| 2008-01-10 09:11:02 | PROVISOR: |
| | SHOW THE ACCESSIBLE ROUTE TO THE UNIT MEET THE |
| | REQUIREMENTS OF SECTION 11-4.3.1 |
| | **NEW** FBC 11-4.5.2 CHANGES IN LEVEL GREATER THAN ? |
| | INCH SHALL BE ACCOMPLISHED BY MEANS OF A RAMP THAT |
| | COMPLIES WITH SECTION 11-4.7 OR 11-4.8. SHOW |
| | COMPLIANCE. THIS IS REQUIRED DUE TO THE FACT THAT THERE |
| | ARE STEPS LEADING TO THE ENTRANCE OF THE ROOM. ALL |
| | RAMPS SHALL BE STABLE, FIRM, SLIP RESISTANT, AND SHALL |
| | COMPLY WITH SECTION 11-4.5.LANDINGS AT RAMPS SHALL |
| | MEET THE REQUIREMENTS OF 11-4.8.4 AND 11-4.13.6 SHOW IN |
| | DETAIL DRAWINGS HOW THESE REQUIREMENTS WILL BE |
| | ACCOMPLISHED. |
| | **(A) ALL LANDINGS ON RAMPS SHALL BE NOT LESS THAN 60 |
| | INCHES CLEAR, AND THE BOTTOM OF EACH RAMP SHALL HAVE |
| | NOT LESS THAN 72 INCHES OF STRAIGHT AND LEVEL |
| | CLEARANCE. 11-4.8.4(2) |
| | **(B) IF A RAMP RUN HAS A RISE GREATER THAN 6 INCHES, |
| | THEN IT SHALL HAVE HANDRAILS ON BOTH SIDES. THE |
| | INFORMATION ABOVE SHALL BE CLEARLY INDICATED ON THE |
| | DRAWINGS. THE DRAWINGS SUBMITTED DO NOT SHOW ALL THE |
| | REQUIREMENTS FOR THE RAMP CLEARLY. SUBMIT ELEVATION |
| | DRAWINGS SHOWING THE SLOPE AND RISE, CLEAR WIDTH, |
| | LANDINGS AND HANDRAILS WITH ALL REQUIRED DIMENSIONS. |
| | CONSTRUCTION DOCUMENTS SHALL BE OF SUFFICIENT CLARITY |
| | TO INDICATE THE LOCATION, NATURE AND EXTENT OF THE WORK |
| | PROPOSED AND SHOW IN DETAIL THAT IT WILL CONFORM TO THE |
| | PROVISIONS O THIS CODE. 106.1.1** |
| | NOTE: IF THIS IS A TEMPORARY STURCTURE, IT SHALL |
| | CONFORM TO FBC. SEC 107. WHIC HAS A TIME LIMIT OF 180 |
| | DAYS. |