Plan Review Notes
Plan Review Notes For Permit 08020128
Permit Number 08020128
Review Stop E
Sequence Number 1
Notes
Date Text
2008-03-08 14:40:072008-03-08 14:40:07
  
 ** DENIED REVIEW**
  
 ** PLAN REVIEW
 SUPER TARGET
 1760 PALM BEACH LAKES BLVD.
  
 ** PLEASE KNOW AS THERE ARE SOME ITEMS NOT YET
 SUBMITTED FOR REVIEW AND SOME ITEMS NOT YET ON PLANS A
 REVIEW OF ONLY THE DOCUMENTS SUBMITTED CAN BE DONE AT
 THIS TIME. THERE MAY BE NEW COMMENTS ON THE FOLLOWING
 REVIEW WHICH CAN NOT BE MADE AT THIS TIME.
  
 1) NOTE: PLANS HAVE ONLY BEEN SUBMITTED FOR * PLAN
 REVIEW ONLY * AND HAVE NOT BEEN SUBMITTED UNDER PERMIT
 APPLICATION. PLEASE KNOW THAT ONCE ALL ITEMS FOR CODE
 REVIEWS ARE DONE PLANS WILL STILL REMAIN IN FAILED
 STATS UNTIL PERMIT APPLICATION HAS BEEN MADE.
 VERIFICATION OF SEVERAL ITEMS SUCH AS VALID LICENSING
 ETC IS DONE AT TIME OF APPLICATION BEFORE ISSUANCE OF
 PERMIT(S).
 IF THERE ARE ANY QUESTIONS ON THIS PLEASE CONTACT THIS
 OFFICE/REVIEWER.
  
 2) NOTE: PLEASE KNOW THAT ALL LOW VOLTAGE WIRING SHALL
 BE UNDER SEPARATE PERMITS FROM THE MAIN ELECTRICAL
 PERMIT. THE LV FOR PHONE, CATV AND OTHER SYSTEMS NOT
 INCLUDING LV FOR SECURITY MAY BE ALL UNDER ONE LV
 PERMIT. THE SECURITY SYSTEM IS A SEPARATE LV PERMIT
 FROM OTHERS LISTED ABOVE. IN EITHER CASE AS ALL LOW
 VOLTAGE SYSTEMS ARE SHOWN ON BASE BUILDING PLANS, THE
 APPLICANT MAY REFERENCE THESE PLANS FOR A *TURN-AROUND*
 PERMIT.
 ** THIS IS GIVEN FOR INFORMATIONAL PURPOSE AND IF THERE
 ARE ANY QUESTIONS ON THIS ITEM PLEASE CONTACT THIS
 REVIEWER.
  
 3) NOTE: PLEASE SEE NOTICE AT THE END OF THIS REVIEW
 WHICH IS NOTED AS ** IMPORTANT** ON CORRECT PROCEDURE
 ON RE-SUBMITTING PLANS AND THE REMOVING OF OLD/VOIDED
 SHEETS. IF THERE QUESTIONS PLEASE CONTACT THIS
 REVIEWER.
  
 4) NOTE: PLEASE BE SURE THE ELECTRICAL PLANS AS WELL AS
 COVER SHEET ON ARCHITECTURAL COVER SHEETS CONTAIN THE
 FOLLOWING CODES. SOME OF THESE MAY ALREADY BE LISTED
 HOWEVER NOT ALL AT BOTH PLACES. THESE MAY BE ON THE
 FIRST E-SHEET AND NOT ON ALL SHEETS.
  
 2004 FBC W/2007 REVISIONS.
 2005 NFPA_70
 2003 NFPA-101
 2002 NFPA-72
 2002 NFPA-110
 2003 NFPA-20 (NOT YET DETERMINED)
  
 ** PLEASE SEE ANY COMMENTS FROM OTHER TRADES WHICH ALSO
 MAY REQUIRE SPECIFIC CODES TO BE LISTED ON PLANS.
  
 5) NOTE: PLEASE SUBMIT THE MANUFACTURES SPECS/CUT
 SHEETS FOR THE GENERATOR, ALL ATS EQUIPMENT, AND FUEL
 TANK.
 PLEASE KNOW THAT A REVIEW OF THE FUEL TANK WILL BE DONE
 BY THE MECHANICAL, FIRE MARSHAL ETC.
 PLEASE SEE COMMENTS BELOW WITH RESPECT TO THE ATS
 UNITS.
 ** PLEASE SUBMIT ANY FIRE PUMP AND FIRE PUMP
 CONTROLLERS SPECS/CUT SHEETS AS WELL IF THIS BUILDING
 WILL CONTAIN ANY SUCH UNITS. PLANS DID NOT SEEM TO
 CONTAIN ANY FIRE PUMP ETC AND A REVIEW OF MANY ITEMS
 COULD NOT BE DONE IF THIS BUILDING IS GOING TO CONTAIN
 A FIRE PUMP.
 IF APPLICABLE PLEASE SEE NFPA-20, CHAPTERS 9 AND 10.
  
