2008-09-12 16:54:54PLUMBING PLAN REVIEW:
 DENIED:
  
 PLAN REVIEW UNDER THE 2004 FLORIDA BUILDING CODES WITH
 2007 REVISIONS, CITY OF WEST PALM BEACH AMENDMENTS TO
 CHAPTER 1 (W.P.B.), FLORIDA ADMINISTRATIVE CODE
 (F.A.C.), AND FLORIDA STATUTES (F.S.).
  
 THE FOLLOWING CORRECTIONS/INFORMATION ARE REQUIRED FOR
 PLUMBING PLAN REVIEW TO MEET CODE COMPLIANCE.
  
 1. SHEET A102 BATH ROOM NUMBER 208 AND 214 INDICATE THE
 WATER CLOSET 1'-4" FROM THE SHOWER WALL TO THE
 CENTERLINE OF THE WATER CLOSETS IN A 30" MIN. SPACE
 PROVIDED FOR THE WATER CLOSET. THIS LEAVES 14" FROM
 CENTERLINE OF THE WATER CLOSET TO THE EDGE OF THE
 LAVATORY. PER CODE A MINIMUM OF 15" IS REQUIRED. WHY
 ISN'T THE WATER CLOSET CENTERED IN THE 30" SPACE AT
 1'-3" TO BE COMPLIANT? PER FBC-2004 PLUMBING SECTION
 405.3.1 WATER CLOSETS, URINALS, LAVATORIES AND BIDETS.
  
 2. SHEET A103 EXISTING GARAGE-PROPOSED SECOND FLOOR
 PLAN ROOM NUMBER 203 DOES NOT INDICATE THE PROPOSED BAR
 SINK THAT IS BEING INDICATED ON SHEET P201 GUEST HOUSE
 SANITARY RISER. PLEASE CORRELATE PLAN SHEET TO REFLECT
 THE PROPOSED BAR SINK. PER (W.P.B. AS AMENDED) SECTION
 106.1.1 INFORMATION ON CONSTRUCTION DOCUMENTS.
  
 3. SHEET A400 PLUMBING FIXTURE SCHEDULE: PLEASE KNOW
 THAT THE FIXTURES IN THE SCHEDULE REQUIRE THIRD-PARTY
 TESTING AND CERTIFICATION. PLEASE KNOW THAT FIXTURES
 LISTED IN THE SCHEDULE ARE NOT COMMONLY USED FIXTURES
 SUCH AS KOHLER OR AMERICAN STANDARD AND AN ONLINE
 SEARCH BY THIS PLANS EXAMINER FAILED TO COME UP WITH
 THE REQUIRED THIRD PARTY TESTING AND CERTIFICATIONS.
 PROVIDE MANUFACTURE SPECIFICATION SHEETS WITH THIS
 INFORMATION. PER FBC-2004 PLUMBING SECTION 303.4
 THIRD-PARTY TESTING AND CERTIFICATION.
 NOTE: THE FOLLOWING IS A LIST OF FIXTURES AND COMPLIANT
 THIRD-PARTY TESING AND CERTIFICATION STANDARDS
 MANUFACTURE SHEETS MUST INDICATE PER THE FBC-2004
 PLUMBING CODE SECTIONS.
  
 A} BATHTUBS= SECTION 407.1 APPROVAL. BATHTUBS SHALL
 CONFORM TO ANSI Z124.1, ASME A112.19.1M, ASME
 A112.19.4M, ASME A112.19.9M, CSA B45.2, CSA B45.3 OR
 CSA B45.5.
  
 B} LAVATORIES= SECTION 416.1 APPROVAL. LAVATORIES SHALL
 CONFORM TO ANSI Z124.3, ASME A112.19.1M, ASME
 A112.19.2M, ASME A112.19.3M, ASME A112.19.4M, ASME
 A112.19.9M, CSA B45.1, CSA B45.2, CSA B45.3 OR CSA
 B45.4. GROUP WASH-UP EQUIPMENT SHALL CONFORM TO THE
 REQUIREMENTS OF SECTION 402 . EVERY 20 INCHES (508 MM)
 OF RIM SPACE SHALL BE CONSIDERED AS ONE LAVATORY.
 SECTION 416.2 CULTURED MARBLE LAVATORIES. CULTURED
 MARBLE VANITY TOPS WITH AN INTEGRAL LAVATORY SHALL
 CONFORM TO ANSI Z124.3 OR CSA B45.5.
  
