| 2007-08-08 18:20:10 | REVIEW #: 1ST |
| | ACTION: DENIED |
| | |
| | FBC 2004 CODE FAMILY W/ 2005 AND 2006 AMENDMENTS FBC |
| | CH.1 AS AMENDED BY THE CITY OF WEST PALM BEACH |
| | |
| | 1. M0.2 MECHANICAL EQUIPMENT NOTE #13: DUCT SMOKE |
| | DETECTORS SHALL BE CONNECTED TO THE FIRE ALARM SYSTEM |
| | PER FBC,M 606.4.1. EITHER A SUPERVISORY SIGNAL AT A |
| | CONSTANTLY ATTENDED LOCATION OR ACTIVATION OF THE |
| | BUILDING'S ALARM NOTIFICATION DEVICES IS ACCEPTABBLE |
| | UNDER THIS CODE. HOWEVER, THE DESIGNER SHOULD CHECK |
| | WITH THE WEST PALM BEACH FIRE PREVENTION BUREAU (FIRE |
| | MARSHAL'S OFFICE) TO DETERMINE THEIR REQUIREMENTS FOR |
| | NOTIFICATION UPON ACTIVATION OF THE DETECTORS. |
| | |
| | 2. M0.3: PROVIDE INFORMATION FROM EQUIPMENT |
| | MANUFACTURER SHOWING REQUIRED CLEARANCES OF OUTDOOR |
| | EQUIPMENT FOR SERVICE, MAINTENANCE AND REQUIRED AIRFLOW |
| | FOR EFFICIENT OPERATION. FBC 106.1.2 |
| | |
| | 3. M1.1: KEYED NOTES 2 AND 4, ONLY TWO OF THE FIVE 2ND |
| | FLOOR DUCT PENETRATIONS SHOW FIRE DAMPERS. FIRE DAMPERS |
| | ARE REQUIRED AT ALL DUCT PENETRATIONS OF 2ND FLOOR SLAB |
| | PER FBC,M 607.6. THE SPECIFIC LOCATION OF EACH FIRE |
| | DAMPER SHALL BE SHOWN AND PROPERLY IDENTIFIED ON PLANS |
| | BY THE DESIGNER. FBC,M 607.8 |
| | |
| | 4. M1.1: REFRIGERANT LINES THROUGH 1ST FLOOR SLAB |
| | APPEAR TO PASS THROUGH STRUCTURAL FOOTERS IN TWO |
| | LOCATIONS. PROVIDE DETAIL SHOWING SIZE AND NUMBER OF |
| | SLEEVES GOING THROUGH THE FOOTERS FOR STRUCTURAL |
| | REVIEW. FBC 106.1.2 |
| | |
| | 5. M1.2: REFRIGERANT LINES FROM 1ST FLOOR ARE SHOWN IN |
| | 2 REFIRGERANT CHASES. THE CHASES ARE NOT SHOWN AS FIRE |
| | RATED ON ARCHITECTURAL PLANS. THESE PENETRATIONS SHALL |
| | BE PROTECTED IN A FIRE RESISTANCE RATED ASSEMBLY PER |
| | FBC 712.4.1.1 OR PROTECTED BY AN APPROVED THROUGH |
| | PENETRATION FIRESTOP SYSTEM PER FBC 712.4.1.2. PROVIDE |
| | DETAIL AND TYPE OF ASSEMBLY TO BE USED. |
| | |
| | 6.PROVIDE SUBMITTALS/INSTRUCTIONS FOR TITUS BYPASS |
| | TERMINALS. |
| | |
| | 7. M1.2: KEY NOTE #9, THE 12X12 DUCT FROM 1ST FLOOR TO |
| | ROOF NEAR 2AHU-10 APPEARS TO PASS THROUGH THE 18X12 |
| | RETURN DUCT. THESE DUCTS DO NOT LOOK LIKE THEY ARE |
| | INTENDED TO BE CONNECTED, BUT THAT'S HOW THEY APPEAR ON |
| | FLOOR PLAN. PLEASE CLARIFY. |
| | |
| | 8. M7.1 DETAIL 7: FIRE DAMPERS LOCATED WITHIN AIR |
| | DISTRIBUTION SYSTEMS SHALL BE INSTALLED IN ACCORDANCE |
