PER |
| | ORDINANCE 4060-07 AS IT PERTAINS TO THE EPA'S STORM |
| | WATER POLLUTION PREVENTION PLAN'S (SWPPP) GUIDELINES. |
| | THE BOND AMOUNT SHALL BE AT A RATE OF 110% OF THE TOTAL |
| | OF THE SITE DEVELOPMENT PORTION OF THE CERTIFIED COST |
| | ESTIMATE PROVIDED BY THE PROJECT CIVIL ENGINEER. |
| | |
| | TYPE OF SURETY BONDS ACCEPTED ARE A.) LETTER OF CREDIT |
| | B.) BOND ISSUED BY A FLORIDA CERTIFIED SURETY COMPANY |
| | C.) CERTIFIED BANK OR FINANCIAL INSTITUTION CHECK. |
| | |
| | THESE ITEMS ARE REQUIRED PRIOR TO THE TIME OF A |
| | SCHEDULED AND CONFIRMED PRECONSTRUCTION MEETING WITH |
| | ENGINEERING SERVICES AND CONTINGENT UPON APPROVAL OF |
| | COMMENCEMENT OF ANY SITE DEVELOPMENT WORK. |
| | |
| | PLEASE ADDRESS ANY QUESTIONS TO THE PLAN REVIEWER |
| | BELOW: |
| | |
| | EMERY P. FABIAN |
| | ENGINEERING PROJECT COORDINATOR |
| | ENGINEERING SERVICES DEPARTMENT |
| | 401 CLEMATIS STREET, 4TH FLOOR |
| | WEST PALM BEACH, FL 33401 |
| | PHONE: 561-822-1200 |
| | FAX: 561-494-1116 |
| | EMAIL: [email protected] |