Plan Review Notes
Plan Review Notes For Permit 07080679
Permit Number 07080679
Review Stop ENG
Sequence Number 1
Notes
Date Text
2007-09-07 13:46:24***FAILED**** PLEASE PROVIDE THE FOLLOWING:
  
 WE HAVE NOT FOUND CIVIL DRAWINGS & ENG REVIEW INFO IN
 YOUR PACKAGE YOU SUBMITTED FOR THIS PERMIT.JUST TO
 LET YOU KNOW A HEAD OF TIME THATWE NEED FOR ENG
 REVIEWSTORM WATER CALS, POLLUTION PREVENTION PLANS,
 CITY STANDARDS SHOWN ON DRAWINGS ETC, ETC.THEREFORE,
 WE ARE ASKING YOU TO INCLUDE THE FOLLOWING WHEN YOU
 SUBMIT CIVIL DRAWINGS FOR ENGINEERING REVIEW, SO WE CAN
 EXPEDITE OUR ENG REVIEW PROCESS.
  
 1. PLEASE PROVIDE A COPY OF NOTICE OF INTENT (NOI).
 PLEASE APPLY AT FDEP, NPDES STORMWATER SECTION FOR
 NOI.
 YOU CAN GET NOI INFO FROM
 WWW.DEP.STATE.FL.US/WATER/STORMWATER/NPDES/
 NOTICE OF INTENT DEP FORM 62-621.300(4)(B),
 EFFECTIVE MAY 1, 2003
 2. PLEASE SHOW ON CIVIL DRAWING THE SITE PLAN SHOWING
 STREETS/ROADS AROUND THE SITE WITH NORTH ARROW.
 3.PLEASE SHOW ON DRAWING ALL CITY STANDARDS NOTES FOR
 SIDEWALK, DRIVEWAY, APPROACH, PARKINGS, HANDICAP
 PARKINGS, DUMPSTER ENCLOSURE, YOU CAN GET A C D FROM
 1000, 45 STREET FOR ALL THESE CITY STANDARDS NOTES.
 PHONE# 494-1040
 4. PLEASE SHOW ON DRAWINGSDUMPSTER & ITS ENCLOSURE
 DETAILS PER CITY OF WPB, &LOCATION ON DWG, LOCATION
 MUST BE ACCESSIBLE FOR PICKUP TRUCK.
 5. FIRST FLOOR ELEVATION, CENTER LINE OF ROAD ,
 SIDEWALK ELEVATION MUST MEET FLOOD ZONE AREA, & 5,10,
 25, 100 YEAR FLOOD CRITERIATO DETERMINE THE FIRST
 FLOOR ELEVATION, PLEASE SHOW IN YOUR STORM WATER CALS
 THAT HOW DID YOU DETERMINE THE FIRST FLOOR ELEVATION??.
  
 6. PLEASE SHOW ON DRAWINGTHE SITE AREA, YOU ARE
 DEVELOPING FOR THIS PROJECT . PLEASE ALSO SHOW TOTAL
 PERVIOUS,& IMPERVIOUS AREA FOR THIS PROJECT,
 LAKE,SIDEWALK, PARKING,BUILDING AREA ETC. MAKE SURE
 THESE AREAS SHOWN ON DRAWINGS MUST MATCH WITH AND USED
 IN STORM WATER QUALITY CALCULATIONS.
 7. HOW DO YOU CONNECT TO THE STORM WATER PIPES IN YOUR
 SITE? ITS DETAILS.PLEASE SHOW ALL STORM WATER PIPES
 AROUND YOUR SITE SO, WE CANSEE THE LAYOUT OF STORM
 WATER PIPES FROM ALL OTHER STORM WATER PIPES. PLEASE
 SHOW DETAIL OF THE CONTROL STRUCTURESWITH
 ELEVATIONS, NOTCHES, BLEEDING ELEVATION, ETC ON
 DRAWINGS, CALCULATION FOR EXFILTRATION TRENCHES, PLEASE
 SHOW DRY DETENTION/WET DETENTION AREAS IN STORM WATER
 CALS.
 8. ALSO PLEASE SHOW ALL CATCH BASINS NEAREST,AROUND
 YOUR SITE FOR STORM WATER DRAIN.
 9. PLEASE PROVIDE A COPY OF SFWMD PERMIT,, &STORM
 WATER QUALITY CALCULATIONS,
 10. PLEASE SHOW ON DRAWINGS THE POLLUTION PREVENTION
 DETAILS,CLOTHES USED FOR SILT ETC., PLANS SHOWING SILT
 FENCE AROUND THE SITE & CATCH BASINS.HEIGHT OF FENCE
 SHOULD BE HIGH ENOUGH PER FDEP TO STOP DUST &
 PARTICLES.
 11. WATER & SEWER PLANS MUST BE APPROVED FROM 45TH
 STREET (MANNY G.), UTILITY DEPT BEFORE WE APPROVED.
  
 PLEASE RESPOND EACH ITEM IN DETAIL TO EXPEDITE YOUR
 PERMITTING PROCESS
  
 RASIK CHOKSHI805-6723