Plan Review Notes
Plan Review Notes For Permit 08090055
Permit Number 08090055
Review Stop ENG
Sequence Number 1
Notes
Date Text
2008-09-17 15:52:21FAILED FOR FOLLOWING REASONS:
  
 1. PLEASE SHOW ON DRAWINGS THE TURBIDITY BARRIER
 DETAILS OF POLLUTION PREVENTION . PLEASE SHOW ON
 DRAWINGS THE TURBIDITY BARRIER AROUND CATCH BASINS, ANY
 OUT FALLS OR LAKES IF YOU HAVE ETC DURING CONSTRUCTION
 AND ALL DEMOLITION PHASE. HEIGHT OF BARRIER SHOULD BE
 HIGH ENOUGH PER FDEP TO STOP DUST PARTICLES.
  
 2. PLEASE PROVIDE A COPY OF BOND FOR ORDINANCE NO.
 4060-07:
  
 ALL DEMOLITION AND NEW CONSTRUCTION PERMITS, WITH
 EXCEPTION OF SINGLE FAMILY, DUPLEX AND ACCESSORY
 APARTMENT, SHALL POST BONDS OR DEPOSITS FOR THE
 FOLLOWING:
  
 1. EROSION CONTROL, AND
 2. LAND STABILIZATION
  
 THE AMOUNT OF THE EROSION CONTROL AND LAND
 STABILIZATION BONDS SHALL BE DETERMINED BY THE ENGINEER
 OF RECORD USING THE CURRENT CITY COST SCHEDULE AND
 VERIFIED BY THE CITY'S ENGINEERING SERVICES DEPT.
 PLEASE CONTACT BRIAN MOREE, ENG SERVICES CONSTRUCTION
 SUPERVISOR, AT 561- 494 -1040 FOR MORE INFORMATION.
  
 UPON VERTICAL CONSTRUCTION COMMENCEMENT, PAYMENT IN
 FULL OF ALL APPLICABLE FEES, AND COMPLIANCE WITH ALL
 TERMS AND CONDITIONS OF ANY POSTED BOND, THE PERMITTEE
 MAY REQUEST RELEASE OF THE BONDS OR DEPOSITS.
  
 A COPY OF ORDINANCE NO. 4060-07 MAY BE OBTAINED FROM
 THE CITY CLERK'S OFFICE LOCATED ON THE FIRST FLOOR.
  
 3. PLEASE SHOW ON DRAWINGS DUMPSTER & ITS ENCLOSURE
 DETAILS PER CITY OF WPB, & LOCATION ON DWG, LOCATION
 MUST BE ACCESSIBLE FOR PICKUP TRUCK.
  
 4. PLEASE SHOW ON STORM WATER QUALITY CALCULATION THAT
 YOU HAVE CONSIDERED FLOOD ZONE AREA, & 5,10, 25, 50,
 100 YEAR FLOOD CRITERIA AND CROWN OF THE ROAD WHEN YOU
 DETERMINE THE FIRST FLOOR ELEVATION. FIRST FLOOR
 ELEVATION SHOULD BE ATLEAST 1 FOOT HIGHER THAN HIGHEST
 CROWN OF THE ROAD.
  
 5. PLEASE SHOW ALL STORM WATER PIPES AROUND YOUR SITE
 SO, WE CAN SEE THE LAYOUT OF STORM WATER PIPES FROM ALL
 OTHER STORM WATER PIPES. PLEASE SHOW DETAIL OF THE
 CONTROL STRUCTURES WITH ELEVATIONS, NOTCHES, BLEEDING
 ELEVATION, ETC ON DRAWINGS, CALCULATION FOR
 EXFILTRATION TRENCHES, PLEASE SHOW DRY DETENTION/WET
 DETENTION AREAS IN STORM WATER CALS IF YOU HAVE ALL
 THESE. PLEASE RESUBMIT GEO-TECH REPORT AND ALL
 ENVRONMENTAL REPORT.
  
 6. ALSO PLEASE SHOW ALL CATCH BASINS NEAREST, AROUND
 YOUR SITE FOR STORM WATER DRAIN SO YOUR SITE DO NOT GET
 FLOODED AND HAVE ENOUGH DRAINS.
  
 7. PLEASE PROVIDE A COPY OF GEO-TECH REPORT & STORM
 WATER QUALITY CALCULATIONS TO 1000 45TH STREET FOR
 THEIR APPROVAL BEFORE WE ISSUE A PERMIT.
  
 8. WATER & SEWER PLANS MUST BE APPROVED FROM MANNY G.
 OF 1000 45TH STREET BEFORE WE ISSUE A PERMIT.
  
 PLEASE RESPOND EACH ITEM IN DETAIL TO EXPEDITE YOUR
 PERMITTING PROCESS
  
 RASIK CHOKSHI 805-6723
  
  
  
  
  
  