 6) NOTE: PLEASE SEE THE EMERGENCY LIFE SAFETY EQUIPMENT
 IS NOT PERMITTED IN THE SAME ROOM(S) AS THE NORMAL
 ELECTRICAL EQUIPMENT. PLEASE SEE NFPA-110 7.2, 7.1.3
 PLEASE SEE 7.2.2.1 BELOW ALSO.
 7.2.1THE EPS SHALL BE INSTALLED IN A SEPARATE ROOM FOR
 LEVEL 1 INSTALLATIONS. EPSS EQUIPMENT SHALL BE
 PERMITTED TO BE INSTALLED IN THIS ROOM.
 7.2.1.1THE ROOM SHALL HAVE A MINIMUM 2-HOUR FIRE RATING
 OR BE LOCATED IN AN ADEQUATE ENCLOSURE LOCATED OUTSIDE
 THE BUILDING CAPABLE OF RESISTING THE ENTRANCE OF SNOW
 OR RAIN AT A MAXIMUM WIND VELOCITY REQUIRED BY LOCAL
 BUILDING CODES.
 7.2.1.2NO OTHER EQUIPMENT, INCLUDING ARCHITECTURAL
 APPURTENANCES, EXCEPT THOSE THAT SERVE THIS SPACE,
 SHALL BE PERMITTED IN THIS ROOM.
 7.2.2EPSS EQUIPMENT SHALL NOT BE INSTALLED IN THE SAME
 ROOM WHERE THE NORMAL ELECTRICAL SERVICE EQUIPMENT IS
 INSTALLED.
 7.2.2.1TRANSFER SWITCHES SHALL BE PERMITTED TO BE
 INSTALLED IN THE NORMAL ELECTRICAL SERVICE ROOM WHERE
 TWICE THE CLEARANCE REQUIRED BY ARTICLE 110.26(A) OF
 NFPA 70, NATIONAL ELECTRICAL CODE, EXISTS BETWEEN
 EQUIPMENT ENCLOSURES.
  
 7) NOTE: PLEASE SEE 230.95, 240.13 AS THESE SECTIONS OF
 THE CODE AMONG OTHERS REQUIRED GROUND FAULT PROTECTION
 (GFP) ON THE SERVICE. THE PLANS CLEARLY SHOW THE GFP
 PROTECTION REQUIRED HOWEVER PLEASE SEE 700.6D, 700.26
 AND NFPA-110 6.2.15. AS THE CODE REQUIRES GFP ON NORMAL
 SIDE AND REQUIRES GF SENSING ON THE EMERGENCY SIDE THE
 ISOLATION OF THE SYSTEMS AND NEUTRALS IS IMPERATIVE.
 PROVISIONS SHALL BE INCLUDED FOR ENSURING CONTINUITY,
 TRANSFER, AND ISOLATION OF THE PRIMARY AND THE EPS
 NEUTRAL CONDUCTORS WHEREVER THEY ARE SEPARATELY
 GROUNDED TO ACHIEVE GROUND-FAULT SENSING.
 PLEASE SEE THE FOLLOWING INFORMATION GIVEN IS SECTIONS
 REMOVED FROM WHITE PAPERS AS WELL FROM TWO MANUFACTURES
 OF TRANSFER SWITCHES AND GENERATORS. THIS MAY HELP IN
 PROVIDING THE NEEDED EQUIPMENT AND ADJUSTMENT SO THE
 PLANS AND RISER.
  
 ** ** ASCO WHITE PAPER EXCERPT***
 **WHERE GROUND FAULTPROTECTION IS TRIGGERED BY THE
 CODE AND AN ALTERNATE POWER SUPPLY IS INCLUDED,
 SWITCHING OF THE NEUTRAL BECOMES NECESSARY. THE CIRCUIT
 SHOWN ABOVE ILLUSTRATESSUCH A CIRCUMSTANCE. THE
 SERVICE IS LARGER THAN 1,000 AMPS. CONSEQUENTLY, GROUND
 FAULT PROTECTION IS REQUIRED AT THE MAIN SERVICE
 DISCONNECT AT A MINIMUM. IF ITIS INSTALLED THERE AND
 THE GENERATOR NEUTRAL GROUNDING WAS THROUGH A SOLID
 CONNECTION TO THE MAIN SERVICE NEUTRAL, A GROUND FAULT
 WHEN THE GENERATOR ISFEEDING THE LOAD WILL CAUSE THE
 MAIN SERVICE DISCONNECT TO OPEN. THIS WILL NOT
 DISCONNECT THE ARCING FAULT FROM THE GENERATOR.
 COORDINATION IS THUSLOST."
  
