| Date |
Text |
| 2009-07-08 13:00:49 | APPROVED WITH PROVISOS: |
| | DEAN S. LAUDERMILK, PROJECT COORDINATOR, CONTACT NUMBER |
| | 494-1083 (ENGINEERING) 805-6716 (CONSTRUCTION SERVICES) |
| | 1. IF AN AIR RIGHTS EASEMENT HAS BEEN APPLIED FOR THIS |
| | COMMENT IS NO LONGER VALID. IF AN AIR RIGHTS EASEMENT |
| | HAS NOT BEEN APPLIED FOR THEN ONE NEEDS TO BE APPLIED |
| | FOR AND APPROVED PRIOR TO GETTING A CO. NO PERMANENT |
| | STRUCTURES ARE ALLOWED IN CITY ROW (BALCONY ABOVE |
| | ENTRANCE DOOR). |
| | 2. DOORS ARE NOT ALLOWED TO OPEN OUT INTO A SIDEWALK |
| | AND OR ROW. THE ENTRANCE DOOR ON RODSEMARY TO THE |
| | RECEPTION AREA NEEDS TO BE RECESSED OR REDESIGNED TO |
| | OPEN IN. |
| | 3. IRRIGATION PLAN NEEDS TO BE MODIFIED. THE |
| | ENGINEERING REVIEW INVOLVES THE SIZE OF METERS TO BE |
| | USED. |
| | A) IRRIGATION SYSTEM ZONES, GALLON PER MINUTE (GPM) |
| | FLOWS MUST BE SHOWN (PER SHEET IR-1 THE 4 ZONES ARE |
| | CALLED OUT). THE VALVE INFORMATION DETAIL ON IR-2 |
| | SHOWS, THE ZONE NUMBER, GALLONS PER MINUTE OF EACH ZONE |
| | AND SIZE OF VALVE FOR EACH ZONE NEEDS TO BE CALLED OUT, |
| | THEY ARE NOT. THEN SEE NOTE IR-B. |
| | B) A 5/8" WATER METER IS CALLED OUT FOR IRRIGATION |
| | USAGE ON IR-1 IN THE NOTES SECTION. A 5/8" WATER METER |
| | WILL ONLY GIVE 10 GPM (SAFE OPERATING FLOW). IF ANY |
| | ZONE IS LARGER THAN THIS THE METER SIZE SHALL NEED TO |
| | BE INCREASED. A 3/4" WATER METER WILL GIVE 15 GPM AND A |
| | 1" WATER METER WILL GIVE 25 GPM. IF ANY ZONE IS OVER 10 |
| | GPM THEN REDESIGN THE IRRIGATION SYSTEM OR INCREASE THE |
| | METER SIZE ACCORDANTLY. |
| | 4. IF THE STORMWATER PRE AND POST SQUARE FOOTAGE HAS |
| | BEEN GIVEN TO ENGINEERING THIS NOTE IS NO LONGER VALID. |
| | IF THE INFORMATION HAS NOT BE RECIEVED THEN FORWARD THE |
| | PRE AND POST PERVIOUS AND IMPERVIOUS SQ. FOOTAGE TO |
| | ENGINEERING. THIS WILL BE CHECKED AND CAN HOLD UP THE |
| | CO ON THE BUILDING. |