Plan Review Notes
Plan Review Notes For Permit 08040824
Permit Number 08040824
Review Stop G
Sequence Number 5
Notes
Date Text
2008-11-13 10:22:25REVISION DENIED
 REFERENCE: FBC-2004 FUEL GAS
  
 1. SHTS P-1 & P-2 DRAWING REFERENCE NOTES 5A, (P-1),
 AND GAS RISER DIAGRAM, (P-2), INDICATE THE MANUAL SHUT
 OFF VALVE AND EMERGENCY SHUT OFF VALVE UP IN THE
 CEILING. THIS IS NOT APPROVED. ALSO THERE IS NO
 REQUIRED UNION INDICATED DOWNSTREAM OF THE MANUAL SHUT
 OFF VALVE. (SEE THE FOLLOWING):
 __ EMERGENCY HOOD SHUT DOWN SHUT OFF
 VALVE TO BE BELOW CEILING. MANUAL SHUT
 OFF VALVE TO BE UPSTREAM. UNION TO BE
 DOWN STREAM OF MANUAL VALVE.
  
 2. SHTS P-1 & P-2 THE FLOOR PLAN, GAS SYSTEM
 CALCULATIONS TABLE & THE GAS RISER DIAGRAM SHOW ITEM
 18, PIZZA OVEN. PER THE CONTRACTOR, ITEM 18 HAS BEEN
 DELETED. THIS WAS INDICATED WHEN THE CONTRACTOR APPLIED
 FOR THE GAS PERMIT. THE PROVISO INDICATED ON THE PLANS
 REQUIRED MANUF. SPECIFICATION SHEETS FOR ITEM 18. THE
 GAS PERMIT WAS ISSUED WITH THE STIPULATION THAT THE
 REVISIONS DELETES ITEM 18.
  
 3. SHT P-2 GAS SYSTEM CALCULATIONS BTU'S DO NOT REFLECT
 THE MANUF. SPECIFICATION SHEETS SUBMITTED PLEASE
 CORRELATE. THE FURTHEST OUTLET IS 145 FEET NOT 140 FEET
 AS INDICATED. THIS IS WITH THE LENGTH OF PIPE FROM THE
 METER TO THE FIRST RISE, (11 FEET OF 2-1/2" PIPE), THE
 LENGTH OF PIPE THRU THE OUTSIDE WALL THRU SLEEVE, AND
 THE LENGTH OF DROP DOWNSTREAM OF THE SLEEVED PIPE.
 PLEASE INDICATE ALL PIPE LENGTHS AND RECALCULATE TOTAL
 DEVELOPED LENGHT AND INDICTE ON THE GAS SYSTEM
 CALCULATIONS.
  
 4. SHT P-2 GAS RISER DIAGRAM HAS SOME PIPE SIZING THAT
 IS INCORRECT. 1-1/4" PIPE IS REQUIRED TO THE SHUT OFF
 VALVE TO THE WATER HEATER. (1" INDICATED). -- 2" PIPE
 IS REQUIRED UP TO ITEM NUMBER 13, (NO PIPE SIZE
 INDICATED). -- 1-1/2" REQUIRED UP TO ITEM 10, (NO PIPE
 SIZE INDICATED). -- 1-1/4" REQUIRED UP TO ITEM 11, (NO
 PIPE SIZE INDICATED). -- 1" REQUIRED UP TO ITEM 9, (NO
 PIPE SIZE INDICATED). -- THE FOLLOWING STUB OUTS TO THE
 APPLIANCES ARE NOT CORRECT. -- 1" REQUIRED TO SHUT OFF
 VALVE FOR ITEM 15. -- 1-1/4" REQUIRED UP TO THE SHUT
 OFF VALVES FOR ITEMS 17, 13 & 10.
  
 5. SHT P-3 FOOD SERVICE PLUMBING EQUIPMENT SCHEDULE.
 REVISIED MANUFACTURE & MODEL NUMBER CHANGED TO READ
 "REFER TO KITCHEN CONSULTANT DRAWINGS". KITCHEN
 CONSULTANT DRAWINGS WERE NOT SUBMITTED. IF THE GAS
 EQUIPMENT HAS CHANGED, THEN THE MANUFACTURE
 SPECIFICATION SHEETS FOR THE GAS EQUIPMENT SHALL BE
 SUBMITTED AND SHALL CORRELATE WITH THE GAS LOAD
 INDICATED ON THE GAS RISER DIAGRAM.
  
 WHEN RESUBMITTING PLANS PLEASE INDICATE
 THE REVISION & REMOVE & REPLACE ANY
 PAGES AS NECESSARY. A TRANSMITTAL LETTER
 LISTING THE ORIGINAL REVIEW COMMENT NUMBER,
 WITH A DESCRIPTION OF THE REVISION MADE,
 IDENTIFYING THE SHEET OR SPECIFICATION
 PAGE WHERE THE CHANGES CAN BE FOUND
 WILL HELP TO EXPEDITE YOUR PERMIT. REMOVE
 ALL VOID SHEETS FROM ALL PLANS AND PLACE
 ONE SET OF THEM LOOSELY ON TOP OF THE
 COLLATED PLANS TO BE REVIEWED.
 THANK YOU FOR YOUR ANTICIPATED COOPERATION.
  
 REVIEW BY KEN STEVENS
 (561) 805-6721
 FAX (561) 805-6731
 E-MAIL [email protected]
  