| Date |
Text |
| 2007-09-18 15:48:53 | REVIEW #: 1 |
| | ACTION: DENIED |
| | |
| | FBC 2004 CODE FAMILY W/ 2005 AND 2006 SUPPLEMENTS |
| | FBC CH.1 AS AMENDED BY THE CITY OF WEST PALM BEACH |
| | |
| | 1. THE DESIGNER OR OWNER MUST SELECT THE LEVEL OF |
| | ALTERATION BEING PROPOSED PER FBC,EB 301.5. |
| | |
| | 2. IS THIS A CHANGE OF OCCUPANCY? SEE FBC,EB 301.4 AND |
| | 306.1. |
| | |
| | 3. VALUE OF WORK HAS NOT BEEN DECLARED. FOR PURPOSE OF |
| | FBC CH,13 COMPLIANCE, IT IS ASSUMED THAT THE WORK |
| | QUALIFIES AS A RENOVATION AS DEFINED IN FBC 13-202. |
| | |
| | 4. AC-1: LOCATION OF CU-2 APPEARS TO BE IN CONFLICT |
| | WITH STAIR LANDING ON WEST ELEVATION. VERIFY REQUIRED |
| | CLEARANCES FOR CU PER FBC,M 304.1. |
| | |
| | 5. AC-1: BATH AND DRYER EXHAUST FROM RESIDENCE WILL BE |
| | DISCHARGING ONTO THE STAIR SHOWN ON WEST ELEVATION. |
| | EXHAUST AIR SHALL NOT BE DIRECTED ONTO WALKWAYS PER |
| | FBC,M 401.5.2. |
| | |
| | 6. AC-1: REFRIGERANT LINES FOR CU-2/AHU-2, IF THEY ARE |
| | TO RUN ABOVE CEILING, THEY MAY BE IN CONFLICT WITJ |
| | STAIR ON WEST ELEVATION WHEN THEY LEAVE THE BUILDING. |
| | PLEASE VERIFY THERE IS NO CONFLICT. FBC 106.1.2. |
| | |
| | 7. PG LSP200 SHOWS AHU IN CLOSET ON 2ND FL NEXT TO |
| | JANITOR'S CLOSET. PG AC-1 DOES NOT. PLEASE COORDINATE |
| | PLANS. FBC 106.1.1 AND 106.1.3. |
| | |
| | 8. AC-1: PLEASE PROVIDE CALCULATIONS SHOWING HOW THE |
| | VENTILATION REQUIREMENTS OF FRC 303.1 ARE BEING MET FOR |
| | THE RESIDENCE. |
| | |
| | 9. AC-1: ALL A/C CLOSETS SHALL BE LINED WITH A |
| | CONTINUOUS, NON-POPOUS, APPROVED AIR BARRIER AND |
| | EXTERIOR WALLS USED AS A PLENUM SHALL BE INSULATED TO |
| | MIN. R-8 PER FBC,M 603.8 AND 603.9. |
| | |
| | 10. PG AC-1: CONDENSER MOUNTING DETAIL, FBC,M 301.13.1 |
| | ONLY APPLIES TO R-3 OCCUPANCIES AND 5 TONS OR LESS. THE |
| | PRESCRIPTIVE METHOD OF 301.13.1 ONLY APPLIES TO CU-2. |
| | PROVIDE ENGINEERING FOR WIND LOADS AND ATTACHMNENTS FOR |
| | OTHER CU'S PER FBC,M 301.13 AND FBC CH.16. |
| | |
| | 11. AC-1: NOTE #14, CONDENSATE DRAIN LINES SHALL BE OF |
| | NON COMBUSTIBLE MATERIALS PER FBC,M 602.2.1. |
| | |
| | 12. AC-1: PROVIDE DETAIL AND LISTING OF |
| | THROUGH-PENETRATION FIRESTOP SYSTEM FOR LINES |
| | PENETRATING THE RATED STORAGE ROOM PER FBC 712.3. |
| | |
| | IF YOU HAVE ANY QUESTIONS PLEASE CONTACT: |
| | RONALD J. REGUEIRO |
| | 561.805.6719 |
| | [email protected] |
| | |