| Date |
Text |
| 2009-07-06 15:01:04 | REVIEW #: 1ST |
| | ACTION: DENIED |
| | |
| | FBC 2007 CODE FAMILY W/ 2009 SUPPLEMENTS |
| | FBC CH.1 AS AMENDED BY THE CITY OF WEST PALM BEACH |
| | |
| | 1. THE SYSTEM SHALL BE PROVIDED WITH DUCT SMOKE |
| | DETECTOR IN ACCORDANCE WITH FBC-M 606.2.2.1. CONTROLS |
| | AND OPERATION SHALL COMPLY WITH FBC-M 606.3 AND 606.4. |
| | |
| | 2. SHOW LOCATION OF BATHROOM EXHAUST TERMINATIONS IN |
| | ACCORDANCE WITH FBC-M 401.4 AND FBC-M 501.2. |
| | |
| | 3. THE SPACE APPEARS TO BE DESIGNED WITH THE CEILING TO |
| | SERVE AS A RETURN AIR PLENUM. CEILING MOUNTED EXHAUST |
| | FANS WOULD RESULT IN POSITIVE PRESSURE EXHAUST DUCTS |
| | PASSING THROUGH THE RETURN AIR PLENUM. EXHAUST DUCTS |
| | UNDER POSITIVE PRESSURE SHALL NOT PASS THROUGH THE |
| | PLENUM IN ACCORDANCE WITH FBC-M 601.5. |
| | |
| | 4. THE VENTILATION SCHEDULE INCLUDED IN THE COOLING |
| | LOAD CALCULATIONS CALL FOR A MINIMUM OF 50 CFM OF |
| | EXHAUST IN THE COPY ROOM. NO SUCH EXHAUST IS SHOWN ON |
| | THE PLANS. PLEASE COORDINATE PLANS WITH THE VENTILATION |
| | SCHEDULE. |
| | |
| | 5. THE MECHANICAL PLANS SUBMITTED WERE DESIGNED BY AN |
| | AIR CONDITIONING CONTRACTOR. THE CONTRACTOR MAY ONLY |
| | ACT AS THE DESIGNER OF THIS SYSTEM IF THEY ARE ALSO THE |
| | INSTALLING CONTRACTOR. THIS REVIEW WILL REMAIN IN FAIL |
| | STATUS PENDING RECEIPT OF A PERMIT APPLICATION FOR THIS |
| | SCOPE OF WORK FROM NORTH COUNTY COOLING IN ACCORDANCE |
| | WITH FS 471.003 |
| | |
| | IF YOU HAVE ANY QUESTIONS PLEASE CONTACT: |
| | RONALD J. REGUEIRO |
| | 561.805.6719 |
| | [email protected] |