| 2007-08-22 16:02:14 | REVIEW #: 1 |
| | ACTION: DENIED |
| | |
| | FBC 2004 CODE FAMILY W/ 2005 AND 2006 SUPPLEMENTS |
| | FBC CH.1 AS AMENDED BY THE CITY OF WEST PALM BEACH |
| | |
| | 1. A DESIGN PROFESSIONAL OR AN OWNER MUST ELECT ONE OR |
| | A COMBINATION OF LEVELS OF ALTERATION PURSUANT TO |
| | SECTIONS 303, 304 AND 305 OF FBC, EXISTING BUILDING. |
| | PLEASE INCLUDE THE LEVEL OF ALTERATION IN THE CODE |
| | SUMMARY SECTION OF PG SP-1. |
| | |
| | 2.RENOVATED COMMERCIAL BUILDINGS SHALL, WHEN |
| | APPLICABLE (SEE SECTION 202 OF FBC CH.13), COMPLY WITH |
| | THE PRESCRIPTIVE REQUIREMENTS CONTAINED IN FORM 400C OR |
| | WITH METHOD B OF SUBCHAPTER 13-4 FOR INSULATION, HVAC |
| | SYSTEMS, LIGHTING, WATER HEATING SYSTEMS AND EXTERIOR |
| | ENVELOPE COMPONENTS BEING RETROFITTED OR REPLACED IN |
| | ACCORDANCE WITH FBC 13-101.1.3. PROVIDE ENERGY |
| | CALCULATIONS ON FORM 400B OR 400C SIGNED AND SEALED PER |
| | FBC 13-103.1.1.1. |
| | |
| | 3. DUCT SMOKE DETECTORS SHALL BE CONNECTED TO THE |
| | BUILDING FIRE ALARM SYSTEM PER FBC,M 606.4.1. |
| | |
| | 4. SHOW MEANS AND LOCATION OF CONDENSATE DISPOSAL IN |
| | ACCORDANCE WITH FBC,M 307.2.1 AND FBC 1503.6. |
| | |
| | 5. SHOW MEANS OF AUXILIARY DRAIN PROTECTION FOR RTU'S |
| | PER FBC,M 307.2.3. A WATER LEVEL DETECTION DEVICE |
| | (FLOAT SWITCH) IN THE PRIMARY DRAIN PAN OF THE RTU'S |
| | WILL SATISFY THIS REQUIREMENT. |
| | |
| | 6. PG M-400 VERTICAL AC DETAIL: THIS DETAIL SHOWS A |
| | FLOAT SWITCH ON THE SECONDARY DRAIN OUTLET. THE SUPPLY |
| | AIR UNIT SCHEDULE CALLS FOR AN AUXILIARY DRAIN PAN W/ |
| | FLOAT SWITCH. PLEASE CLARIFY WHICH METHOD IS TO BE USED |
| | OR PROVIDE BOTH. FBC,M 307.2.3 |
| | |
| | 7. PROVIDE A COMPREHENSIVE AIR BALANCE SCHEDULE WHICH |
| | INCLUDES EXHAUST AIR TOTALS TO SHOW THE BUILDING TO BE |
| | PRESSURISED WITH RESPECT TO THE OUTDOORS PER FBC |
| | 13-409.1.ABC.2. |
| | |
| | 8. SHOW BY WHAT MEANS THE OUTDOOR AIR FOR AC-1 AND AC-2 |
| | IS PROVIDED. OUTDOOR AIR INTAKES ARE TO BE LOCATED IN |
| | COMPLIANCE WITH FBC,M 401.5 AND 401.6. |
| | |
| | 9. PG M-100: DUCTS FOR AC-1 AND AC-2 ARE SHOWN |
| | PENETRATING THE 2ND FLOOR SLAB. SHOW HOW THESE OPENINGS |
| | ARE TO BE PROTECTED IN ACCORDANCE WITH FBC,M 607.5. |
| | |
| | 10. PG M-400 RTU DETAIL: THERE IS NO SUCH THING AS |
| | TABLE 1606.1.4 IN THE FLORIDA BUILDING CODE. PROVIDE |
| | COMPLETE DETAIL AND WIND LOAD CALCULATIONS SHOWING HOW |
| | ALL OUTDOOR EQUIPMENT (RTU'S AND CU'S) IS TO BE SECURED |
| | TO MEET WIND LOAD REQUIREMENTS PER FBC,M 301.13 AND FBC |
| | CH.16. |
| | |
| | IF YOU HAVE ANY QUESTIONS PLEASE CONTACT: |
| | RONALD J REGUEIRO |
| | 561.805.6719 |
| | [email protected] |