| 2008-03-24 14:08:40 | ****CORRECTIONS**** |
| | |
| | SAMANTHA HILL, BUILDING PLANS EXAMINER |
| | 561-805-6724 [email protected] |
| | |
| | FBCFLORIDA BUILDING CODE 2004 |
| | FBC EBFLORIDA BUILDING CODE 2004 EXISTING BUILDING |
| | CODE |
| | FBC RFLORIDA BUILDING CODE 2004 RESIDENTIAL |
| | FBC* CITY OF WEST PALM BEACH AMENDMENTS TO THE FBC2004 |
| | FAC FLORIDA ADMINISTRATIVE CODE |
| | FSFLORIDA STATUTE |
| | |
| | |
| | 1.PROVIDE THE EVAULATION REPORT.DESIGN PRESSURE |
| | LIMITATIONS FOR THIS PRODUCT WERE NOT PROVIDED. |
| | FAC9B72, FBC CHAPTERS 15 AND 16. |
| | |
| | 2.A.THE APPLICATION STATES THAT YOU ARE APPLYING TO |
| | REROOF ONE BUILDING, BUT THERE ARE SEVERAL DIFFERENT |
| | ADDRESSES ON THE APPLICATION.PLEASE GO TO |
| | WWW.PBCGOV.COM/PAPA, PRINT THE AERIAL MAP OF THIS |
| | PARCEL, AND INDICATE WHICH BUILDING IS TO BE INCLUDED |
| | IN THIS PERMIT IF THIS PERMIT IS FOR A BUILDING WHICH |
| | IS "COMMON AREA" AS INDICATED ON THE PARCEL ID. |
| | |
| | B.IT APPEARS THAT THIS IS A QUADPLEX OF |
| | TOWNHOMES.IF THIS IS THE CASE, A SEPARATE PERMIT IS |
| | REQUIRED FOR EACH PARCEL (AND YOU CAN DISREGARD THE |
| | COMMENT 2A).TWO SETS OF COMPLETE PERMIT DOCUMENTS |
| | (APPLICATION, PRODUCT APPROVALS, ETC.) ARE REQUIRED FOR |
| | EACH PERMIT UNLESS YOU "MASTER" ONE SET OF PERMIT |
| | DOCUMENTS ($250 ADDITIONAL FEE FOR THE MASTER). |
| | |
| | 3.AS THE INFORMATION REGARDING DESIGN PRESSURES WAS |
| | NOT PROVIDED, A COMPLETE CHECKLIST CANNOT BE PROVIDED. |
| | HOWEVER, PLEASE NOTE THAT IF ENHANCED FASTENING IS |
| | REQUIRED FOR ZONES 2 AND 3 (PERIMETERS AND CORNERS, |
| | RESPECTIVELY), A LETTER STATING WHAT THAT ENHANCED |
| | FASTENING PATTERN WILL BE WILL BE REQUIRED.IF THE |
| | EVALUATION REPORT REQUIRES ENGINEERING, THEN |
| | ENGINEERING WILL ALSO BE REQUIRED.THIS IS ADVISORY |
| | AND CANNOT BE DETERMINED UNTIL THE EVALUATION REPORT IS |
| | PROVIDED. |
| | |
| | 4.WILL THIS CONTRACTOR BE APPLYING TO REROOF OTHER |
| | BUILDINGS?IF YES, PLEASE CONTACT ME REGARDING THE |
| | BEST WAY TO EXPEDITE THIS PROCESS.IF NOT, OR IF THE |
| | CONTRACTOR WISHES TO CONTINUE TO APPLY FOR PERMITS AS |
| | USUAL, PLEASE DISREGARD THIS COMMENT. |