| | WITH THE REQUIREMENTS OF THIS SECTION, AND THE |
| | MANUFACTURER?S INSTALLATION INSTRUCTIONS AND LISTING |
| | PER FBC,M 607.2. IF THIS DETAIL IS NOT FROM THE |
| | MANUFACTURER, IT IS NOT ACCEPTABLE AND THE |
| | MANUFACTURER'S INSTALLATION INSTRUCTIONS MUST BE |
| | PROVIDED. |
| | |
| | 9. M7.2 DETAIL 3: SHOW CONDENSING UNIT ATTACHMENT TO BE |
| | DESIGNED FOR THE 140 MPH WIND ZONE PER FBC,M 301.13 AND |
| | FBC CH.16 |
| | |
| | 10. ENERGY CALCULATIONS: PROJECT SUMMARY INDICATES MAX |
| | TONNAGE AT 3.4. THE LARGEST SYSTEM SHOWN ON PLANS IS 5 |
| | TONS. ALSO, THE OWNER'S NAME AND THE ADDRESS OF THE |
| | PROJECT ARE MISSING. PLEASE CORRECT. |
| | |
| | 11. ENERGY CALCULATIONS: FORM 400A HAS BEEN USED FOR |
| | THIS BUILDING. HOWEVER, EITHER METHOD B OR C SHALL BE |
| | USED. PLEASE SEE THE FOLLOWING REQUIREMENTS FOR ENERGY |
| | CALCULATIONS FOR SHELL BUILDINGS: |
| | "NONRESIDENTIAL BUILDINGS THAT ARE PERMITTED PRIOR TO |
| | DESIGN COMPLETION OR WHICH WILL BE FINISHED IN SECTIONS |
| | AT A TIME AFTER CONSTRUCTION OF THE SHELL SHALL COMPLY |
| | WITH EITHER METHOD B OR C OF SUBCHAPTER 13-4 OF THE |
| | CODE PRIOR TO GRANTING OF A PERMIT TO BUILD. ALL |
| | ASSUMPTIONS MADE ABOUT FEATURES NOT INSTALLED UNTIL |
| | LATER THAT ARE NOT ON THE BUILDING PLANS SHALL BE |
| | LISTED AND APPENDED TO THE COMPLIANCE FORM SUBMITTED TO |
| | THE BUILDING DEPARTMENT. UNLESS THE BUILDING IS |
| | COMPLETED AS PER ALL ASSUMPTIONS MADE IN THE ORIGINAL |
| | CODE COMPLIANCE SUBMITTAL, A REVISED CODE SUBMITTAL(S) |
| | USING METHODS A, B OR C SHALL BE SUBMITTED WHEN |
| | COMPLETION OF THE BUILDING (OR PART OF THE BUILDING) IS |
| | PERMITTED." FBC 13-101.1.6 |
| | |
| | 12. PROVIDE AN AIR BALANCE SCHEDULE FOR THE SPACES |
| | BEING CONDITIONED TO ASSURE THAT THE BUILDING IS |
| | PRESSURIZED WITH RESPECT TO THE OUTDOORS. FBC |
| | 13-409.1.ABC.2 |
| | |
| | 13. PROVIDE SHUTOFF DAMPER CONTROLS THAT WILL |
| | AUTOMATICALLY SHUT WHEN SYSTEMS OR SPACES SERVED ARE |
| | NOT IN USE. FBC 13-409.1.ABC.3.3 |
| | |
| | 14. PROVIDE ALL RELEVANT SUBMITTAL DATA FOR THE |
| | PROPOSED GENERATOR, INCLUDING INFORMATION ON FUEL |
| | STORAGE TANK TO BE USED. |
| | NOTE: GENERATORS ARE TO BE INSTALLED IN CONPLIANCE WITH |
| | NFPA 37-02. FUEL GAS PERMIT AND PBC DERM APPROVAL MAY |
| | BE REQUIRED. |
| | |
| | IF YOU HAVE ANY QUESTIONS PLEASE CONTACT: |
| | RONALD J REGUEIRO |
| | 561.805.6719 |
| | [email protected] |