| 2009-09-18 14:18:56 | ** TEMPORARY FAILED REVIEW ** |
| | |
| | 1) NOTE: REVIEW IS IN TEMPORARY FAILED STATUS. THE |
| | SUBMITTED REVISED ENERGY CALCULATIONS WERE NOT SEALED |
| | WITH REQUIRED RAISED SEAL PER FAC 61G15-23.002, |
| | FS471.025. ALL COPIES OF PLANS, SUBMITTED SUPPORTING |
| | DOCUMENTS WHICH ARE DONE BY THE ENGINEER ARE REQUIRED |
| | TO MEET SECTIONS AS NOTED. THIS INCLUDES |
| | OWNERS/CONTRACTORS SETS OF PLANS. |
| | CALLED CONTRACTOR AND LEFT MESSAGE AS THE SHEET 3 OF 8 |
| | WHICH WAS SIGNED AND DATED BY THE ENGINEER MAY BE |
| | DROPPED BY THE OFFICE TO PLACE IN SUBMITTED |
| | CALCULATIONS. ONLY THE RAISED SEAL DID NOT GET DONE ON |
| | SHEET. |
| | ** RULES FROM THE ENGINEERING BOARD ARE MORE |
| | RESTRICTIVE THAN THE ARCHITECTS BOARD WHICH ONLY |
| | REQUIRES FILE SET TO BE DONE THE SAME. |
| | |
| | |
| | 2) NOTE: A COLOR PHOTO-COPY WAS MADE OF SHEET C-2 WHICH |
| | IS NOT PERMITTED. THIS IS A COLOR PHOTO-COPY OF PLANS |
| | WHICH WERE SIGNED, DATED AND SEALED BY DESIGN |
| | PROFESSIONAL. |
| | DESIGNER OF RECORD MAY COME INTO OFFICE, RE-SIGN, DATED |
| | AND SEAL SHEETS. |
| | FAC 61G15-23.002, FS 471.025 |
| | |
| | 3) NOTE: IMPACT FEE REVIEW HAS BEEN PLACED IN FAILED |
| | STATUS. THIS WAS NOT DONE BY BUILDING REVIEWER EVEN |
| | THOUGH NOTED IN SYSTEM. |
| | |
| | IF THERE ARE ANY QUESTIONS; OR IF COMMENTS ARE NOT |
| | TYPED IN A CLEAR MANNER PLEASE DO NOT HESITATE TO |
| | CONTACT THIS REVIEWER. |
| | |
| | DEWEY PALMER |
| | ELECTRICAL PLAN REVIEW II |
| | CONSTRUCTION SERVICES DEPARTMENT |
| | CITY OF WEST PALM BEACH |
| | 561-805-6717 |
| | [email protected] |
| | |