| Date |
Text |
| 2008-02-27 14:17:28 | FAILED FOR FOLLOWING REASONS: |
| | |
| | 1.ORDINANCE NO. 4060-07: |
| | |
| | ALL DEMOLITION AND NEW CONSTRUCTION PERMITS, WITH |
| | EXCEPTION OF SINGLE FAMILY, DUPLEX AND ACCESSORY |
| | APARTMENT, SHALL POST BONDS OR DEPOSITS FOR THE |
| | FOLLOWING: |
| | |
| | 1. EROSION CONTROL, AND |
| | 2. LAND STABILIZATION |
| | |
| | THE AMOUNT OF THE EROSION CONTROL AND LAND |
| | STABILIZATION BONDS SHALL BE DETERMINED BY THE ENGINEER |
| | OF RECORD USING THE CURRENT CITY COST SCHEDULE AND |
| | VERIFIED BY THE CITY'S ENGINEERING SERVICES DEPT. |
| | PLEASE CONTACT BRIAN MOREE, ENG SERVICES CONSTRUCTION |
| | SUPERVISOR, AT 561- 494 -1040 FOR MORE INFORMATION. |
| | |
| | UPON VERTICAL CONSTRUCTION COMMENCEMENT, PAYMENT IN |
| | FULL OF ALL APPLICABLE FEES, AND COMPLIANCE WITH ALL |
| | TERMS AND CONDITIONS OF ANY POSTED BOND, THE PERMITTEE |
| | MAY REQUEST RELEASE OF THE BONDS OR DEPOSITS. |
| | |
| | A COPY OF ORDINANCE NO. 4060-07 MAY BE OBTAINED FROM |
| | THE CITY CLERK'S OFFICE LOCATED ON THE FIRST FLOOR. |
| | |
| | 2. PLEASE SHOW ON CALCULATION THAT YOU HAVE CONSIDERED |
| | FLOOD ZONE AREA, & 5,10, 25, 100 YEAR FLOOD CRITERIA |
| | AND CROWN OF THE ROAD WHEN YOU DETERMINE THE FIRST |
| | FLOOR ELEVATION. FIRST FLOOR ELEVATION SHOULD BE |
| | ATLEAST1 1/2 FEET HIGHER THAN HIGHEST CROWN OF THE |
| | ROAD. YOU NEED TO PROVIDE WATER QUALITY CALCULATIONS |
| | AND THIS CALCULATIONS ARE TO BE APPROVED FROM 1000 45TH |
| | STREET ENGINEERING BEFORE WE APPROVE. |
| | |
| | 3. PLEASE SHOW ON DRAINAGE DRAWINGTHE SITE AREA, |
| | GREEN, LAKE,PARKING AREA, IMPERVIOUS,PERVIOUS AREAYOU |
| | ARE DEVELOPING FOR THIS PROJECT . PLEASEMAKE SURE |
| | THESE AREAS SHOWN ON DRAINAGE DRAWINGS MUST MATCH WITH |
| | AND USED IN STORM WATER QUALITY CALCULATIONS. PLEASE |
| | PROVIDE A COPY OF THESE CALCULATIONS. |
| | |
| | 4. PLEASE SHOW ALL STORM WATER PIPES AROUND YOUR SITE |
| | SO, WE CANSEE THE LAYOUT OF STORM WATER PIPES FROM |
| | ALL OTHER STORM WATER PIPES. PLEASE SHOW DETAIL OF THE |
| | CONTROL STRUCTURESWITH ELEVATIONS, NOTCHES, BLEEDING |
| | ELEVATION, ETC ON DRAWINGS, CALCULATION FOR |
| | EXFILTRATION TRENCHES, PLEASE SHOW DRY DETENTION/WET |
| | DETENTION AREAS IN STORM WATER CALS IF YOU HAVE ALL |
| | THESE. PLEASE RESUBMIT GEO-TECH REPORT AND ALL |
| | ENVRONMENTAL REPORT. |
| | |
| | |
| | PLEASE RESPOND EACH ITEM IN DETAIL TO EXPEDITE YOUR |
| | PERMITTING PROCESS |
| | |
| | RASIK CHOKSHI805-6723 |