 *****CATERPILLAR WHITE PAPER EXCERPT***
 SHOULD THE DESIGNER WANT TO GROUND THE GENERATOR AND
 STILL ADHERE TO CODE AND AVOID THE PROBLEMS
 OF SPLIT RETURN PATHS AND IMPROPER GFP SENSING
 THE USE OF A FOUR POLE TRANSFER SWITCH IS CALLED FOR.
 FOUR POLE TRANSFER SWITCHES
 FOUR POLE SWITCHES ARE EMPLOYED TO INSURE
 THAT THE GENERATOR CAN BE GROUNDED WITHOUT COMPROMISING
 THE NEC. THAT IS, THE GEN SET
 CAN BE WIRED AS A SEPARATELY DERIVED SYSTEM BY
 GROUNDING THE NEUTRAL AT THE GEN SET AS LONG AS THE
 NEUTRAL IS NO LONGER SOLID THROUGH THE TRANSFER SWITCH.
 THIS OF COURSE INFERS THAT NEUTRAL BE SWITCHED AT THE
 SAME TIME AS THE PHASES.
 THIS SCHEME WILL ALSO INSURE GFP OPERATION AS INTENDED.
 FIG. 12 SHOWS A FOUR POLE TRANSFER SWITCH WIRED WITH A
 GEN SET HAVING ITS NEUTRAL GROUNDED AT THE HOUSING. IN
 THIS WIRING THE NEUTRAL RETURN PATH IS DELIBERATELY
 OPEN FOR GROUND RETURN CURRENTS BY THE TRANSFER SWITCH
 CONTACTS. THIS WILL ALSO AVOID NUISANCE TRIPPING IN THE
 CASE OF AN UNBALANCED LOAD. IN EFFECT, THE GEN SET IS
 NOW COMPLETELY ISOLATED FROM THE UTILITY SERVICE AND
 PRESENTS AN EFFECTIVE AND SAFE ALTERNATIVE TO SOLID
 NEUTRAL LINES. A DESIGNER HAS THE TOOLS TO NOW
 CONFIGURE A STANDBY SYSTEM AS EITHER SEPARATELY DERIVED
 OR NOT. IF THE SYSTEM NEEDS ARE FOR NOT GROUNDING THE
 GEN SET AT ITS SITE THEN A THREE POLE TRANSFER SWITCH
 WITH A SOLID NEUTRAL SHOULD BE EMPLOYED. IF THE GEN SET
 NEEDS TO BE GROUNDED AT ITS SITE, THEN A FOUR POLE
 TRANSFER SWITCH MUST BE DESIGNED INTO THE SYSTEM. THIS
 WILL INSURE THAT THE NEUTRAL IS SWITCHED ISOLATING THE
 NORMAL OR UTILITY SUPPLY. LASTLY, SHOULD THE DESIGNER
 DECIDE TO SWITCH THE NEUTRAL, CONSIDERATION TO CONTACT
 RATINGS AND PERFORMANCE SHOULD BE TAKEN INTO ACCOUNT.
 FOURTH POLE AND UL REQUIREMENTS
 AS OF APRIL 1989, UL 1008 REQUIRED THAT THE FOURTH POLE
 OF A TRANSFER SWITCH BE TESTED AND PROVEN TO HAVE
 RATINGS EQUAL TO ITS PHASE CONTACTS IF NOT OF THE SAME
 CONSTRUCTION. AND THAT BUS SPACING IS CLOSER TO LINE
 THAN ITS LINE TO LINE SPACING OR IT HAS A DIFFERENT
 MEANS OF SUPPORT FOR ITS NEUTRAL BUS. THAT MEANS THAT
 THE NEUTRAL CONTACT MUST BE CAPABLE OF WITHSTAND AND
 CLOSE INTO FAULT RATINGS AT LEAST EQUAL TO THE PHASE
 CONTACTS. THE FACT IS, NOT ALL TRANSFER SWITCHES
 EMPLOYING A FOURTH POLE ARE CONSTRUCTED IN LIKE
 FASHION.
  
 AS NOTED ABOVE THE USE OF 4-POLE TRANSFER SWITCHES IS
 NEEDED. PLEASE SHOW ON PLANS THE SEPARATELY DERIVED
 GROUNDING ELECTRODE SYSTEM AT THE GENERATOR.
  
