| Date |
Text |
| 2008-06-03 16:06:46 | ALL PREVIOUS PLAN REVIEW COMMENTS HAVE BEEN ADEQUATELY |
| | ADDRESSED RELATED TO THE PLANS. PLANS HAVE BEEN STAMPED |
| | AS REVIEWED FOR CODE COMPLIANCE. THE FOLLOWING ISSUES |
| | ARE OUTSTANDING: |
| | |
| | 1. THIS IS A THRESHOLD BUILDING AND AS SUCH, THREE |
| | COMPLETE SETS OF PLANS, SPECIFICATIONS AND SUBMITTALS |
| | ARE REQUIRED FOR PERMIT. PLEASE COLLATE AND SUBMIT |
| | THREE COMPLETE SETS OF ALL PERMIT DOCUMENTATION |
| | (INCLUDING PRODUCT APPROVALS, SUCH AS FOR THE |
| | PRE-ENGINEERED A/C STANDS) FOR PERMIT. |
| | |
| | 2. THE WINDLOAD REPORT SUBMITTED BY THE MECHANICAL |
| | DESIGNER HAS NOT SUCCESSFULLY PASSED A BUILDING PLAN |
| | REVIEW. THE INFORMATION ON FANS, GRAVITY VENTS AND |
| | CONDENSING UNITS IS SUFFICIENT, BUT THERE ARE NOT THREE |
| | COPIES SUBMITTED. THE INFORMATION PROVIDED FOR THE |
| | ROOFTOP PACKAGE UNITS IS NOT ADEQUATE AS IT IS A REPORT |
| | FROM 1993. THERE HAVE BEEN MANY CHANGES TO THE CODES |
| | AND RELATED REFERENCE STANDARDS SINCE THAT TIME. |
| | |
| | BASED ON THE LANGUAGE IN FBCM 301.13, THE MANUFACTURER |
| | OF THE APPLIANCES, WHO IS RESPONSIBLE FOR THE DESIGN OF |
| | THE APPLIANCES, SHALL CERTIFY THAT THE APPLIANCES ARE |
| | DESIGNED TO WITHSTAND ANTICIPATED WIND PRESSURES IN |
| | ACCORDANCE WITH FBCB CHAPTER 16. ONCE THIS BECOMES THE |
| | ONLY OUTSTANDING ISSUE RELATED TO MECHANICAL. A PASSED |
| | STATUS WILL BE ENTERED AND THE MISSING WIND LOAD |
| | INFORMATION WILL BE COVERED IN A PROVISO IN ORDER TO |
| | ALLOW THE PROJECT TO MOVE FORWARD WHILE MISSING |
| | INFORMATION IS OBTAINED AND SUBMITTED. |