| Date |
Text |
| 2008-09-19 13:39:10 | FAILED FOR FOLLOWING REASONS: |
| | |
| | 1.PLEASE SHOW ON DRAWINGS THE POLLUTION PREVENTION |
| | DETAILS,CLOTHES USED FOR SILT FENCE ETC., PLANS SHOWING |
| | SILT FENCE AROUND THE SITE & STORM CATCH BASIN DRAINS |
| | DURING CONSTRUCTION AND ALL DEMOLITION PHASE. HEIGHT OF |
| | FENCE SHOULD BE HIGH ENOUGH PER FDEP TO STOP DUST |
| | PARTICLES. |
| | |
| | 2. PLEASE PROVIDE A COPY OF BOND FOR ORDINANCE NO. |
| | 4060-07: |
| | |
| | ALL DEMOLITION AND NEW CONSTRUCTION PERMITS, WITH |
| | EXCEPTION OF SINGLE FAMILY, DUPLEX AND ACCESSORY |
| | APARTMENT, SHALL POST BONDS OR DEPOSITS FOR THE |
| | FOLLOWING: |
| | |
| | 1. EROSION CONTROL, AND |
| | 2. LAND STABILIZATION |
| | |
| | THE AMOUNT OF THE EROSION CONTROL AND LAND |
| | STABILIZATION BONDS SHALL BE DETERMINED BY THE ENGINEER |
| | OF RECORD USING THE CURRENT CITY COST SCHEDULE AND |
| | VERIFIED BY THE CITY'S ENGINEERING SERVICES DEPT. |
| | PLEASE CONTACT BRIAN MOREE, ENG SERVICES CONSTRUCTION |
| | SUPERVISOR, AT 561- 494 -1040 FOR MORE INFORMATION. |
| | |
| | UPON VERTICAL CONSTRUCTION COMMENCEMENT, PAYMENT IN |
| | FULL OF ALL APPLICABLE FEES, AND COMPLIANCE WITH ALL |
| | TERMS AND CONDITIONS OF ANY POSTED BOND, THE PERMITTEE |
| | MAY REQUEST RELEASE OF THE BONDS OR DEPOSITS. |
| | |
| | A COPY OF ORDINANCE NO. 4060-07 MAY BE OBTAINED FROM |
| | THE CITY CLERK'S OFFICE LOCATED ON THE FIRST FLOOR. |
| | |
| | 3. PLEASE SHOW ON DRAWING ALL CITY STANDARDS NOTES FOR |
| | SIDEWALK, DRIVEWAY, APPROACH, PARKINGS, HANDICAP |
| | PARKINGS, DUMPSTER ENCLOSURE, YOU CAN GET A C D FOR ALL |
| | CITY STANDARDS NOTES FROM 1000, 45 STREET, ENGINEERING |
| | SERVICES, PHONE# 494-1040 |
| | |
| | 4. PLEASE SHOW ON DRAWINGS DUMPSTER & ITS ENCLOSURE |
| | DETAILS PER CITY OF WPB, & LOCATION ON DWG, LOCATION |
| | MUST BE ACCESSIBLE FOR PICKUP TRUCK. |
| | |
| | 5. PLEASE SHOW ON YOUR STORM WATER QUALITY CALCULATION |
| | THAT YOU HAVE CONSIDERED FLOOD ZONE AREA, & 5,10, 25, |
| | 100 YEAR FLOOD CRITERIA AND CROWN OF THE ROAD WHEN YOU |
| | DETERMINE THE FIRST FLOOR ELEVATION. FIRST FLOOR |
| | ELEVATION SHOULD BE ATLEAST 1 FOOT HIGHER THAN HIGHEST |
| | CROWN OF THE ROAD. |
| | |
| | 6. PLEASE SHOW ON DRAINAGE DRAWING THE SITE AREA, |
| | GREEN, LAKE,PARKING AREA, IMPERVIOUS,PERVIOUS AREA YOU |
| | ARE DEVELOPING FOR THIS PROJECT . PLEASE MAKE SURE |
| | THESE AREAS SHOWN ON DRAINAGE DRAWINGS MUST MATCH WITH |
| | AND USED IN STORM WATER QUALITY CALCULATIONS. ALSO, |
| | STORM WATER QUALITY CALS MUST BE APPROVED FROM 1000 |
| | 45TH STREET ENGINEERING SERVICES BEFORE WE ISSUE A |
| | PERMIT. |
| | |
| | |
| | 7. PLEASE SHOW ALL STORM WATER PIPES AROUND YOUR SITE |
| | SO, WE CAN SEE THE LAYOUT OF STORM WATER PIPES FROM ALL |
| | OTHER STORM WATER PIPES. PLEASE SHOW DETAIL OF THE |
| | CONTROL STRUCTURES WITH ELEVATIONS, NOTCHES, BLEEDING |
| | ELEVATION, ETC ON DRAWINGS, CALCULATION FOR |
| | EXFILTRATION TRENCHES, PLEASE SHOW DRY DETENTION/WET |
| | DETENTION AREAS IN STORM WATER CALS IF YOU HAVE ALL |
| | THESE. PLEASE RESUBMIT GEO-TECH REPORT WITH SOIL |
| | CONDUCTIVITY USED IN EX-FILTRATION TRENCH AND ALL |
| | ENVRONMENTAL REPORT. |
| | |
| | 8. ALSO PLEASE SHOW ALL CATCH BASINS NEAREST, AROUND |
| | YOUR SITE FOR STORM WATER DRAIN SO YOUR SITE DO NOT GET |
| | FLOODED AND HAVE ENOUGH DRAINS. |
| | |
| | 9. WATER & SEWER PLANS MUST BE APPROVED FROM 1000 45TH |
| | STREET ENGINEERING BEFORE WE ISSUE A PERMIT. |
| | |
| | PLEASE RESPOND EACH ITEM IN DETAIL TO EXPEDITE YOUR |
| | PERMITTING PROCESS |
| | |
| | RASIK CHOKSHI 805-6723 |