 8) NOTE: PLEASE SEE PANEL LP4 ON THE SECONDARY SIDE OF
 THE TRANSFORMER REQUIRES A MAIN CIRCUIT BREAKER PER
 240.21, 408.36.
  
 9) NOTE: PLEASE COMPLETE ALL INFORMATION ON PLANS AND
 SUPPORTING DOCUMENTS FOR COMPLIANCE WITH THE FBC AND
 CHAPTER 13.
 PLEASE KNOW THE MINIMUM REQUIRES FEDERALLY ADOPTED INTO
 LAW IN JULY 04 WAS THAT ALL STATES ARE REQUIRED TO MEET
 THE MINIMUM OF 1999 ASHRAE 90.1 OR BETTER BY THE NEXT
 CODE CYCLE. PLEASE SEE THE FBC AND CHAPTER 13 FOR ALL
 ITEMS.
 THIS NOTE WILL BE DONE INS SUB-SECTIONS AND THE INPUT
 DATA REPORT WILL BE NOTED AS IDR.
  
 A) PLEASE BE SURE TO SEE 13-415.1.ABC.1.1, .1.2, .1.3
 AND .1.4 FOR ALL LIGHTING CONTROLS REQUIRED. PLEASE SEE
 THERE ARE SEVERAL LOCATIONS WHICH ARE MISSING REQUIRED
 CONTROLS.
 FOR EXAMPLE:
 MISSING SEPARATE SPACES OVER RIDES AND LIGHTING
 CONTROLS.ALL OVER RIDES ARE REQUIRED FOR SYSTEM
 CONTROLS.
 SOME EXAMPLES OFROOMS MISSING REQUIRED CONTROLS:
 143,008,105,105A,108,109,122,168,139 ETC THIS IS NOT
 ALL LOCATIONS AND ONLY GIVING A FEW AS EXAMPLES.
 MISSING LIGHTING ZONES AS REQUIRED.
 MISSING BACK UP TIME FOR OUTSIDE LIGHTING PROGRAMMING
 WHICH CODE SECTION ABOVE REQUIRES A 10HR MINIMUM.
 PLEASE SEE MISSING CONTROLS AND DETAILS FOR OUTSIDE
 LIGHTING.
  
 B) PLEASE SEE 13-413.1.ABC.2.1 AND .2.2 AND PLEASE
 PLACE REQUIRED NOTES ON PLANS ACCORDINGLY.
  
 C) PLEASE SEE 13-413.1.ABC.1.1 AND .1.2 AND SUBMIT
 VOLTAGE DROP CALCULATIONS FOR ALL WORST CASE. PLEASE
 SEE THERE ARE BRANCH CIRCUITS AND FEEDERS WHICH ARE IN
 QUESTION DUE TO THE LONGER LENGTHS AS SHOWN ON PLANS.
  
 D) PLEASE BE SURE ALL LIGHTING ON PLANS COORDINATES
 WITH THE LIGHTING ON THE IDR SUBMITTED WITH THE ENERGY
 CALCULATIONS. PLEASE KNOW AT THIS TIME THERE ARE
 SEVERAL HUNDRED FIXTURES/LUMINAIRES MISSING FORM THE
 IDR.
 PLEASE SEE FOR EXAMPLE: THE IDR FOR EXTERIOR LIGHTING
 SHOWS NOT ONE FIXTURE. HOW IS THIS POSSIBLE WHEN THERE
 ARE HUNDRED(S) OF LUMINAIRES ONPLANS???
 PLEASE SEE FOR EXAMPLE: THE LIGHTING SHOWN ON THE
 FIXTURE LEGEND DOES NOT CORRELATE WITH THE IDR FOR
 DOZENS OF FIXTURES FOR THE CORRECT WATTAGES. PLEASE SEE
 13-415.2.ABC.1, .1.1, .1.2 AND .1.3 FOR VA RATINGS TO
 BE USED IN CALCULATIONS.
 THIS SHALL INCLUDE ALL ACCENT LIGHTING SUCH AS TRACK
 LIGHTING WHICH IS NOTED SPECIFICALLY IN THE CODES ABOVE
 ALONG WITH THE VA TO BE FIGURED FOR COLD CATHODE
 LIGHTING NOTED ON SPECIALTY LIGHTING PLANS.
  
 E) PLEASE BE SURE TO SHOW AND INDICATE ALL LIGHTING
 FIXTURE DESIGNATIONS ON PLANS. PLEASE SEE SOME
 LOCATIONS DO CONTAIN A NOTE FOR TYPES OF FIXTURES
 HOWEVER MANY AREAS DO NOT CONTAIN DESIGNATIONS WHICH
 COORDINATE WITH THE FIXTURE LEGEND.
 EXAMPLE: ARE 102
  
 F) PLEASE COORDINATE ELECTRICAL WATER HEATERS ON
 PLANS/EQUIPMENT SCHEDULE WITH THAT OF THE UNITS SHOWN
 ON THE IDR. THE IDR APPEARS TO SHOW MORE THAN THE UNITS
 ON EQUIPMENT SCHEDULE.
  
