| Date |
Text |
| 2008-03-14 09:19:24 | FAILED FOR FOLLOWING REASONS: |
| | |
| | 1. PLEASE PROVIDE A COPY OF NOTICE OF INTENT (NOI). |
| | PLEASE APPLY AT FDEP, NPDES STORMWATER SECTION FOR |
| | NOI. |
| | YOU CAN GET NOI INFO FROM |
| | WWW.DEP.STATE.FL.US/WATER/STORMWATER/NPDES/ |
| | NOTICE OF INTENT DEP FORM 62-621.300(4)(B), |
| | EFFECTIVE MAY 1, 2003 |
| | |
| | 2.PLEASE PROVIDE A COPY OF BOND FOR ORDINANCE NO. |
| | 4060-07: |
| | |
| | ALL DEMOLITION AND NEW CONSTRUCTION PERMITS, WITH |
| | EXCEPTION OF SINGLE FAMILY, DUPLEX AND ACCESSORY |
| | APARTMENT, SHALL POST BONDS OR DEPOSITS FOR THE |
| | FOLLOWING: |
| | |
| | 1. EROSION CONTROL, AND |
| | 2. LAND STABILIZATION |
| | |
| | THE AMOUNT OF THE EROSION CONTROL AND LAND |
| | STABILIZATION BONDS SHALL BE DETERMINED BY THE ENGINEER |
| | OF RECORD USING THE CURRENT CITY COST SCHEDULE AND |
| | VERIFIED BY THE CITY'S ENGINEERING SERVICES DEPT. |
| | PLEASE CONTACT BRIAN MOREE, ENG SERVICES CONSTRUCTION |
| | SUPERVISOR, AT 561- 494 -1040 FOR MORE INFORMATION. |
| | |
| | UPON VERTICAL CONSTRUCTION COMMENCEMENT, PAYMENT IN |
| | FULL OF ALL APPLICABLE FEES, AND COMPLIANCE WITH ALL |
| | TERMS AND CONDITIONS OF ANY POSTED BOND, THE PERMITTEE |
| | MAY REQUEST RELEASE OF THE BONDS OR DEPOSITS. |
| | |
| | A COPY OF ORDINANCE NO. 4060-07 MAY BE OBTAINED FROM |
| | THE CITY CLERK'S OFFICE LOCATED ON THE FIRST FLOOR. |
| | |
| | 3. PLEASE SHOW ON DRAWINGSDUMPSTER & ITS ENCLOSURE |
| | DETAILS PER CITY OF WPB, &LOCATION ON DWG, LOCATION |
| | MUST BE ACCESSIBLE FOR PICKUP TRUCK. |
| | |
| | 4. PLEASE PROVIDE WATER QUALITY CALCULATIONS.PLEASE |
| | SHOW ON CALCULATION THAT YOU HAVE CONSIDERED FLOOD ZONE |
| | AREA, & 5,10, 25, 100 YEAR FLOOD CRITERIA AND CROWN OF |
| | THE ROAD WHEN YOU DETERMINE THE FIRST FLOOR ELEVATION. |
| | FIRST FLOOR ELEVATION SHOULD BE ATLEAST 1 FOOT HIGHER |
| | THAN HIGHEST CROWN OF THE ROAD. |
| | |
| | 5. PLEASE SHOW ON DRAINAGE DRAWINGTHE SUMMARYOF THE |
| | SITE AREA, PERVIOUS AND IMPERVIOUS AREAS. ALSOGREEN, |
| | LAKE,PARKING AREA,YOU ARE DEVELOPING FOR THIS PROJECT |
| | . PLEASEMAKE SURE THESE AREAS SHOWN ON DRAINAGE |
| | DRAWINGS MUST MATCH WITH AND USED IN STORM WATER |
| | QUALITY CALCULATIONS. PLEASE PROVIDE A COPY OF THESE |
| | CALCULATIONS. |
| | |
| | 6. PLEASE SHOW ALL STORM WATER PIPES AROUND YOUR SITE |
| | SO, WE CANSEE THE LAYOUT OF STORM WATER PIPES FROM |
| | ALL OTHER STORM WATER PIPES. PLEASE SHOW DETAIL OF THE |
| | CONTROL STRUCTURESWITH ELEVATIONS, NOTCHES, BLEEDING |
| | ELEVATION, ETC ON DRAWINGS, CALCULATION FOR |
| | EXFILTRATION TRENCHES, PLEASE SHOW DRY DETENTION/WET |
| | DETENTION AREAS IN STORM WATER CALS IF YOU HAVE ALL |
| | THESE. |
| | |
| | 7. ALSO PLEASE SHOW ALL CATCH BASINS NEAREST,AROUND |
| | YOUR SITE FOR STORM WATER DRAIN SO YOUR SITE DO NOT GET |
| | FLOODED AND HAVE ENOUGH DRAINS. |
| | |
| | 8. PLEASE PROVIDE A COPY OF SFWMD PERMIT,, GEO-TECH |
| | REPORT , ENVIRONMENTAL REPORT&STORM WATER QUALITY |
| | CALCULATIONS. STORM WATER CALS MUST BE APPROVED FROM |
| | 100045TH STREET ENGINEERING SERVICES BEFORE WE |
| | APPROVED. |
| | |
| | 9. WATER & SEWER PLANS MUST BE APPROVED FROM 45TH |
| | STREET ENGINEERING BEFORE WE APPROVE. |
| | |
| | PLEASE RESPOND EACH ITEM IN DETAIL TO EXPEDITE YOUR |
| | PERMITTING PROCESS |
| | |
| | RASIK CHOKSHI805-6723 |