 C} SHOWER= SECTION 417.1 APPROVAL. PREFABRICATED
 SHOWERS AND SHOWER COMPARTMENTS SHALL CONFORM TO ANSI
 Z124.2, ASME A112.19.9M OR CSA B45.5. SHOWER VALVES FOR
 INDIVIDUAL SHOWERS SHALL CONFORM TO THE REQUIREMENTS OF
 SECTION 424.4 .
  
 D} WATER CLOSET= SECTION 420.1 APPROVAL. WATER CLOSETS
 SHALL CONFORM TO THE WATER CONSUMPTION REQUIREMENTS OF
 SECTION 604.4 AND SHALL CONFORM TO ANSI Z124.4, ASME
 A112.19.2M, CSA B45.1, CSA B45.4 OR CSA B45.5. WATER
 CLOSETS SHALL CONFORM TO THE HYDRAULIC PERFORMANCE
 REQUIREMENTS OF ASME A112.19.6. WATER CLOSET TANKS
 SHALL CONFORM TO ANSI Z124.4, ASME A112.19.2, ASME
 A112.19.9M, CSA B45.1, CSA B45.4 OR CSA B45.5.
 ELECTRO-HYDRAULIC WATER CLOSETS SHALL COMPLY WITH ASME
 A112.19.13.
  
 E} FAUCETS AND OTHER FIXTURE FITTINGS SECTION 424.1
 APPROVAL. FAUCETS AND FIXTURE FITTINGS SHALL CONFORM TO
 ASME A112.18.1 OR CSA B125. FAUCETS AND FIXTURE
 FITTINGS THAT SUPPLY DRINKING WATER FOR HUMAN INGESTION
 SHALL CONFORM TO THE REQUIREMENTS OF NSF 61, SECTION 9.
 FLEXIBLE WATER CONNECTORS EXPOSED TO CONTINUOUS
 PRESSURE SHALL CONFORM TO THE REQUIREMENTS OF SECTION
 605.6 .
  
 F} SECTION 424.1.1 FAUCETS AND SUPPLY FITTINGS. FAUCETS
 AND SUPPLY FITTINGS SHALL CONFORM TO THE WATER
 CONSUMPTION REQUIREMENTS OF SECTION 604.4 .
  
 G} SECTION 424.1.2 WASTE FITTINGS. WASTE FITTINGS SHALL
 CONFORM TO ONE OF THE STANDARDS LISTED IN TABLES 702.1
 AND 702.4 FOR ABOVE-GROUND DRAINAGE AND VENT PIPE AND
 FITTINGS, OR THE WASTE FITTINGS SHALL BE CONSTRUCTED OF
 TUBULAR STAINLESS STEEL WITH A MINIMUM WALL THICKNESS
 OF 0.012 INCH (0.30 MM), TUBULAR COPPER ALLOY HAVING A
 MINIMUM WALL THICKNESS OF 0.027 INCH (0.69 MM) OR
 TUBULAR PLASTIC COMPLYING WITH ASTM F 409.
  
 H} SECTION 424.2 HAND SHOWERS. HAND-HELD SHOWERS SHALL
 CONFORM TO ASSE 1014 OR CSA B125.
  
 I} SECTION 424.3 SHOWER VALVES. SHOWER AND TUB-SHOWER
 COMBINATION VALVES SHALL BE BALANCED PRESSURE,
 THERMOSTATIC OR COMBINATION
 BALANCED-PRESSURE/THERMOSTATIC VALVES THAT CONFORM TO
 THE REQUIREMENTS OF ASSE 1016 OR CSA B125. SHOWER AND
 TUB-SHOWER COMBINATION VALVES AND MASTER THERMOSTATIC
 MIXING VALVES REQUIRED BY THIS SECTION SHALL BE
 EQUIPPED WITH A MEANS TO LIMIT THE MAXIMUM SETTING OF
 THE VALVE TO 120?F (49?C), WHICH SHALL BE FIELD
 ADJUSTED IN ACCORDANCE WITH THE MANUFACTURER?S
 INSTRUCTIONS.
  
 J} SECTION 424.4 HOSE-CONNECTED OUTLETS. FAUCETS AND
 FIXTURE FITTINGS WITH HOSE-CONNECTED OUTLETS SHALL
 CONFORM TO ASME A112.18.3M.
  
