| Date |
Text |
| 2008-05-10 12:44:58 | |
| | |
| | DENIED |
| | |
| | 1)THE CLAIMED VALUATION ON THE PERMIT APPLICATION IS |
| | LOW. FOR PERMITTING PURPOSES, VALUATION OF BUILDINGS |
| | AND SYSTEMS SHALL BE THE TOTAL REPLACEMENT COST |
| | EXCLUDING LAND VALUE. OUR VALUATION REFERENCE IS ICC |
| | (BVD), MARSHALL-SWIFT AND MEANS COST ANALYSIS SERVICES |
| | PER 108.3 FBC* |
| | |
| | 2)THE STATE OF FLORIDA REQUIRES COLLECTION OF A RADON |
| | SURCHARGE ON ALL NEW CONSTRUCTION COMPUTED ON UNDER |
| | ROOF FLOOR SPACE PER 10D-91 FAC. THESE FEES WILL BE |
| | ADDED TO THE PERMIT APPLICATION FEES |
| | |
| | |
| | NOTE: FEES ARE DUE IN THE AMOUNT OF $851.56 FOR |
| | INCREASED VALUE AND STATE RADON FEES THIS AMOUNT IS |
| | REQUIRED TO BE PAID PRIOR TO FURTHER PLAN REVIEW |
| | |
| | 3)ZONING REQUIRES A LANDSCAPE PLAN, PLEASE ADD A |
| | DRAINAGE PLAN PER R401.3 FBC RES. THAT SHOWS DRAINAGE |
| | AWAY FROM BUILDING AND PROPERTY LINES |
| | |
| | 4)WINDOW #6 IN WINDOW SCHEDULE HAS H36 AS 53 1/8" |
| | WIDE THIS WINDOW IS 26 1/2" WIDE AND ALSO DOES NOT MEET |
| | EGRESS REQUIREMENTS WITH ONLY 4.93 SQ. FT. CLEAR |
| | OPENING AREA. SGD WILL MEET THE EGRESS REQUIREMENTS FOR |
| | THIS ROOM. |
| | |
| | 5)WINDOW TYPE #4 REQUIRES 2X4 MULLION AS STATED ON |
| | SCHEDULE BUT NO PRODUCT APPROVAL WAS SUBMITTED. |
| | |
| | 6)CLARIFY TOP OF BEAM ELEVATION FOR FOYER AND FRONT |
| | PORCH, ROOF PLAN ON A-5.0 SHOWS 9'-4" BUT CEILING |
| | ELEVATION IS 14'-4" AS IS DETAIL 5 ON D-1 |
| | |
| | 7)PROVIDE MIN ROOF SHEATHING ATTACHMENT PER |
| | R803.2.3.1 FBC RES. MINIMUM 8D RING SHANK NAILS |
| | |
| | 8)SUBMIT ENGINEERED TRUSS DRAWINGS THAT COMPLY WITH |
| | R802.10.1 FBC WITH PERMIT APPLICATION OR BEFORE |
| | INSTALLATION THAT HAVE BEEN REVIEWED AND APPROVED BY |
| | THE DESIGNER OF RECORD |
| | |
| | 9)PROVIDE GLASS TYPE FOR SLIDING GLASS DOORS WITH |
| | PANELS 48" IN WIDTH (DOOR "T" AND "U"), PLEASE NOTE |
| | THAT TYPE "A" (MIN) GLASS WILL MEET DESIGN PRESSURES |
| | FOR ALL THE PANEL SIZES BELOW 48" BUT DO NOT MEET THE |
| | REQUIRED PRESSURE FOR THE LARGER PANELS |
| | |
| | 10)PLEASE NOTE THAT A GAS PERMIT WILL BE REQUIRED, |
| | SEE ATTACHED INFORMATION NEEDED FOR GAS PERMIT |
| | |
| | 11)APPROACH PERMIT WILL BE REQUIRED PLEASE NOTE THAT |
| | NO CONTRACTOR HAS SIGNED ON TO PERMIT AND NO PERMIT |
| | NUMBER HAS BEEN GENERATED, APPROCH PERMITS REQUIRE |
| | ENGINEERING REVIEW |
| | |
| | REMOVE ALL OLD PAGES AND RESUBMIT 2 COMPLETE SETS OF |
| | NEW DRAWINGS WITH REVISIONS AND INCLUDE 1 COPY OF THE |
| | OLD PAGES ONLY FOR REFERENCE. PLEASE RE-SUBMIT ANY |
| | PAGES WITH THE IMPACT FEE STAMP. ALL OUT DATED OR NON |
| | REQUIRED PRODUCT APPROVALS CAN BE REMOVED |
| | |
| | BLDG PLAN REVIEW |
| | ADRIAN MORSE |
| | 561-805-6716 |
| | |
| | |
| | |
| | |
| | |