 ** PLEASE SEE THAT THE NOTES ABOVE WITH RESPECT TO FBC
 CHAPTER 13 ARE SOME OF THE ITEMS GIVEN AS EXAMPLES AND
 ARE IN NO WAY ALL ITEMS. PLEASE SEE COMMENTS FROM OTHER
 TRADES FOR THE SAME CHAPTER.
  
 10) NOTE: PLEASE SUBMIT SITE LIGHTING PLANS. UNABLE TO
 REVIEW AT THIS TIME.
 NEC 2005, FBC CHAPTER 13
 FBC ADMIN SECTION 106.1.2, 106.3.5.1.2 FOR ADDITIONAL
 INFORMATION.
  
 11) NOTE: PLEASE SUBMIT EMERGENCY EGRESS PHOTO-METRICS
 FOR ALL EGRESS PATHS INCLUDING ALL STAIR AREAS. PLEASE
 SEE 7.8.1.3, 7.9.2.2 AS THE LIGHTING LEVELS FOR STAIRS
 UNDER NORMAL CONDITIONS ARE REQUIRED AT 10FT CANDLES
 MINIMUM.
 PLEASE SEE THAT ALL REQUIRED EGRESS PATHS, MAIN
 ELECTRICAL ROOMS, ELEVATOR EQUIPMENT/MACHINE ROOMS ETC
 SHALL CONTAIN BATTERY BACK UP TYPE FIXTURES TO PROVIDE
 THE 1FT CANDLE MINIMUM FOR THE *EGRESS PATHS*. PLEASE
 SEE 7.8.1.2.2 AND 7.8.2.
 COULD NOT LOCATE FIXTURES ON FIXTURE LEGEND WITH THE
 REQUIRED BATTERY BACK UP.
 PHOTO-METRICS ARE REQUIRED AND AS NONE HAVE BEEN
 SUBMITTED AT THIS TIME NO REVIEW CAN BE DONE. FLORIDA
 ADMINISTRATIVE CODE 61G15-33.004
 FBC 106.1.2
  
 12) NOTE: PLEASE PROVIDE GROUND RISE ON ONE-LINE SHEET
 OR OTHER SHEET PER 250.58. ALSO AS NOTED ABOVE WITH
 RESPECT TO THE GENERATOR AND SEPARATELY DERIVED SYSTEMS
 PER 250.20, 250.30. THE NOTE ON RISER SHEET FOR
 TRANSFORMER GROUND IS OK.
  
 13) NOTE: PLEASE INDICATE COLOR CODING FOR THE 277/480V
 SYSTEM AS FOLLOWS.
 BROWN, PURPLE AND YELLOW.
 THIS LOCAL JURISDICTION EXISTINGWIRING SYSTEMS ARE AS
 NOTED ABOVE INCLUDING OTHER LOCAL JURISDICTIONS AS THE
 NEC DOES NOT PROVIDE COLOR CODING NEEDED FOR THESE
 VOLTAGES. THE ORANGE MARKING AS NOTED IN THE NEC IS FOR
 THE HIGH-LEG OF AN OPEN DELTA SYSTEM.
 90.4
  
 14) NOTE: PLEASE SUBMIT THE MANUFACTURES SPECS/CUT
 SHEETS ON THE PROPOSED UPS SYSTEM. PLEASE BE SURE
 DOCUMENTS CONTAIN A LISTING FROM A NRTL. (NATIONALLY
 RECOGNIZED TESTING LABORATORY).
 110.3, 90.7.
 FBC 106.1.2 FOR ADDITIONAL INFORMATION.
  
 15) NOTE: PLEASE SEE NOTE ONE E001 MENTIONS TO SEE E361
 FOR DETAILS ON THE GENERATOR HOWEVER NO DETAILED
 SPECIFIC INFORMATION COULD BE LOCATED.
 PLEASE SEE OCTAGONAL NOTE #15 FOR EXAMPLE.
 PLEASE SEE OTHER SHEETS ON PLANS SUBMITTED CONTAIN
 OTHER NOTES IN BOXES AND OCTAGONAL NOTES HOWEVER THE
 NOTES DO NOT MATCH OR THE NOTE IS NOT ON ANY LEGEND OR
 DETAIL ON SHEET TO LOCATE INFORMATION.
 PLEASE SEE ONE EXAMPLE BESIDES ONE NOTED ABOVE: SHEET
 E210 NOTES 4 AND 6 WHICH ARE IN LISTED NOTED. ONLY ONE
 NOTE/ SQUARE BOX #6 WAS LOCATED ON SHEET, WHERE IS NOTE
 #4?
 OCTAGONAL NOTES ON E355, E14, E17, ???
 ** PLEASE GO THROUGH ALL SHEETS AND UPDATE NOTES, ETC
 THIS NOTES ONLY SOME ITEMS. SOME OTHERS NOTED ABOVE WAS
 THE MISSING FIXTURE DESIGNATIONS OR NOTES/BOXES ETC FOR
 THE FIXTURES.
  