 K} SECTION 424.5 TEMPERATURE-ACTUATED, FLOW REDUCTION
 VALVES FOR INDIVIDUAL FIXTURE FITTINGS.
 TEMPERATURE-ACTUATED, FLOW REDUCTION DEVICES, WHERE
 INSTALLED FOR INDIVIDUAL FIXTURE FITTINGS, SHALL
 CONFORM TO ASSE 1062. SUCH VALVES SHALL NOT BE USED
 ALONE AS A SUBSTITUTE FOR THE BALANCED PRESSURE,
 THERMOSTATIC OR COMBINATION SHOWER VALVES REQUIRED IN
 SECTION 424.3 .
  
 L} SECTION 424.6 TRANSFER VALVES. DECK-MOUNTED
 BATH/SHOWER TRANSFER VALVES CONTAINING AN INTEGRAL
 ATMOSPHERIC VACUUM BREAKER SHALL CONFORM TO THE
 REQUIREMENTS OF ASME A112.18.7.
  
 4. SHEET P200 E.W.H. PIPING SCHEMATIC: PLEASE KNOW THAT
 THE "WATTS #288 ATMOSPHERIC VACUUM BREAKER" IS THE
 WRONG VALVE FOR A BOTTOM FED WATER HEATER. A "WATTS
 #N36 VACUUM RELIEF VALVE" IS THE CORRECT TYPE OF VALVE
 FOR A BOTTOM FED WATER HEATER. PER FBC-2004 PLUMBING
 SECTION 504.2 VACUUM RELIEF.
  
 5. SHEET P200 MAIN HOUSE WATER HEATER DETAIL NOTES #9:
 A VACUUM RELIEF VALVE IS REQUIRED FOR THE 80 GALLON
 STORAGE TANK NOT A VACUUM BREAKER. PLEASE CLEARLY
 INDICATE THIS REQUIRED VALVE ON THE RESUBMITTAL. PER
 FBC-2004 PLUMBING SECTION 504.2 VACUUM RELIEF.
  
 6. SHEET P200 MAIN HOUSE WATER HEATER DETAIL NOTES #8
 THE "AUTO AIR VENT-GRUNDHFUS YGE075T" LOCATION IS
 MISSING FROM THE DETAIL. CLEARLY INDICATE THE LOCATION
 OF THIS ITEM. PER FBC-2005 PLUMBING SECTION 501.1
 SCOPE.
  
 7. SHEET P201 MASTER BATH ROOM #205: DUE TO THE FIXTURE
 LAYOUT CHANGES OF THIS ROOM A COMPLETE SANITARY
 ISOMETRIC RISER DIAGRAM IS REQUIRED OF THE NEW PROPOSED
 MASTER BATH LAYOUT. PER FBC-2004 PLUMBING SECTION 701.1
 SCOPE, SECTION 901.1 SCOPE AND (W.P.B. AS AMENDED)
 SECTION 106.3.5.4 (9) PLUMBING.
  
 8. SHEET P201 MAIN HOUSE SANITARY RISER: A CLEANOUT IS
 REQUIRED FOR THE 3 INCH WASHING MACHINE STACK. CLEARLY
 INDICATE THE REQUIRED 3 INCH CLEANOUT FOR THE WASHING
 MACHINE STACK TO BE LOCATED A FOUR FEET ABOVE FINNISH
 FLOOR (4' A.F.F.) PER FBC-2004 PLUMBING SECTION 708.9
 ACCESS.
  
 ********IMPORTANT INFORMATION********
 WHEN RESUBMITTING PLANS, PLEASE PROVIDE A COPY OF THE
 OLD PLANS, CLEARLY INDICATE THE REVISION ON THE NEW
 PLANS, REMOVE AND REPLACE ANY PAGES AS NECESSARY. A
 TRANSMITTAL LETTER LISTING THE ORIGINAL REVIEW COMMENT
 NUMBER, WITH A DESCRIPTION OF THE REVISION MADE,
 IDENTIFYING THE SHEET OR SPECIFICATION PAGE WHERE
 CHANGES CAN BE FOUND WILL HELP TO EXPEDITE YOUR PERMIT.
 THANK YOU FOR YOUR ANTICIPATED COOPERATION.
  
 END OF COMMENTS:
  
 REVIEW BY: MIKE PERSON
 PLUMBING PLANS EXAMINER
 PHONE= (561) 805-6730
 FAX= (561) 805-6731
 E-MAIL= [email protected]


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved