| Date |
Text |
| 2008-06-30 10:50:32 | ****PRIVATE PROVIDER AUDIT**** |
| | |
| | SAMANTHA HILL, BUILDING PLANS EXAMINER |
| | 561-805-6724 [email protected] |
| | |
| | FBCFLORIDA BUILDING CODE 2004 |
| | FBC EBFLORIDA BUILDING CODE 2004 EXISTING BUILDING |
| | CODE |
| | FBC RFLORIDA BUILDING CODE 2004 RESIDENTIAL FBC* |
| | CITY OF WEST PALM BEACH AMENDMENTS TO THE FBC2004 FAC |
| | FLORIDA ADMINISTRATIVE CODE |
| | FSFLORIDA STATUTE |
| | |
| | 1. ADDRESSED OR INFORMATIONAL ONLY. |
| | |
| | 2.FBC*105.13, PHASED PERMIT APPROVAL, THE HOLDER OF |
| | SUCH PERMIT FOR THE FOUNDATIONS OR OTHER PARTS OF A |
| | BUILDING OR STRUCTURE SHALL PROCEED AT THE HOLDER'S OWN |
| | RISK WITH THE BUILDING OPERATION AND WITHOUT ASSURANCE |
| | THAT A PERMIT FOR THE ENTIRE STRUCTURE WILL BE GRANTED. |
| | CORRECTIONS MAY BE REQUIRED TO MEET THE REQUIREMENTS OF |
| | THE TECHNICAL CODES. |
| | |
| | THIS PERMIT WILL BE ISSUED AT RISK. |
| | |
| | 3.SEE FAC61G15-23.002, ALL INFORMATION REQUIRED BY |
| | THIS SECTION IS REQUIRED ON EACH SHEET (PRINTED NAME |
| | AND LICENSE NUMBER OF THE PERSON SEALING THE DOCUMENT, |
| | CERTIFICATE OF AUTHORIZATION FOR THE ENGINEERING |
| | FIRM). |
| | |
| | 2ND REVIEW, NOTE THAT THE CERTIFICATE OF AUTHORIZATION |
| | FOR SCHNABEL ENGINEERING SOUTH, LLC WAS NOT INCLUDED |
| | AND ONLY TWO SETS WERE SUBMITTED.I WAS ABLE TO LOCATE |
| | A COFA FOR SCHNABEL ENGINEERING SOUTH, LLC, BUT FOUND |
| | THE RECORD FOR SCHNABLE SOUTH, LLC; IF USING THIS |
| | NUMBER PLEASE CONFIRM WITH FBPE THAT IT IS ACCEPTABLE |
| | TO USE THIS NUMBER FOR A COMPANY WITH A SLIGHTLY |
| | DIFFERENT NAME. |
| | |
| | 4.ADDRESSED OR INFORMATIONAL ONLY. |
| | |
| | 5.PLEASE INCLUDE THE DATE OF THE PLAN (OR REVISION |
| | NUMBER) ON THE PRIVATE PROVIDER PLAN COMPLIANCE |
| | AFFIDAVIT. |
| | |
| | 2ND REVIEW, SEE OTHER COMMENTS REGARDING AFFIDAVITS. |
| | PLEASE CONFIRM THAT ALL AFFIDAVITS ARE CORRECT PRIOR TO |
| | RESUBMITTAL; SEE OTHER COMMENTS. |
| | |
| | 6.ADDRESSED. |
| | |
| | 7.PLEASE NOTE THAT THE PRIVATE PROVIDER AFFIDAVIT IS |
| | CHECKED (FOR EACH SHEET NUMBER) PRIOR TO PERMIT |
| | ISSUANCE.PLEASE CONFIRM THAT THE AFFIDAVIT REFERS TO |
| | ALL SHEETS PRIOR TO RESUBMITTAL. |
| | |
| | 2ND REVIEW, NOTE THE FOLLOWING REGARDING THE |
| | AFFIDAVIT: |
| | |
| | |
| | A. THE STRUCTURAL SPECIFICATIONS ARE DATED 6/6/8, BUT |
| | THE AFFIDAVIT IS FOR SPECIFICATIONS DATED 6/12/8. |
| | |
| | B. THE SOILS REPORT IS DATED 10/1/7, AFFIDAVIT IS FOR A |