 16) NOTE: PLEASE SEE THE ALARM DEVICE LOCATIONS AS
 NOTED ON PLANS SHEET E-210 MAKE NOTE TO SEE
 ARCHITECTURAL SHEETS FOR LOCATIONS AND DEVICE HEIGHTS.
 THIS REVIEWER COULD NOT READILY LOCATE THESE ON
 ARCHITECTURAL SHEETS. PLEASE PROVIDE DETAILED
 INFORMATION ON THE ELECTRICAL PLANS OR ADD DEVICES TO
 E-SHEETS.
 PLEASE PROVIDE A RESPONSE WHERE THESE ITEMS ARE
 LOCATED.
 FBC 106.3.5.1.2, 106.1.2 FOR ADDITIONAL INFORMATION.
 SEE THE NEXT NOTE:
  
 17) NOTE: PLEASE INCLUDE ALL MINIMUM LEVELS FOR FLORIDA
 ADA COMPLIANCE.
 PLEASE SEE FBC 2004 11-4.28.1, .2 AND .3(4) MORE
 SPECIFICALLY. THE LEVELS FOR ALL DEVICES TO MEET
 MINIMUM ADA LEVELS NEED TO BE NOTED ON PLANS AS WELL AS
 ADJUSTING THE DEVICES NOTED ON PLANS.
 FOR EXAMPLE: STROBES SHOWN AT LEVELS WAY BELOW THE
 MINIMUM LEVELS REQUIRED FOR ADA. (15CD ETC, WHEN
 REQUIRES TO BE 75CD MINIMUM).
  
 18) NOTE: PLEASE SEE FBC 3006.2, .4 ETC AND POSSIBLE
 COMMENTS FROM OTHER TRADES. PLEASE KNOW THE ELEVATOR
 MACHINE ROOMS ARE REQUIRED MEETING INDIVIDUAL AIR
 CONDITIONING AS WELL AS VENTILATION REQUIREMENTS.
 PLEASE SEE NEC 620.21-620.25. AT THIS TIME THERE ARE
 ITEMS IN THESE ROOMS AND OTHER EQUIPMENT WHICH IS
 REQUIRED TO BE ON DEDICATED CIRCUITS YET THEY FEED
 OTHER AREAS. SEE THE FOLLOWING COMMENT WHICH DIRECTLY
 AFFECT THIS NOTE.
 PLEASE SEE FOR EXAMPLE: THE LIGHTING IN THE MACHINE
 ROOM IS REQUIRED TO BE ON A DEDICATE CIRCUIT YET PLANS
 SHOWS THIS SAME CIRCUIT FEEDING OTHER AREAS/ROOMS WHICH
 IS NOT PERMITTED.
  
 19) NOTE: PLEASE SEE THE PLANS SHOWS CIRCUITS FOR MUCH
 OF THE EQUIPMENT FOR ESCALATOR AND ELEVATOR TO A Y1
 PANEL YET NO Y PANEL COULD BE LOCATED IN PANEL
 SCHEDULES OR LOCATED ON RISER. WHAT IS THIS PANEL? NEC
 240.4,310.16, 408, 620 ETC
 FBC 106.3.5.1.2, 106.1.2 FOR ADDITIONAL INFORMATION.
  
 20) NOTE: PLEASE SEE 620.213 AND ASME A17.1-2004,
 SAFETY CODE FOR ELEVATORS AND ESCALATORS, REQUIRES A
 MINIMUM OF 5 FT-CANDLES (54 LUX) AT THE PIT FLOOR AND
 REQUIRES LUMINAIRES TO BE EXTERNALLY GUARDED TO PREVENT
 ACCIDENTAL BREAKAGE.
 PLEASE INCLUDE IN THE PHOTO-METRIC CALCULATIONS AS
 NEEDED ABOVE FOR EGRESS PATHS. MAY SUBMIT ONE AS
 TYPICAL FOR BOTH.
  
