| Plan Review Notes For Permit 08050784 |
| Permit Number |
08050784 |
|
| Review Stop |
B |
| Sequence Number |
4 |
|
| Notes |
| Date |
Text |
| 2008-10-09 14:33:30 | BUILDING PROVISO: FBC BUILDING 3110.1.2 / CITY OF WPB | | | CODE OF ORDINANCES SECTION 94-546. STRUCTURE IS LOCATED | | | IN AN "A" FLOOD ZONE. A FLOOD ELEVATION CERTIFICATE MAY | | | BE REQUIRED. DEPENDING ON THE TIMING OF THE BUILDING | | | C.O. IF THE GENERATORS ARE GOING TO RECEIVE THEIR CO AT | | | THE SAME TIME AS THE BUILDING A FLOOD ZONE CERTIFICATE | | | WILL BE REQUIRED. IF THE GENERATORS ARE GOING TO BE | | | FINAL AFTER THE BUILDING C.O. THEN EITHER A SURVEY WITH | | | ELEVATION HEIGHT OR DESIGNER OF RECORD PROVIDING SITE | | | PLAN WITH ASSOCIATED SLAB ELEVATION. THE MINIMUM FLOOD | | | ELEVATION THE SLAB MAY BE SET AT IS 13'-6" IN A "A-9" | | | FLOOD ZONE, THIS MAY BE ACCOMPLISHED AT TIME OF THE | | | FINAL. |
|