| 2009-10-10 10:00:48 | |
| | |
| | ** DENIED REVIEW ** |
| | **ORIGINALLY SUBMITTED 8/13 AND PLACED ON HOLD FOR |
| | ELECTRICAL REVIEW AS NEW REVISED SHEETS NEEDED TO BE |
| | INSERTED INTO SETS BEFORE REVIEW. |
| | OTHER REVISED TRADE SHEETS WERE ALSO INCLUDED WHEN |
| | SHEETS WERE INSERTED WHICH ARE DATED AFTER ORIGINAL |
| | SUBMITTED DATE. THERE WERE ALSO NEW REVISED PLUMBING |
| | SHEETS INSERTED AFTER THE PLUMBING REVIEW WAS DONE. NEW |
| | SHEETS ALSO INSERTED THIS WEEK FOR ZONING. |
| | ORIGINALLY SUBMITTED AS 28 REVISED SHEETS THERE IS NOW |
| | A TOTAL OF 47 REVISED SHEETS IN EACH SET. INCLUDING |
| | FIVE REVISED PLUMBING REVISED SHEETS. ADDITIONAL FEE |
| | FOR REVISED SHEETS WILL BE DUE. |
| | |
| | 1) NOTE: AS NOTED PREVIOUSLY. THE SAME ENERGY |
| | CALCULATIONS AS PREVIOUSLY SUBMITTED ARE NOT REVISED |
| | AND ARE THE SAME AS SUBMITTED. |
| | |
| | ** PREVIOUS NOTES** |
| | ENERGY CALCULATIONS NOT STAMPED FOR ELECTRIC. AS STATED |
| | ON PREVIOUS REVIEWS. ALL SYSTEMS AND COMPONENTS IN THE |
| | BUILDING AND ON SAID PLANS NEED TO COORDINATE WITH THE |
| | INPUT DATA REPORT. AN EXAMPLE IS TAKING A CREDIT FOR |
| | ALL ROOMS AND SPACES IN BUILDING TO CONTAIN * CARPET |
| | AND RUBBER PADDING*. THE FACT THERE IS NUMEROUS AREAS |
| | AND LOCATIONS WITHIN BUILDING WHICH DO NOT CONTAIN THIS |
| | TYPE OF FLOORING. THERE ARE ALSO ROOMS AND OTHER AREAS |
| | SUCH AS ELECTRICAL ROOMS, MECHANICAL ROOMS, SURGERY |
| | ROOMS, STORAGE ROOMS ETC WHICH WILL NOT HAVE ANY CARPET |
| | AND RUBBER PADDING. |
| | SEE COMMENTS FROM OTHER TRADES. SEE FBC CHAPTER 13 AS |
| | THE SUBMITTED CALCULATIONS DO NOT MEET THE MINIMUM OF |
| | THE FLORIDA BUILDING CODE IN CHAPTER 13. |
| | |
| | 2) NOTE: REVISED PLANS SUBMITTED REMOVING PHASE TWO |
| | SCOPE OF WORK HOWEVER REVISED CIRCUITING, LOADS AND |
| | PANEL SCHEDULES WERE NOT SUBMITTED OR REVISED FOR AREAS |
| | WHICH ARE IN THE PHASE ONE SCOPE OF WORK. THERE ARE |
| | SEVERAL AREAS WHICH OVER LAP FOR THE ABOVE CIRCUITING |
| | ETC. |
| | PLEASE SUBMIT REVISED PANEL SCHEDULES PER 408.4 REVISED |
| | PANEL SCHEDULES WERE NOT SUBMITTED AS PART OF PHASE TWO |
| | SCOPE OF WORK. |
| | PLEASE REVISE CIRCUITING AND LOADS PER NEC 220, |
| | 220.12,220.14, 220.42 ETC |
| | |
| | |
| | |
| | IF THERE ARE ANY QUESTIONS; OR IF COMMENTS ARE NOT |
| | TYPED IN A CLEAR MANNER PLEASE DO NOT HESITATE TO |
| | CONTACT THIS REVIEWER. |
| | |
| | DEWEY PALMER |
| | ELECTRICAL PLAN REVIEW II |
| | CONSTRUCTION SERVICES DEPARTMENT |
| | CITY OF WEST PALM BEACH |
| | 561-805-6717 |
| | [email protected] |
| | |