| | SOILS REPORT DATED 8/1/7.THE SOILS REPORT SUBMITTED |
| | IS NOT STAMPED BY GFA, BUT MOST OTHER REVIEWED SHEETS |
| | AND REPORTS/SPECS WERE STAMPED (THE SURVEY ALSO DID NOT |
| | INCLUDE A GFA STAMP). |
| | |
| | C. SHEET S107CR1 IS NOT INCLUDED IN THE AFFIDAVIT. |
| | |
| | D. SHEET S107C IS INCLUDED IN THE AFFIDAVIT BUT NOT |
| | INCLUDED IN THE PLAN. |
| | |
| | E. FOUR OF THE PLUMBING SHEETS ARE DATED 5/29/8, BUT |
| | THE AFFIDAVIT IS FOR SHEETS DATED 4/15/8. |
| | |
| | F. SHEET M101C IS DATED 4/16/8, THE AFFIDAVIT IS FOR |
| | SHEETS DATED 4/15/8. |
| | |
| | 8.ADDRESSED. |
| | |
| | 9. 2ND REVIEW, INFORMATION TO SHOW COMPLIANCE WITH |
| | FBC*109.3.4 REGARDING TERMITE TREATMENT WAS HAND |
| | WRITTEN ON THE PLAN.ALL CHANGES TO THE PLAN MUST BE |
| | INCORPORATED INTO THE DRAWING AS IT IS IMPOSSIBLE TO |
| | DETERMINE AT WHAT POINT THIS CHANGE WAS DONE, AND |
| | WHETHER OR NOT THE PRIVATE PROVIDER REVIEWED THIS |
| | CHANGE.THIS APPLIES TO ALL PRIVATE PROVIDER PROJECTS. |
| | SHEET S101CR1. |
| | |
| | |
| | 10. ADDRESSED. |
| | |
| | 11.AT THIS TIME, WILLIE SWOPE (PALM BEACH COUNTY |
| | IMPACT FEES) HAS DETERMINED THAT IMPACT FEES ARE NOT |
| | APPLICABLE IF THIS FACILITY IS OWNED AND OPERATED BY |
| | SOLID WASTE AUTHORITY.IF HE OBTAINS OTHER INFORMATION |
| | WHICH WOULD REQUIRE THAT IMPACT FEES BE PAID ON THIS |
| | PROJECT, THE CONTRACTOR WILL BE ADVISED. |
| | |
| | 12. FBC* 109.3.7, A RESIDENT INSPECTOR WILL BE REQUIRED |
| | TO SUPERVISE THE INSTALLATION OF THE STEEL STRUCTURE. |
| | THIS COMMENT DOES NOT AFFECT THIS PERMIT AT THIS TIME; |
| | THIS IS ADVISORY ONLY.THREE SETS WILL BE REQUIRED |
| | WHEN BUILDING PERMIT APPLICATION IS MADE. |
| | |
| | INFORMATIONAL ONLY.THE PERMIT WILL BE ISSUED WITH A |
| | PROVISO THAT A RESIDENT INSPECTOR WILL BE REQUIRED. |
| | |
| | 13. THIS PERMIT WAS SUBMITTED AS A FOUNDATION PERMIT |
| | ONLY.THEREFORE, A COMPLETE PLAN REVIEW OF OTHER |
| | SHEETS HAS NOT BEEN DONE AT THIS TIME, SUCH AS LIFE |
| | SAFETY, ACCESSIBILITY, ETC.AS NOTED, THIS PERMIT WILL |
| | BE ISSUED AT RISK. |
| | |
| | 14-19. ADDRESSED. |
| | |
| | NEW COMMENTS: |
| | |
| | 21.***IF ALL TRADES PASS REVIEW, AND OTHER ITEMS ON |
| | THIS LIST ARE ADDRESSED, ITEM 9 CAN BE A PROVISO ITEM |
| | (SHEET S101CR1 TO BE REVISED PRIOR TO FIRST INSPECTION |
| | OR WITHIN 30 DAYS OF PERMIT ISSUANCE, WHICHEVER COMES |
| | FIRST).IF OTHER TRADES HAVE PLAN REVIEW COMMENTS, |
| | PLEASE REVISE THE PLAN PRIOR TO RESUBMITTAL.*** |