| 2008-05-23 14:23:53 | GAS PLAN REVIEW: |
| | DENIED 2ND TIME: |
| | |
| | PLAN REVIEW UNDER THE 2004 FLORIDA BUILDING CODES WITH |
| | 2007 REVISIONS, CITY OF WEST PALM BEACH AMENDMENTS TO |
| | CHAPTER 1 (W.P.B.), FLORIDA ADMINISTRATIVE CODE |
| | (F.A.C.), AND FLORIDA STATUTES (F.S.). |
| | |
| | THE FOLLOWING COMMENTS ARE NUMBERED TO CORRESPOND WITH |
| | THE PREVIOUS GAS REVIEW COMMENTS AS WELL AS THE |
| | DESIGNER'S RESPONSES FOR THE PURPOSE OF CONTINUITY. NEW |
| | COMMENTS WILL BE SO NOTED FOLLOWING THE PREVIOUS REVIEW |
| | COMMENTS. |
| | |
| | |
| | 1. "OK" COMMENT ADDRESSED. |
| | |
| | 2. "OK" COMMENT ADDRESSED. |
| | |
| | 3. SHOW THE DISTANCE FROM THE POINT OF |
| | DELIVERY, (METER), TO THE MOST REMOTE |
| | OUTLET IN THE BUILDING AND/OR SYSTEM PER |
| | FBC-2004 FUEL GAS CODE APPENDIX A - USE |
| | OF CAPACITY TABLES A.3.1(4). |
| | |
| | **RESPONSE NOTED, HOWEVER PER OUR MEETING ON 4/10/08 |
| | IT WAS STATED THAT THERE WERE EXISTING GAS APPLIANCES |
| | AND GAS PIPING IN THE EXISTING MAIN RESIDENCE AND THAT |
| | THE EXISTING LONGEST LENGTH AND BTU LOAD WOULD BE |
| | INDICATED ON THE RESUBMITTED GAS RISER FOR THE EXISTING |
| | MAIN RESIDENCE. THAT INFORMATION IS NOT ON THE |
| | RESUBMITTED GAS RISER AND IS REQUIRED DUE TO THE FACT |
| | THAT GAS SYSTEMS ARE SIZED BY THE LONGEST LENGTH AND |
| | BTU LOADS. PER FBC-2004 FUEL GAS SECTION 401.1 SCOPE. |
| | |
| | 4. "OK" COMMENT ADDRESSED. |
| | |
| | 5. "OK" COMMENT ADDRESSED. |
| | |
| | 6. "OK" COMMENT ADDRESSED. |
| | |
| | **THE FOLLOWING ARE NEW COMMENTS** |
| | |
| | 7. SHEET B5 GAS RISER: PER THE RESUBMITTED INFORMATION |
| | THAT THE DELIVERY PRESSURE IS 0.5 PSI AND THE LONGEST |
| | LENGTH IS 129' THE GAS PIPING IS UNDER SIZED PER |
| | FBC-2004 FUEL GAS TABLE 402.4(2). REFERENCE THE RED |
| | LINE CORRECTIONS TO THE RISER DIAGRAM AS WELL AS THE |
| | ATTACHED TABLE TO THESE COMMENTS INDICATING THIS. |
| | NOTE: UNTIL COMMENT #3 IS FULLY ADDRESSED THIS IS ONLY |
| | A REVIEW OF WHAT INFORMATION IS ON THE RESUBMITTED GAS |
| | RISER AND COULD CHANGE IF THE EXISTING GAS SYSTEM HAS A |
| | LONGER LENGTH OF 129'. |
| | |
| | 8. SHEET B5 GAS RISER: IF THE DELIVERY PRESSURE IS |
| | ONLY 0.5 PSI WHY IS A MAIN REGULATOR BEING INDICATED |
| | FOR THE ACCESSORY BUILDING? THIS REGULATOR IS NOT |
| | REQUIRED FOR 0.5 PSI SYSTEMS. PLEASE CLARIFY THIS PER |
| | FBC-2004 FUEL GAS SECTION 401.1 SCOPE. |
| | |
| | 9. SHEET B5 GAS RISER: PLEASE KNOW THAT THE FITTING |
| | FOR THE WTR/HTR AND GENERATOR DOES NOT EXIST AND SHOULD |
| | BE CLEARLY INDICATED AS TWO SEPERATE TEES ON THE |
| | RESUBMITTAL. PER FBC-2004 FUEL GAS SECTION 401.1 |
| | SCOPE. |
| | |
| | 10. SEE MECHANICAL COMMENTS #3 AND #4 AND COMPLY. |
| | |
| | ********IMPORTANT INFORMATION******** |
| | WHEN RESUBMITTING PLANS, PLEASE PROVIDE A COPY OF THE |
| | OLD PLANS, CLEARLY INDICATE THE REVISION ON THE NEW |
| | PLANS, REMOVE AND REPLACE ANY PAGES AS NECESSARY. A |
| | TRANSMITTAL LETTER LISTING THE ORIGINAL REVIEW COMMENT |
| | NUMBER, WITH A DESCRIPTION OF THE REVISION MADE, |
| | IDENTIFYING THE SHEET OR SPECIFICATION PAGE WHERE |
| | CHANGES CAN BE FOUND WILL HELP TO EXPEDITE YOUR PERMIT. |
| | THANK YOU FOR YOUR ANTICIPATED COOPERATION. |
| | |
| | END OF COMMENTS: |
| | |
| | REVIEW BY: MIKE PERSON |
| | PLUMBING PLANS EXAMINER |
| | PHONE= (561) 805-6730 |
| | FAX= (561) 805-6731 |