 21) NOTE: PLEASE SUBMIT MORE DETAIL FOR THE RTCU
 CONTROL PANELS WHICH THE GFI RECEPTACLES FOR ROOFTOP
 EQUIPMENT IS BEING SHOWN. THESE ARE 277/480V UNITS, AND
 NOT CLEAR WHAT THESE PANELS ARE AT THIS TIME. PLEASE
 CLARIFY.
  
 22) NOTE: PLEASE SEE ROOM LOCATED ON SHEET E131 WHICH
 IS TO THE LEFT AND DOWN FROM AREA/ROOM 122. THIS ROOM
 DOES NOT APPEAR TO SHOW ANY DOORS.
 FBC 106.1.2
  
 23) NOTE: PLEASE KNOW THE RATINGS OF THE MAIN
 ELECTRICAL ROOM 145 AND ELECTRICAL DISTRIBUTION ROOM
 116 NEEDS TO BE VERIFIED. PLEASE KNOW AS FULL FIRE
 SPRINKLER PLANS WERE NOT SUBMITTED THE ROOM RATING
 NEEDS TO BE VERIFIED.
 THIS INFORMATION WILL BE GONE OVER WITH THE BUILDING
 REVIEWER WHEN BUILDING REVIEW IS DONE. COULD NOT
 READLIY LOCATE ON THE ARCHITECTURAL SHEETS THE RATING
 OF THESE ROOMS.
 MAY BE 3HRS OR AT THE LEAST 1HR. 450.42
 WILL ALSO NEED MORE INFORMATION ON THE VENTILATION
 TAKING PLACE IN THESE ROOMS ONCE THE MECHANICAL REVIEW
 TAKES PLACE.
 PLEASE PROVIDE TEMPERATURE RISE AND EQUIPMENT HEATING
 WILL NEED TO BE GONE OVER.
  
 24) NOTE: PLEASE SEE THE PANEL SCHEDULES NOTE A *HANDLE
 LOCK-OFF DEVICE* ON SOME ITEMS. PLEASE BE SURE TO
 VERIFY THE DEVICES BEING NOTED AS MANY OF THESE ITEMS
 ARE ONLY LISTED FOR TEMPORARY USE AND IF A DEVICE IS TO
 BE PERMANENTLY INSTALLED IN LIEU OF A REQUIRED
 DISCONNECT THE LOCK OFF DEVICE SHALL BE AN INTEGRAL
 PART OF THE BREAKER ASSEMBLY.
 PLEASE PROVIDE NOTE ACCORDINGLY AND PLEASE KNOW THIS
 WILL BE VERIFIED IN FIELD BY THE ELECTRICAL INSPECTOR
 AND FINAL DETERMINATION BY THE AHJ.
 110.3, 90.4, 90.7.
  
 25) NOTE: PLEASE SEE 210.8B2 INTHE 2005 NEC AS GFI
 PROTECTION IS REQUIRED FOR ALL 120V 15/20 AMP CIRCUITS
 IN KITCHENS.
 PLANS DO NOT SHOW PROTECTION, EQUIPMENT SCHEDULE DOES
 NOT SHOW PROTECTION AND COULD NOT LOCATE THE BREAKERS
 IN PANELS FOR REQUIRED PROTECTION.
 PLEASE PROVIDE AND ADJUST PLANS.
  
 26) NOTE: PLEASE CLARIFY ACCESS TO THE EDR 116, WHICH
 APPEARS TO BE SHOWN THROUGH A ROOM 115. WHAT IS THIS
 ROOM 115?
 PLEASE SEE A351 WHICH INDICATES THE ROOM SHOWN AS 116
 ON ELECTRICAL PLANS AS 129 ON A-SHEETS. PLEASE
 COORDINATE.
 **MAY NOT ACCESS THROUGH A STORAGE, OFFICE ROOM AS THIS
 CLEARLY WOULD INTERFERE WITH THE MEANS OF EGRESS
 PATHS.
 THIS MAY ALSO BE NOTED BY THE FIRE MARSHAL AND BUILDING
 REVIEWER(S).
 PLEASE CLARIFY.
 LS 101, NEC ACCESS TO ELECTRICAL ROOM 110.26, 240.24
  
 27) NOTE: PLEASE SEE KNOW THE CODE WILL REQUIRE A
 NEUTRAL CONDUCTOR TO THE FIRST MEANS OF DISCONNECT FOR
 EACH OF THE ATS DEVICES. RISER SHOWS (7) WITH 3W, WHICH
 LENDS TO NO NEUTRAL CONDUCTORS. PLEASE KNOW THAT
 WHETHER OR NOT THE UNIT IS SEPARATELY DERIVED THIS IS
 REQUIRED.
 250.6, 250.24, 250.20 ETC
  
 28) NOTE: PLEASE INDICATE THE SIZES OF BRANCH CIRCUIT
 CONDUCTORS ON THE PANEL SCHEDULES. AS THE VD
 CALCULATIONS HAVE NOT BEEN SUBMITTED AND THESE ARE NOT
 SHOWN AT THIS TIME ON PANEL SCHEDULES, UNABLE TO VERIFY
 ALL.
 240.4, 310.16.
 FBC 106.1.2, 106.3.5.1.2FOR ADDITIONAL INFORMATION.
  
 29) NOTE: PLEASE PROVIDE NOTES ON PLANS FOR REQUIRED
 SIGNAGE FOR ARC FLASH PROTECTION. 110.16
  
 30) NOTE: PLEASE INCLUDE DISCONNECTING MEANS FOR ALL
 FEEDERS FROM GENERATOR TO BUILDING. PLEASE SEE,
 225.31-225.39, 700.12B6, 701.11B6, AND 702.11B6. PLEASE
 KNOW BASED ON NOT HAVING THE INFORMATION ON THE
 BREAKERS FOR THE GENERATOR, THE CODE REQUIRES THE MEANS
 OF DISCONNECT TO BE *WITHIN SIGHT* AND *READILY
 ACCESSIBLE*. PLEASE SEE NEC ART 100 FOR DEFINITIONS.
 PLEASE ALSO KNOW AS THERE MAY BE ZONING AND OTHER
 REQUIREMENTS WHICH MAY REQUIRED FENCING/WALLS/AND
 LANDSCAPING THE BREAKERS MAY NOT BE READILY ACCESSIBLE.
 PLEASE ALSO KNOW THAT BASED ON THE GENERATOR AND THE
 LOCATION OF THIS UNIT THESE MAY BE INSIDE A LOCKED
 ENCLOSURE. THIS BEING SAID SEPARATE DISCONNECTSWHICH
 ARE NOT REQUIRED TO CONTAIN OVER CURRENT PROTECTION
 WILL BE REQUIRED AT THE BUILDING OR IN CLOSE PROXIMITY
 TO BE DETERMINED BY THIS OFFICEAND THE FIRE MARSHAL.
  
 31)NOTE: PLEASE KNOW ALTHOUGH NOT REQUIRED, A
 RESPONSE LETTER WILL BE HELPFUL IN THE FOLLOWING
 REVIEW.
  
 ** THIS OFFICE EXPRESSES THAT IF THERE ARE ANY
 COMMENTS, QUESTIONS OR CLARIFICATION NEEDED TO PLEASE
 DO NOT HESITATE IN CONTACTING THIS OFFICE.
 PLEASE SEE BELOW FOR CONTACT INFORMATION.
  
 * ** IMPORTANT**
 ONCE ALL REVIEWS ARE DONE AND PLANS ARE PICKED UP FOR
 CORRECTIONS, PLEASE BE SURE TO COMPLETELY REMOVE ALL
 OLD/VOIDED SHEETS AND ONLY INSERT NEW REVISED SHEETS
 INTO TWO COMPLETE SETS FOR REVIEW AND STAMPING. DO NOT
 LEAVE ANY OLD/VOIDED SHEETS IN SETS.
 PLEASE DO NOT ATTACH SUPPORTING DOCUMENTS TO PLANS. ANY
 ADDITIONAL DOCUMENTATION SUCH AS PRODUCT APPROVALS,
 SPEC/CUT SHEETS, CALCULATIONS ETC SHOULD BE PLACED INTO
 TWO SETS/FOLDERS/BINDERS ETC.
 PLEASE KNOW ONLY ONE SET OF THE OLD/VOIDED SHEETS
 SHOULD BE SUBMITTED FOR REFERENCE.
 THIS WILL HELP IN THE REVIEW PROCESS AND AVOID ANY
 DELAYS.
  
 DEWEY PALMER
 ELECTRICAL PLAN REVIEW II
 CONSTRUCTION SERVICES DEPT.
 CITY OF WEST PALM BEACH
 561-805-6717
 [email protected]
2008-03-07 19:04:112008-03-07 19:04:11
  
 REVIEW CONTINUED 3/7, IN PROGRESS TO CONTINUE 3/8,
 NOTES TO FOLLOW ONCE COMPLETED.
2008-02-16 19:56:142008-02-16 19:56:14
  
 REVIEW STOPPED,ELECTRICAL REVIEW WILL CONTINUE AFTER
 2/29. PLANS WILL GO INTO *F* STATUS AT THAT TIME AND
 NOTES WILL BE POSTED ONCE REVIEW IS COMPLETED.
2008-02-16 19:04:462008-02-16 19:04:46
  
 ONE ROLL IN ELECTRICAL FOR REVIEW.